3. Problems Encountered and Measures Taken in the Ramming Process
Before proceeding with large-scale rammed earth construction, Wang Shu insisted on conducting a test ramming on one of the site's larger walls. This wall was structurally representative, measuring over 30 meters in length and more than 10 meters in height. The wall was rammed as quickly as possible, while the speed of construction on the other walls was controlled to await the results of this trial. However, when ramming reached above the third floor level, issues of wall leaning and cracking became apparent. First, a large diagonal crack appeared near the second and third floor positions, with the lower part of the crack showing a tendency to bulge outward (
Figure 8). This crack was structurally deep, posing a significant risk to the stability of the wall. Secondly, several small vertical cracks were observed on the wall surface between the floor slabs (
Figure 9). The edges of these cracks were clean, with no outward bulging on either side, leading to the preliminary conclusion that these fine cracks were likely caused by shrinkage due to the excessive length of the wall. These smaller cracks were judged to have no impact on the overall structural stability of the wall.
To make a more precise assessment, the team carefully marked the locations of all cracks on the elevation drawings of the wall. It became evident that the cracks showing signs of outward leaning were primarily concentrated around the second floor and third floor slabs. Based on the detailed drawings of the wall-slab joints, we speculated that the problem might stem from the kickplate (baseboard) edging at the floor-slab interface (
Figure 10). This recessed kickplate design, which the team had discussed extensively before construction, was intended to prevent water from the interior floor from seeping into the earthen wall and to ensure that the kickplate and the wall would be flush after completion. However, during the actual construction process, it became apparent that when the rammed earth wall settled, the settlement on the side with the kickplate was restricted, causing the wall to lean towards the side without the kickplate. If not addressed in time, this could eventually lead to wall collapse. The small cracks between the floor slabs, on the other hand, were primarily shrinkage cracks caused by the excessive length of the wall[
6]. Observations from the site indicated that the lower level exhibited fewer shrinkage cracks than the second level, likely due to the greater pressure exerted by the wall’s own weight, which reduced the potential for shrinkage. We concluded that these natural shrinkage cracks did not affect the stability of the wall, and the issue could be resolved by introducing expansion joints at intervals along the wall.
Before completely dismantling the outward-leaning wall, the laboratory took samples of the rammed earth blocks to test their compressive strength, ensuring that the leaning and cracking were not caused by inadequate material grading (
Figure 11). After several rounds of testing, the results confirmed that there were no issues with the material composition, conclusively pointing to the kickplate design as the source of the problem. The next step was to remove the recessed kickplate that was connected to the main structural framework, allowing the rammed earth wall to be decoupled from the frame, thus preventing interference between the two structures and allowing the wall to settle naturally (
Figure 12). However, this solution raised a new challenge: how to prevent the wall from leaning outward once it was detached. According to Wang Shu's design, the wall was over 10 meters high but only 0.6 meters thick, resulting in a height-to-thickness ratio of 1:17. Additionally, one side of the wall was entirely exposed, making it difficult to balance detaching the wall from the structural frame while ensuring it wouldn’t lean or collapse. This presented a particularly tricky problem at the time.
To solve this problem, our team turned once again to the traditional villages in the mountainous regions of southern Zhejiang for inspiration. In the village of Shanxia Bao in Wuyi County, Jinhua, we found a collapsed house with a hybrid structure of rammed earth and timber. On the remaining two-story rammed earth gable wall, parts of the timber frame were still visible, with several wooden tie rods extending from the wall to securely anchor it to the main timber structure (
Figure 13). The connection points between the timber rods and the main framework had a certain degree of flexibility, allowing the rammed earth wall to settle slightly without causing damage. This offered us an ingenious solution to our problem. Additionally, some of the more sophisticated nodes in the village design featured tie rods that extended entirely through the rammed earth wall, where a long, flat wooden beam would be inserted horizontally or vertically, forming a mortise-and-tenon structure. This created a "T-shaped" tie component that provided an anchor for the wall. With this external tie structure in place, the wall could be adjusted to correct any outward leaning. An elderly carpenter in the village shared with us a fascinating method for repairing rammed earth walls: when they noticed a wall leaning outward, they would position a long, slanted pole against the head of the "T-shaped" tie component, providing a ground support for the pole. Using a lever, they would slowly push the leaning wall back into place. After the wall returned to its original position and had stabilized, they would hammer a fixed pin into the outside of the "T" structure (
Figure 14), completing the correction. This process highlighted another important aspect of rammed earth—it is a relatively flexible material that can be repaired and adjusted over time.
So our team came up with the idea of making exposed tensioned structural components by borrowing traditional methods, and after consulting with the project management engineers on site, We absorbed their suggestions and decided to use another, more subtle approach to tie rods. The revised solution involved embedding a mesh structure of steel bars, arranged both horizontally and vertically, at the level of the floor slabs during the ramming process. The horizontal steel bars extended outward and were anchored to the floor slab at an adjustable fixed point, with sufficient room for the bars to move vertically to accommodate settlement. This design effectively addressed the problem of the wall's outward leaning while allowing for the natural settlement of the rammed earth wall. At the same time, it preserved the integrity of the exposed side of the earthen wall, maintaining its aesthetic and structural coherence (
Figure 15).
