Submitted:
07 August 2025
Posted:
08 August 2025
You are already at the latest version
Abstract

Keywords:
1. Introduction
- The target of the modelling process, described in detail in the present study, allows professionals to understand the main advantages of BIM adoption, concerning the level of collaboration and the integration capacity between all disciplines. In the context of the application of BIM over the selected study case, the elaboration of the architectural project was first conceived, followed by the modelling of the structural solution and of the water and electricity networks. These components composes the 3D BIM model (item 4);
- In addition, the study put in evidence, the facility of obtaining the quantification of the material applied in distinct project components. This is a relevant task easily developed over the 3D model composed of all the disciplines, named the 4D BIM model. Following this perspective, the study demonstrates how the aspects of collaboration and budgeting, are tasks that can be elaborated in an agile, correct and complete, using a multidisciplinary 3D BIM model with a high level of detail and additional information incorporated (item 5);
- In the establishment of the construction planning activity, concerning the generation of the 5D BIM model, it was necessary to increase the information of the initial 3D BIM model. Namely, in relation to the identification of construction tasks and the calculation of the respective execution period. The association of data related to unit costs constitutes a complementary information that was added to the parametric objects used on the creation of the 3D model. As so, the required information for this activity was added, and this feature should be understood as a benefit and not a limitation [12]. The database of a complete 3D model, composed of tasks and unity costs, is insufficient to obtain correct 4D and 5D models (item 6).
- The present research also explores the association and integration of BIM with VR technology illustrating the improvement of the BIM methodology when incremented with VR functionalities. Two VR/AR software were used to support and review the design, improving stakeholder engagement by giving design teams the ability to present a realistic representation of a design in a early stage of its development (item 7).
2. Materials and Methods
- Collaboration between professionals from different disciplines can be strongly boosted with the generation of all components of the 3D BIM model, related to each field, and eventually developed by distinct professionals or located in remote locations, constituting a fundamental characteristic of BIM, but which in current practice is not yet sufficiently applied [13]. The 3D BIM model generated within the present study is composed of architecture, structures, water network and electrical system disciplines;
- In the context of the activity inherent to the industry, there is still a lack of some dissemination aimed at the potential of BIM in the construction planning process, with the possibility of simulating the animated visualization of the planed work, allowing users to compare the planned construction with the real one on site [14]. The design elaborated in this context is normally named the 4D BIM model;
- In addition, there is still some resistance to the understanding that a complete 3D BIM model, in terms of information associated with each project component, can constitute an appropriate database for the development of detailed budgets by discipline, component or construction zone [15]. This activity, known as the 5D BIM model, requires the elaboration of the quantity take-off activity and the insertion of the unity cost as new parameter of the objects applied in the model;
- The use of VR and AR systems in construction has been applied mainly in the design visualization and collaboration, but the development of more advanced technologies and the falling costs of VR/AR hardware have made it more accessible and widely adopted by the construction industry [16]. There are many benefits in using virtual reality in construction, including the ability to streamline project planning and coordination, facilitate project visualization, enhancing asset management and improving quality control. The present study links BIM and VR/AR.
3. Concepts and Technological Evolution of BIM and VR
3.1. Building Information Modeling (BIM)
3.2. Virtual Reality
4.1. Architectural Component
- The exterior wall was defined with the required layers composed of different material and thickness (porcelain stoneware tile, mortar, stucco, 11cm brick, extruded polystyrene (XPS), air box, 15cm brick and plaster);
- Three type of interior walls were considered: 15cm thick (11cm brick panel covered with stoneware tile); 25cm thick, shared by the toilets and other divisions (7cm and 11cm brick panels with plaster coatings and ceramic elements); 21cm thick, shared by the two toilets (double brick panel of 11cm and 7cm, with rock wool insulation).
4.2. Structural Component
4.3. Water Supply System
- For the cold water, the interior plumbing was considered to have a coating greater than 2cm, and is not embedded either inside the structural elements or the floor slabs with a structural function. For the modelling of the hot water network, it was developed in parallel to the cold water pipes in a higher plane at a distance of not less than 5cm (Figure 8 a).
- The modelling of the piping network for water drainage the process is very similar to the design of the model for water distribution networks. As indicated in the project provided, the material applied corresponds to polyvinyl chloride (PVC). This material was created in Revit as a new material, and the properly established graphical appearance and associated properties were queried from the related product catalog (Figure 8 b).
