Abstract
Keywords:
1. Introduction
2. Materials and Methods
Description of the Study Area
3. Methodology
Data Collection
Data Analysis
- ➢ Null Hypothesis (H0): There is no monotonic trend in the time series
- ➢ Alternative hypothesis (HA): There is a monotonic trend in the time series
4. Results and Discussion
Descriptive Analysis
Trend and Rate of Changes in Percentage Cost Over Runs
Summary, Conclusions, and Recommendations
Funding
Conflicts of Interest
References
- L. G. Berihu, B. Grum, Z. Tariku, and B. A. Abebe, “Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia,” Advances in Civil Engineering, vol. 2023, pp. 1–19, May 2023. [CrossRef]
- A.O. Daoud, M. El Hefnawy, and H. Wefki, “Investigation of critical factors affecting cost overruns and delays in Egyptian mega construction projects,” Alexandria Engineering Journal, vol. 83, pp. 326–334, Nov. 2023. [CrossRef]
- Y. F. Kassa, “Determinants of Infrastructure Project Delays and Cost Escalations: The Cases of Federal Road and Railway Construction Projects in Ethiopia,” vol. 63, no. 1, 2020.
- A.M. Kuhil and N. Seifu, “Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration, Ethiopia,” AJMS, vol. 8, no. 2, pp. 4–9, May 2019. [CrossRef]
- G. Taye, “Simulation Modeling of Cost Overrun in Construction Project in Ethiopia,” IJRTE, vol. 8, no. 4, pp. 12685–12691, Nov. 2019. [CrossRef]
- A. Shiferaw Belachew, “Causes of Cost Overrun in Federal Road Projects of Ethiopia in Case of Southern District,” AJCE, vol. 5, no. 1, p. 27, 2017. [CrossRef]
- N. S. Dusso and T. W. Bayeh, “The Causes and Effects of Delay of Building Construction in Ethiopia, Southern Nation Nationalities of People Region in Gurage Zone (Case of Wolkite Town),” CER, Jan. 2020. [CrossRef]
- S. Getaneh and M. Kansal, “Pandemic Construction Delay and Cost Overrun Analysis in Water Resource Project,” vol. 12, 2022.
- T. Gebrehiwet and H. Luo, “Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study,” Procedia Engineering, vol. 196, pp. 366–374, 2017. [CrossRef]
- A.A. Seman, H. M. S. Ahmed, A. Ahmed, and A. A. Haso, “Causes and Effects of Project Delay in Public Construction Projects in Ethiopia,” In Review, preprint, Mar. 2023. [CrossRef]
- R. Susanti, “Cost overrun and time delay of construction project in Indonesia,” J. Phys.: Conf. Ser., vol. 1444, no. 1, p. 012050, Jan. 2020. [CrossRef]
- A.T. Tessema, G. A. Alene, and N. M. Wolelaw, “Evaluating Delay Factors on Road Construction Projects in Ethiopia Using Relative Importance Index Method,” vol. 13, no. 01, 2023.
- S. A. Mutairi, “Analysis of Delays during Initial Phase of Construction Projects and Mitigation Measures,” International Journal of Economics and Management Engineering, vol. 11, no. 3, 2017.
- A. Narayan Shete and V., D. Kothawade, “An Analysis of Cost Overruns and Time Overruns of Construction Projects in India,” IJETT, vol. 41, no. 1, pp. 33–36, Nov. 2016. [CrossRef]
- S. Melaku Belay, S. Tilahun, M. Yehualaw, J. Matos, H. Sousa, and E. T. Workneh, “Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia,” Advances in Civil Engineering, vol. 2021, pp. 1–15, Nov. 2021. [CrossRef]
- Dire Dawa City Administration, “DireDawa_GHG Emissions Inventory Report V8.pdf,” Dire Dawa, 2022. Accessed: Dec. 04, 2024. [Online]. Available: https://www.epa.gov.et/images/PDF/Climatechange/DireDawa_GHG%20Emissions%20Inventory%20Report%20V8.pdf.
- P. J. Keane and A. F. Caletka, “Delay Analysis in Construction Contracts”.
- L. Ye, J. Zhou, X. Zeng, and M. Tayyab, “Hydrological Mann-Kendal Multivariate Trends Analysis in the Upper Yangtze River Basin,” Journal of Geoscience and Environment Protection, vol. 03, no. 10, pp. 34–39, 2015. [CrossRef]
- T. Pohlert, “Trend: Non-Parametric Trend Tests and Change-Point Detection,” The R Project for Statistical Computing, Vienna, Austria, Jul. 2018. Accessed: Mar. 04, 2019. [Online]. Available: https://CRAN.R-project.org/package=trend.






| Time Series | Z | P-Value | Sen Slope (%/Year) |
|---|---|---|---|
| 2008 -2024 | -0.45 | 0.651 | - |
| 2008 -2016 | -0.73 | 0.465 | - |
| 2017 -2024 | 0 | 1 | - |
| Time Series | Z | P-Value | Sen Slope (%/Year) |
|---|---|---|---|
| 2008 -2024 | 2.68 | 0.007 | 200 |
| 2008 -2016 | -0.73 | 0.465 | - |
| 2017 -2024 | -0.12 | 0.902 | - |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |