2. Materials and Methods
Traditionally, transformers can be equipped with sensors to monitor the loading, ambient temperature, and top oil temperature. Monitoring of the winding hot spot temperature is often included, as this is the critical temperature for aging of the paper in the windings [
8]. Such sensors are commonly fibre optic types, since high electric and magnetic fields in the windings exclude many types of sensors.
A 40 MVA substation transformer (T3) placed in south-eastern part of Norway, see
Figure 1. The cooling system of the T3 is of ONAN type, i.e., heat exchange between the oil and the windings through natural convection, and heat exchange between the oil and the ambient air, also through natural convection. The transformer T3 is equipped with sensors for measuring the clamping pressure on-line (fibre Bragg grating), as well as with several temperature sensors (fibre GaAs type) in the windings, see
Figure 2. There are fibre-optic temperature sensors for the hot spot and in the middle of both the helix LV- and disc-type HV-windings, as well as for oil temperature into and out of the windings. The temperatures at outlet to, and inlet from, one radiator are also measured. In addition there is a resistive temperature sensor (Pt100) for top oil temperature and the ambient temperature is measured some distance below the radiators.
The transformer clamping system consists of top and bottom clamping beams, connected by tie plates mounted along the core legs, see
Figure 2. The windings, the laminated wooden blocks and plates, and the insulation materials are compressed between these beams. The purpose of the clamping system is to maintain sufficient pressure on the windings to keep the turns/discs/conductors in place. The initial clamping pressure is set during the final stages of fabrication. This is typically achieved by jacking up the winding stack to a high pressure and adjusting the height of the top blocks to fit, such that the designed pressure remains after removing the jacks.
There are eight clamping pressure sensors installed on the leg of the central phase. These are located on top of the upper winding plate, and underneath the wooden insulation blocks positioned below the steel clamping beams, see
Figure 2. The pressure measurements presented in this paper is the average of the seven sensors still in function. Clamping pressure act to compress the sensor unit which leads to strain that can be measured. The clamping pressure sensor unit consists of a temperature sensor and a strain sensor, both on the same fibre. The operating principle of fibre Bragg grating sensors is that the grating acts as a dielectric mirror, for a frequency given by the grating distance. As such, the grating distance can be measured by sending a wide frequency wave package into the fibre, and then measuring the peak frequency of the reflected wave. Mechanical strain and thermal expansion change the grating distance, and thus the reflected frequency. The sensors are calibrated by fitting a third-order polynomial for both the temperature and the mechanical strain sensor. Importantly, the temperature measurement is used to compensate for temperature expansion of the strain sensor when calculating the pressure. The operational details of the sensors and measurements from the transformer heat run test were presented earlier [
7].
Steel (the tie plates), copper (the windings), and insulation materials (wood, paper, and pressboard) have different mechanical and thermal properties. Thermal expansion coefficients are typically 12⋅10-6/K, 17⋅10-6/K, 70⋅10-6/K, for steel, copper, and pressboard (out of plane), respectively. The insulation materials are much softer and have a higher thermal expansion coefficient than the metals. Increasing the temperature will cause expansion of all the parts, but less for the steel tie plates than the windings, increasing the tensile stress in the tie plates and the compressive stress in the windings. The higher thermal expansion of copper than steel adds to this, but the major effect is the difference between the pressboard and the steel. Conversely, cooling the entire system will reduce the pressure in the clamping system. In general, the system is not in thermal equilibrium, neither during normal operation, nor following step changes. The varying temperature throughout the system will influence thermal expansion of the windings and clamping system, which in turn affects the clamping pressure.
Energising the transformer is done by connecting the HV windings, which magnetises the core. Magnetic losses in the core cause core heating, affecting the tie plates placed along the core legs. The subsequent thermal expansion of the tie plates will reduce the clamping pressure. Core heating affects the temperature of the transformer as a whole, but the tie plates more directly than the windings. On the other hand, when loading the transformer, current flows through the windings, and copper losses heat the conductors, and in turn the paper, pressboard, and insulation liquid. This affects the windings more directly than the tie plates and will increase the clamping pressure.
The transformer (T3) is placed in the grid, as one of two in a newly constructed substation. This is a typical configuration, following the “N-1” requirement to be able to supply power, even with one transformer failing. The configuration also enables the shifting of load between them, see
Figure 3. Loading and unloading T3 is done by operating the low voltage circuit breaker (CB-18T3), while the high voltage circuit breaker (CB-132T3) is closed. Energising and de-energising T3 is done by operating the high voltage circuit breaker (CB-132T3), while the low voltage circuit breaker (CB-18T3) is open.
A step loading programme of T3 can be performed as follows:
Resting time. Keep the transformer T3 de-energised and unloaded while T1 takes all load of the substation.
Energise T3 by connecting the high voltage side (CB-132T3).
Share load between T1 and T3 by connecting the low voltage side (CB-18T3).
Disconnect the low voltage side of T1 (CB-18T1) such that T3 takes all the load.
Stabilisation time. Keep the transformer energised and loaded.
The operations 1-3, or the reverse, can be done within a minute. The result is a step increase in load for T3, from a resting unloaded condition, to taking all the load of the substation. A series of such operations was performed in February 2023, see
Figure 4.
The scheme of operations for transformer T3 was as follows:
O1: De-energise after resting without load for one day.
O2: Energise and load, one day after O1.
O3: Unload and de-energise, two days after O2.
O4: Energise, one day after O3.
O5: Load, one day after O4.
O6: Unload and de-energise, two days after O5.
O7: Energise and load, two days after O6.
O8: Unload and de-energise, one day after O7.
The main goal of the experiment was to investigate the clamping pressure dynamics while loading and unloading the transformer. The scheme was designed such that the influence of energisation (core losses) can be separated from loading (copper losses). The different operations were performed at intervals of one to two days, to allow the system some time to equilibrate between the operations. The substation is constructed for the future, having a low loading for now, reaching about 60 % of nominal during the heavy loading in winter times. The maximum load obtained for T3 during the experimental period presented in this this paper was about 50 % of rated power.