4.4. Electric System
5.1. Identification of Activities and Duration
- Concreting the floor slab of the 1st floor corresponds to a man-hour rate of 1.25/m3, a rate that is then multiplied by the concrete volume of 2.6m3, a value obtained through the capacities of Revit. The result value is divided by the two workers, having been obtained the 1.60h (Table 1);
- The reinforcements work requires the cutting, the folding, the framing and the placement of arms in the place, inside the formwork of each structural element. The productivity associated with bars of diameter 10mm and 12 mm is distinct. The man-hour rate for the reinforcement is quantified per 10kg of steel and as so it was necessary to estimate the weight of all the reinforcements. It was obtained a total weight of 212.5kg and 118.8kg for the bars of diameter 10mm and 12mm, respectively, corresponding to 3.35h and 1.68h of work;
- The period of placing the formwork, forming the slabs, columns and beams, was also calculated. A hydraulic mortar was placed at the base of the cladding with a finish by gluing or cementing. The porcelain stoneware boards carried out by cementing and gluing thin stoneware tiles were applied;
- When building the columns, it was considered the application of concrete with normal consistency and the cutting, bending, framing and application of the steel bars of diameter 16mm, 12mm and 6mm. The execution of beams considered the activity of concreting, the bars preparation and placing the steel bars of diameter 20mm, 16mm, 12mm, 8mm and 6mm. Finally, the execution periods related to the roof and floor were calculated, considered as a reinforced concrete slabs, with the application of 10mm and 12mm steel bars;
- The short wall defined outlined the terrace considered the period of the formwork application, the preparation of bars of 6mm and 8mm diameter bars and concreting;
- In relation to the exterior wall, placing two brick panels, an intermediate thermal insulation board and the execution of the exterior and interior plastering were considered. In the process, the tasks of masters, projection and tightening, battening, repair and a 2nd batten for the execution of the wall were considered. Inside, the wall was covered by cementing or gluing ceramic tiles. The result of the calculations is listed in the Table 2. For the interior walls, the period of execution of the three types of walls was also quantified;
- The activity associated with the plumbing work consists of: opening cracks in the brick masonry walls, laying pipes and closing the holes; temporary safety of concrete pipes laid on the floor; placing the pipes with plastic fittings in concrete clamps. The man-hour rate of this activity was calculated on a per-m² basis. The man-hour rate is dependent on the quantity and type of the elements. The time of the installation of the sanitary equipment, with the connection of three washbasins, a bidet, two toilets, two showers and a bathtub was then calculated;
- Considering the electrical system, it was obtained the time involved in connection and assembly activities of switches and single-phase sockets, both of which are placed inside;
- Finally, the doors and windows were placed in the walls. The laying is carried out with dowels of diameter from 7mm to 9mm, with 25mm length. Each span bordering was completed with masonry material. For the installation of the elements, shoring, fastening, application of sealants, assembly and adjustment were considered.
- This condition allows the user to select groups of elements, whose category corresponds to a zone or type of component, in a semi-automatic way to be associated with an activity;
- For other activities, it was necessary to manually select the desired elements, by clicking over the model elements, as was the case of the different type of walls, because they are executed at different times;
- In addition, the category related to piping, requires separation of elements of the water distribution and the drainage system. Two conditions were created, one referring to System Type with elements associated with the Piping Systems category, the piping system, and the category Plumbing Fixtures, which considers only sanitary devices. Both present execution tasks with distinct temporal action.
- The table of quantities referring the structural elements, comprised the concrete volume and the steel weight of diameters associated to each elements (columns, beams, floor slab and roof slab);
- The quantity take-off table for the water distribution systems, includes the piping type and extension, accessories and devices. Each list includes the distribution of water and sewage and information regarding the type of system, cross-section diameter, length, main material and secondary material;
- The quantity table of the electricity project was obtained for the lighting devices, namely the light switches, the lighting accessories (lamps) and the electricity accessories (sockets).
- In relation to the reinforced concrete columns, the cost estimated considers the dimensions of the cross-section of 20x20cm² and 20x40cm², a ceiling height of 3.0m, the wooden formwork, the metal elements struts, the concrete prepared on site and the concreting work. It was obtained a value of €853.06/m³ and €735.21/m³, for each type of column.
- The costs of the water supply pipe were assigned to each nominal diameter. For the multilayer pipes the polyethylene/aluminum/polyethylene material was considered (Table 3).
- The cost of the PVC drainage pipe system was also established associated with each type of diameter. The quantity elements is obtained automatically in the form of tables. The unit cost by diameter was assigned to each pipe type and the total of costs was obtained (Table 4);
- The present work involved several procedures in the field of BIM, from modelling to cost estimation. However, in the construction context, there is still a lack of disclosure aimed at the potential of BIM in the construction planning process, with the possibility of presenting a visual simulation of the work progress and comparing it real progress on site.