Once it became clear that uneven settlement was causing the cracks and outward leaning in the earthen walls, our team assigned a group of diligent workers to monitor and record the settlement displacement of the newly rammed walls daily. The goal was to determine the "optimal time period"—the amount of time required for each section of the wall, based on the proportions provided by our Sustainable Laboratory, to transition from completion of ramming to initial solidification. This data was critical for both the construction of the building and for our research in the laboratory. As mentioned earlier, to ensure the precision and texture of the rammed earth finish, we employed a “pouring-like” method, which differs from traditional techniques. This method involved using a single layer of formwork that spanned the entire length of the wall for each section. The "optimal time period" was crucial for controlling the timing of the formwork removal between the upper and lower layers, the degree of soil hardening, and the overall construction progress. Analyzing the material properties of the rammed earth, which has a dispersed particle structure, it became evident that once the formwork was removed, the evaporation of moisture created voids that led to settlement, marking the wall's solidification process. This settlement was clearly linked to the solidification of the wall[
7], and once complete, the internal settlement of the wall should cease. By monitoring the settlement displacement at the top of the wall—where displacement is most noticeable—we could estimate the time required for the wall to solidify. This data was used to guide the timing for completing each section of the wall. The process required meticulous timing: it couldn’t be too fast or too slow. Precisely controlling this aspect of the construction was key to ensuring successful execution.
After dismantling the trial rammed earth wall, a significant amount of leftover soil was scattered at the site. The workers gathered this material for reuse in the subsequent ramming process. However, these dismantled earth blocks varied in size and couldn’t be directly mixed with water for ramming. Therefore, they were first processed through a crusher to be ground into a fine powder (
Figure 16). This powder was a mixture of soil and sand. The sand content could be divided into two parts: first, the sand that was part of the original mix, and second, gravel from the original mixture that had been crushed into sand by the machine. Our team tested this soil and sand mixture in the laboratory using specialized instruments, which allowed us to adjust the internal composition ratios to make this recycled material suitable for reuse[
8]. This process highlights the most essential characteristic of rammed earth construction—its recyclability. This recyclability holds two significant implications: first, the materials can be reused repeatedly. Even after a wall is dismantled, the materials can be repurposed for construction elsewhere, a quality that most modern building materials lack. It is also the centerpiece of the nature-oriented vernacular construction system, aligned with traditional philosophical views on eternity. The concept of endless cycles, epitomized in Daoist thought and texts such as the I Ching, reflects the belief in continuous renewal—"cyclical regeneration, eternal life”. If we think about it today, this sustainable construction method is also a strategy to resist the gradual scarcity of resources caused by the rough use of materials under the current mainstream construction system. Second, the composition of the rammed earth itself is naturally recyclable. It consists entirely of materials sourced directly from nature, with no added chemicals like lime. This means that when these materials eventually return to the earth, they cause no environmental pollution or damage. They originate from the earth and will, in time, seamlessly return to it[
9].
After learning from the previous setbacks, the subsequent rammed earth construction work gradually progressed smoothly. Once the ramming was completed and the formwork was removed, the exterior surface of the walls revealed a fine, horizontal layered texture. Within each compacted layer, there were subtle differences in texture from top to bottom. The upper parts, being more compacted by the vertical blows of the ramming hammer, had a denser surface than the lower parts. This stratification is reminiscent of the depiction of layered mountains in traditional Chinese landscape paintings. It's a fascinating characteristic of the material, as the construction process leaves visible traces of craftsmanship. However, due to the constraints of the formwork on both sides, these delicate variations are difficult to control during construction [
10], much like the traditional firing process of ceramics. In ceramic production, the final appearance of the glaze is only roughly predictable based on experience, since the transformation in color and shape occurs out of sight in the kiln. When the kiln is opened, there is a sense of anticipation—one can generally control the outcome, but the finer details are always uncertain. This concept applies to the control of texture and color in rammed earth walls as well. From the soil excavated at the site, we identified two distinct color types: a yellowish soil near the foot of the mountain, and a red soil found beneath the cultivated layers on the slopes. After laboratory testing, we selected the yellow soil as the primary source for the ramming, but Wang Shu requested that some areas of the walls exhibit a mixed effect with red soil. During the construction process, the workers were instructed to follow the design plans, which marked the locations for incorporating red soil into the walls (
Figure 17). Although the team carefully mapped the precise locations, shapes, and sizes of the red soil areas on both sides of each wall, the presence of the formwork prevented the workers from seeing the surface as they worked. As a result, they had to rely largely on their experience and intuition, rather than direct observation, when executing the design. Consequently, when the formwork was removed, the final result differed somewhat from the intended design in the drawings. However, this outcome, though unintended, reflects a kind of serendipitous craftsmanship that is both lively and rich with character, a hallmark of traditional building methods where "objective chance" plays a significant and creative role.