1. Introduction
Spun piles are widely used in Indonesia for bridge and wharf foundations. The piles have been produced with limited confinement below the minimum standards since it is design based on elastic concept where the damages are inhibited. The design code (SNI 8460:2017) for sub-structures still adopted elastic method. However, in term of concrete pile detailing, it refers to upper structure code (SNI 2847:19/ACI 318:2019) where at potential plastic hinge, confinement should be fulfilled. Hence, the spun pile and pile cap connection requires adequate confinement, as it experiences the highest curvature. Post-severe-earthquake observations have reported several damages occurring in the pile close to the pile [
1]. Therefore, the spun pile at this location must be equipped with adequate confinement. Since it refers to two different standards with different concepts, the requirement for confinement in spun piles in Indonesia is not strictly enforced. As a result, spun piles with low confinement have been widely used in bridges and pier infrastructures across Indonesia.
Recent seismic hazard assessments indicate an increase in seismic acceleration across many regions of Indonesia. Allowing inelastic behaviour to piles in the future becomes a real concern when a major earthquake occurs. This highlights the need to implement performance based design for substructures. Therefore, ensuring adequate confinement in spun pile connections becomes essential. Confinement plays a crucial role in restraining concrete, allowing it to develop fcc’, which enables the structure to sustain large displacement during a major earthquake. The provision of confinement in the plastic hinge area should correlate with the ductility of the structure and its energy dissipation capacity during an earthquake.
Several studies have been conducted in Indonesia to investigate the behavior of spun piles with limited confinement [
2,
3,
4]. An experimental study on three spun pile specimens with a volumetric ratio of 0.24%, which is about 25% of the minimum requirement according to ACI 318:2019 [
2] was performed. The spun pile had a diameter of 400 mm, a wall thickness of 70 mm, and a concrete strength (fc’) of 54.4 MPa, with stirrups having a yield strength (Fy) of 681 MPa. The bending test results showed that 3.2 mm diameter stirrups with 100 mm spacing were unable to prevent concrete spalling. Therefore, the reserach was concluded that the existing spun pile configuration is not recommended in high-seismic-risk areas.
Another experimental study was conducted on the connection between spun piles and pile caps using a typical connection type commonly used in Indonesia [
4]. A 450 mm diameter spun pile with an 80 mm wall thickness was connected to the pile cap with an anchorage length of 500 mm embedded into the pile cap, with an additional 200 mm bent at a 30-degree angle. Therea are three spun pile to pile cap connections in the experimental study: an empty spun pile (SPPC01) and two spun piles with concrete infill (SPPC02 and SPPC03), both reinforced with 6D19 bars. SPPC03 used expansive concrete to ensure better bonding between the infill concrete and the spun pile and SPPC02 used reguler concrete. All three specimens were subjected to cyclic horizontal loading, with a constant vertical load of 0.1fc’Ag applied during testing. The results indicated that the connections exhibited relatively ductile behavior, with a ductility value of 3.7 for the infilled spun pile connections and up to 5 for the empty spun pile. The strength of the spun pile with concrete infill and 6D19 reinforcement increased by 41% compared to the empty spun pile connection. However, despite its higher ductility, the empty spun pile failed to reach the target drift of 3.5%, failing at 2.75% drift instead. The test results also revealed fracture in the prestressing strands at a location 30 mm – 50 mm outside the pile cap. Overall, the experimental study demonstrated that spun piles with minimum confinement performed reasonably well, although they exhibited limited ductility and pinched hysteretic curves. The spun pile with 6D19 reinforcement showed significant strength improvement compared to the empty spun pile, with better energy dissipation performance.
On the other hand, an experimental study on spun pile-to-pile cap connections was also conducted in China, where the spun piles used had sufficient confinement [
5]. A total of six specimens with different connection configurations were tested, representing common connection types used in China. The 500 mm diameter spun piles with a 100 mm wall thickness were made of 80 MPa concrete and were connected to the pile cap using anchor bars welded to steel plates attached to the surface of the spun pile. Additionally, two specimens with different connection details where the spun pile was filled with reinforced concrete and the rebars were anchored 500 mm – length into the pile cap. These connections which are labelled as CT4 and CT5 are similar to the connection type in Indonesia. Though the volumetric ratios were not mentioned but based on the data, the spun pile had transverse reinforcement slightly lower than the minimum standard. The piles used D4 – 50 mm for spiral which is equivalent to 0.43% of confinement where the minimum requirement refer to ACI was 0.623%. All specimens were subjected to a constant vertical load of 0.1fc’Ag and cyclic horizontal loading. The results indicated that the ductility values of the connections ranged between 3 and 4. Specimen PC5 exhibited the best performance in term of its ultimate Moment and ductility. Overall, the hysteretic curves also showed pinching behavior. This study demonstrated that the performance of a better confinement spun piles in China was not significantly different from the spun piles with poor confinement tested in Indonesia, in terms of ductiliy.
The experimental study on spun pile-to-pile cap connections in Korea, conducted by Bang, utilized spun piles with a diameter of 500 mm, a wall thickness of 80 mm, and fc’ of 80 MPa [
6]. The study compared three different pile head treatment. PHC-A and PHC-B were reinfoced by 9 PC bars with 9.2 mm diameter, meanwhile PHC-C had 12 PC bars of 8.3 mm-diamater. The pile head treatment of three connections were different. The pile of PHC-A was fully embedded to the pile cap with 500 mm length. PHC-B was similar to the the connection type in Indonesia by removing only the concrete of the pile without cutting the PC bars. The pile was filled by reinforced concrete of fc’24MPa and 9D19 deformed bars where the anchorage length of 920 mm. PHC-C has similar pile head treatment with PHC-B with additional transverse reinforcement. The study found that different pile head treatment resulted different connection performance. PHC-A has the highest initial rigidity but the lowest bending capacity. PHC-C which has additional transverse reinforcement has the highest energy dissipation and bending capacity.
Due to the uncertainty of the hard soil position, ensuring confinement in the spun pile at the connection area can be achieved by providing external confinement. This option is more efficient as it can be customized to suit the connection location rather than adding spiral reinforcement along the entire length of the pile. Concrete jacketing, steel jacketing, or FRP wrap are three commonly used confinement methods.
A 50 mm-thick concrete jacketing in the connection area of spun piles was conducted to strengthening the connection [
7]. The spun pile had a diameter of 500mm, a wall thickness of 100mm, and a concrete strength of fc’ 80 MPa. The spun pile was reinforced with ten 7mm-diameter strands and spiral reinforcement of D4 – 50mm with a confinement ratio of 0.43%. The specimen was subjected to a constant vertical load of 0.1fc’Ag and cyclic horizontal loading. The experiment demonstrated a more robust hysteretic curve with the ductility value increasing from 3.07 for specimens without strenghening to 4.5. Additionally, the connection strength increased by 54.4% compared to the unreinforced connection. The study concluded that concrete jacketing significantly improves connection performance. Nevertheless, the application of concrete jacketing as a strengthening technique is difficult to implement in foundation systems.
Yang conducted an experimental study on the spun pile–pile cap connection by applying three layers of FRP with a height of 800 mm to the spun pile in the connection area [
8]. The spun pile used had a diameter of 500 mm, a wall thickness of 100 mm, and a concrete strength of fc’ 80 MPa. The piles use stirrups of 5 mm in diameter with 80 mm spacing, which lead to a confinement ratio of 0.245%. The experimental study showed a more robust hysteretic curve; however, the ductility did not improve which was 2.30. The presence of CFRP had minimal effect on the connection ductility.
Research on steel jackets as a strengthening method has been widely conducted on column structures [
9,
10,
11,
12]. Steel jackets can provide confinement similar to continuous hoop reinforcement. Columns strengthened with steel jacketing exhibit higher strength and ductility. In conclusion, the study found that steel jackets significantly improve the initial stiffness, strength, ductility, and energy dissipation of columns.
Recent seismic hazard assessments indicate an increase in seismic acceleration across many regions of Indonesia. The potential for damage to piles in the future during major earthquakes has become a serious concern. This highlights the need to implement performance-based design for substructures. Therefore, ensuring adequate confinement in spun pile connections is essential. It is necessary to find an external confinement solution that is customized to the diameter of the spun pile, easy to construct, and cost-effective.
A numerical study on the use of steel jackets as external confinement for spun piles in the connection area has been conducted [
13]. The validation of the FE model using Abaqus was performed based on the experimental study conducted by Wang. Parametric variations in steel jacket thickness demonstrated that steel jackets provide additional strengthening and also enhance the ductility of the connection. The use of concrete jacketing requires formwork during construction, making it less practical. Steel jacketing made from hot-formed steel has limitations in terms of diameter and thickness. FRP offers advantages in constructability but is relatively expensive. This study proposes a steel jacket made from cold-formed steel as an alternative external confinement. Besides being cost-effective, its thin profile allows for customization of the diameter to match the spun pile.
The innovation of steel jacket and the associated construction methods have been registered with the Indonesian Patent [registration number P00202109462]. An experimental study has been conducted to ensure the construction process and the effect of steel jacketing to the spun pile connection behaviour [
14]. The jacket improves the connection’s deformability and boosts the energy dissipation capacity by 1.8 times compared to a connection without the steel jacket. Additionally, it increase the bending strength by 18%. Those results showed that the steel jacket can be used as a promising alternative solution to fulfill the confinement of the spun pile on the connection area since it improve dissipated energy of the connection. This paper report further numerical study based on finite element analysis to investigate parameters that affect the behavior of the connection. Brief description of previous experimental study was reported.