7. VR and AR Application
7.1. VR Software
- The Fuzor software allows the engineer to simulate the construction planning. Thus, it is possible to observe the progress of the work in loco and find out how the construction will take place through a virtual environment. Using this application, the management of materials and labor in the local is facilitated [30];
- For a more collaborative purposes, the Arkio software is a suitable VR application. This is frequently applied on the development of conceptual models visualized in a virtual environment, as it allows several users to participate simultaneously in the same project. This software contains modeling tools such as creating volumes, voids, changing colors or textures [31];
- The Unity software is other system developed by a enterprise focused on the gaming industry. This application allows user to develop immersive 3D environments, to select pre-made projects and to adjust it to new 3D models [32];
- The SentioVR software is a plug-in of Revit. It is not necessary to install external software in Revit, facilitating its integration and avoiding inefficient interoperability. This allows users to observe the virtual model and the collaboration between members [33];
- The Enscape software is other plug-in of Revit. It can be installed directly in Revit, allowing the user to visualize the model, giving the opportunity to demonstrate it to the client and other professionals and assist an elevated degree of communication among them [34];
- The Unreal Engine software, developed by the company Epic Games, is oriented towards the design of interactive games, created in 3D environments and with a high capacity for immersion and interaction. Although the company's main focus is on the entertainment sector, the software has been explored in other industries, such as the presentation of architectural projects or the simulation of car traffic and transport [35]. This software was applied in the present study considering the VR facility;
- AUGmenture system is an Augmented Reality (AR) software. Using a 3D geometric model, previously created, it is possible to observe the model as a mock-up from smartphones or tablets. It is frequently used as a collaborative tool supporting the discussion of ideas and alternative design solutions [36]. This software was also applied in the present study considering the AR facility.
7.2. BIM/VR Experience
7.3. BIM/AR Experience
8. Discussion and Conclusions
- The applied modelling process for the different disciplines, allowed to generate all the components of the 3D BIM model with a rigorous detail in form and dimensions, in materials and physical properties, and in other type of information such as the supplier, the selected model or the manufacturer's website. The complete model is a valuable database for the integration of design steps, the collaboration within the team and the support to the development of complementary tasks;
- The development of construction planning requires the association of data to the 3D model, in order to create the respective 4D BIM model. This task required the identification of all the construction activities and the calculation of each period of execution. When compared to the traditional way of performing this task, over the digital drawings of each design, the manipulation of the 3D model is manifestly more agile, since the work of grouping elements and their association with activities and respective period of execution, is more direct than the measurement and identification of components over the drawing;
- The costs estimation (5D BIM model) is a task that must be performed rigorously over the 3D BIM model. The option of adding information throughout the development of the project and the elaboration of complementary tasks, such as budgeting, is a feature that is not yet properly recognized by construction professionals. All unit costs can be associated with the model by assigning them to specific parameters of the objects used in the modeling process;
- The tables of quantities associated with costs are an adequate support for the collaboration between professionals and the understanding with the promoters, allowing to easily obtain updated tables after any change made in the project, as all tables have a dynamic character. The comparison of solutions from any of the modeled disciplines can be easily studied based on the 3D model and respective dynamic tables of quantities and costs;
- The visualization of the model using VR systems allows to achieve a realist perception of feasibility on site, helping with aesthetic and functional decisions as well as ergonomic issues. It is possible, in an immersive way, to move within the model, make changes, take dimensions and place annotations for future modifications;
- Both VR and AR systems can be applied in any stage of development of the multidisciplinary project and construction phases of the 4D model. The perception of the evolution of the project and construction is improved with the application of VR/AR systems on the 3D BIM model and on the 4D model. Collaboration and communication between partners and the resolution of conflicts. In addition, the eventual errors are better-understood visulix8zed in a VR environment. After the errors can be resolved by manipulating the BIM model.
Author Contributions
Funding
Conflicts of Interest
References
- Al-Mohammad, M.S.; Haron, A.; Esa, M.; Aloko, M.N.; Alhammadi, Y.; Anandh, K.S.; Rahman, R.A. Factors affecting BIM implementation: evidence from countries with different income levels. Constr. Innov. 2022, 23, 683–710. [Google Scholar] [CrossRef]
- Haggard, K.E. Case Study on Virtual Reality in Construction. 2017. https://core.ac.uk/download/pdf/84280005.pdf.
- Sampaio, A.Z.; Gomes, A.M. Professional one-day training course in BIM: a practice overview of multi-applicability in Construction. J. softw. eng. appl, /: 15. https.
- Sacks, R.; Eastman, C.; Lee, G.; Teicholz, P. BIM handbook: A guide to Building Information Modeling for owners, managers, designers, engineers and contractors, 3rd ed., New Jersey: John Wiley & Sons, Inc. 2018, SBN: 978-1-119-28753-7.
- Sampaio, A.Z. Enhancing BIM Methodology with VR Technology, book: State of the Art Virtual Reality and Augmented Reality Knowhow, N. Mohamudally, Ed., Rijeka, IntechOpen, 2018. [CrossRef]
- Succar, B. Building information modelling framework: a research and delivery foundation for industry stakeholders. Automat. Constr 2008, 18, 357–375. [Google Scholar] [CrossRef]
- Smith, P. BIM Implementation: global strategies. Procedia Eng. 2014, 85, 482–492. [Google Scholar] [CrossRef]
- Charef, R.; Emmitt, S.; Alaka, H.A. Beyond the third dimension of BIM: a systematic review of literature and assessment of professional views. J. Build. Eng. 2018, 19, 242–257. [Google Scholar] [CrossRef]
- Ingram, J. Understanding BIM: the past, present and future. 2020, 1st ed.. https://www.routledge. 9780. [Google Scholar]
- Sacks, R.; Wang, Z.; Ouyang, B.; Utkucu, D. , Chen, S. Toward artificially intelligent a cloud-based building information modelling for collaborative multidisciplinary design. Adv. Eng. Inform. [CrossRef]
- Sarmento, R. S. BIM implementation in the development of the multidisciplinary project: 4D and 5D models and VR integration. MSc thesis in Construction 2023, Lisbon, Portugal. [Google Scholar]
- Teng, Y.; Xu, J.; Pan, W.; Zhang, Y. A systematic review of the integration of building information modelling into life cycle assessment. Buil. Environ. 2022, 221. [Google Scholar] [CrossRef]
- Sanchez-Lite, A.; Zulueta, P.; Sampaio, A.Z.; Gonzalez-Gaya, C. BIM for the Realization of Sustainable Digital Models in a University-Business Collaborative Learning Environment: Assessment of Use and Students’ Perception. Buildings 2022, 12. [Google Scholar] [CrossRef]
- Wang, J.; Wang, X.; Shou, W.; Chong, H.Y.; Guo, J. Building information modeling-based integration of MEP layout designs and constructability. Autom. Constr. 2016, 61, 134–146. [Google Scholar] [CrossRef]
- Salzano, A.; Miano, A.; Prota, A.; Jacobsson, R. The use of the BIM approach from the conceptual planning to the construction phase: the case study of the SHiP Experiment. Designs 2022, 6, 48. [Google Scholar] [CrossRef]
- Yu, X.; Yu, P.; Wang, C.; Wang, D.; Shi, W.; Shou, W.; Wang, J.; Wang, X. Integrating Virtual Reality and Building Information Modeling for improving highway tunnel emergency response training. Buildings 2022, 12, 1523. [Google Scholar] [CrossRef]
- Terreno, S.; Anumba, C.J.; Gannon, E.; Dubler, C. The Benefits of BIM Integration with Facilities Management: A Preliminary Case Study. Computing in Civil Engineering 2015. [CrossRef]
- Azhar, S. Building information modelling (BIM): trends, benefits, risks, and challenges for the AEC industry. Leadersh. Manag. Eng. 2011, 11, 241–252. [Google Scholar] [CrossRef]
- Eastman, C.M. The use of computers instead of drawings in building design. AIA J. /: 46–50, Reports on research at Carnegie-Mellon University. https, 1142; 50. [Google Scholar]
- Wong, K.W.; Zhou, J. Enhancing environmental sustainability over building life-cycles through green BIM: A review. Automat. Constr 2015, 57, 156–165. [Google Scholar] [CrossRef]
- Sampaio, A.Z. Maturity of BIM implementation in the construction industry: Governmental Policies. Int. J. Eng. Technol. 2021, 69, 92–100. [Google Scholar] [CrossRef]
- Shehzad, H.M.; Ibrahim, R.B.; Yusof, A.F.; Khaidzir, K.A. Building information modelling: factors affecting the adoption in the AEC industry. 2019; -6. [Google Scholar] [CrossRef]
- Birkemo, A.S. , Hjortland, S.C., Samarakoon, M.S. Improvements for the workflow interoperability between BIM and FEM tools. WIT Trans. Built Environ. 2019, 192, 317–327. [Google Scholar] [CrossRef]
- Gomes, A.M.; Sampaio, A.Z.; Azevedo, G.; Sanchez-Lite, A. BIM in structural project: Interoperability analyses and data management. Appl. Sci. 2023, 12, 8814. [Google Scholar] [CrossRef]
- Gigante, M.A. Virtual Reality: definitions, history and applications, Virtual Reality Systems. Academic Press, 1993, 3-14. [CrossRef]
- Interrante, V.; Höllerer, T.; Lécuyer, A. Virtual and Augmented Reality. IEEE Comput. Graph. Appl. 2018, 38, 28–30. [Google Scholar] [CrossRef]
- Johansson, M.; Roupé, M. Real-world applications of BIM and immersive VR in construction. Autom. Constr. 2024, 158, 105233. [Google Scholar] [CrossRef]
- Revit (Autodesk) https://www.autodesk.com/.
- EPAL's Building Networks Manual, (in portuguese). 2023, EPAL documentation, Lisbon, Portugal.
- Fuzor. https://www.kalloctech.
- Arkio. https://www.arkio.
- Unity. https://unity.
- SentioVR. https://www.sentiovr.
- Enscape. https://enscape3d.
- Unreal Engine. https://www.unrealengine.
- AUGmenture. https://www.augmentecture.
- Tang, S.; Shelden, D.R.; Eastman, C.M.; Bozorgi, P.P.; Gao, X. A review of building information modeling (BIM) and the internet of things (IoT) devices integration: Present status and future trends. Automat. Constr. 2019, 101, 127–139. [Google Scholar] [CrossRef]
- Koutamanis, A. Dimensionality in BIM: why BIM cannot have more than four dimensions? Automat. Constr. 2020, 114, 103153. [Google Scholar] [CrossRef]
- Schley, M.; Haines, B.; Roperm, K.; Williams, B. BIM for facility management, Version 2.1. 2016. https://it.ifma.org/wp-content/uploads/2019/04/BIM-FM-Consortium-BIM-Guide-v2_1.
- Mahmoud, E.; Marcus, J.; Peter, D. , Moe, M., Implementation of Building Information Modelling in infrastructure construction projects: a study of dimensions and strategies. Int. J. Inf. Syst. Proj. Manag. 2021, 9, 43–59. [Google Scholar] [CrossRef]














| Activity | Quantity m-h/uni. | Unity | Men | Quantity | Uni. | Hours |
| Concreting | 1.250 | m.h/m³ | 2 | 2.6 | m³ | 2 |
| Armor (D10 mm) | 0.315 | m.h/10kg | 2 | 212.5 | kg | 3 |
| Armor (D12 mm) | 0.283 | m.h/10kg | 2 | 118.8 | kg | 2 |
| Formwork | 2.500 | m.h/m² | 2 | 16.0 | m² | 20 |
| Shape layer application | 1.550 | m.h/m² | 2 | 16.0 | m² | 12 |
| Application of screed | 0.940 | m.h/m² | 2 | 16.0 | m² | 8 |
| Laying porcelain stoneware | 1.390 | m.h/m² | 2 | 16.0 | m² | 11 |
| Total | 58 |
| Activity | Quantity (m-h/m2) | Men | Quantity (m2) | Hours |
| Execution of 15cm brick masonry | 2.215 | 2 | 16 | 17.7 |
| Execution of 11cm brick masonry | 2.923 | 2 | 16 | 23.4 |
| Paint application | 0.400 | 2 | 16 | 3.2 |
| Laying thermal insulation | 0.400 | 2 | 16 | 3.2 |
| Plastering application | 2.440 | 2 | 16 | 19.5 |
| Laying porcelain stoneware | 0.900 | 2 | 16 | 7.2 |
| Total | 73.2 |
| Diameter (mm) | Quantity (m) | Unit cost (€/m) | Total cost (€) |
| D16 | 7,47 | 3,22 | 24,05 |
| D20 | 17,66 | 4,18 | 73,82 |
| D25 | 3,95 | 6,22 | 24,57 |
| Total | 122,44 |
| Diameter (mm) | Quantity (m) | Unit cost (€/m) | Total cost (€) |
| D32 | 2 | 5,06 | 10,12 |
| D40 | 2,2 | 5,69 | 12,52 |
| D50 | 1,26 | 6,73 | 8,48 |
| D75 | 1,54 | 8,22 | 12,66 |
| D90 | 2,24 | 10,02 | 22,44 |
| D110 | 0,99 | 12,6 | 12,47 |
| Total | 78,70 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).