A Study of Design Change Management for Infrastructure Development Projects in New Zealand

Version 1 : Received: 21 July 2022 / Approved: 21 July 2022 / Online: 21 July 2022 (08:06:44 CEST)

A peer-reviewed article of this Preprint also exists.

Wang, R.; Samarasinghe, D.A.S.; Skelton, L.; Rotimi, J.O.B. A Study of Design Change Management for Infrastructure Development Projects in New Zealand. Buildings 2022, 12, 1486. Wang, R.; Samarasinghe, D.A.S.; Skelton, L.; Rotimi, J.O.B. A Study of Design Change Management for Infrastructure Development Projects in New Zealand. Buildings 2022, 12, 1486.

Abstract

Design changes seem inevitable in engineering, procurement and construction EPC projects. Such changes create a need for a proactive approach to adjusting project scope, cost and time (the triple constraints) for efficiency and effectiveness in overall delivery. This study investigates the causes and implications of design changes in order to improve design change management practices. Data for the study was obtained through online interviews with New Zealand industry practitioners. Thematic analysis was used to collate the results into meaningful data. The study found that design changes were predominantly caused by clients' inadequate strategic planning, insufficient attention to design, EPC contractors' inadequate design ability, and on-site variations. There were three categories of such design changes: direct impact on the project, the reciprocal and complementary effect on stakeholders, and the far-reaching impact on the community. The study concludes by suggesting improvements, such as strengthening the integration of project teams to enhance design quality, strategic alignment of stakeholders at the planning stage, early contractor involvement (ECI) between the planning and design phases, and improving collaboration between design and construction teams. Further, a combination of high technical skills (e.g. design ability) and soft skills (can-do attitude, interpersonal skills, problem-solving skills, documentation skills, etc.) are needed to effect the desired improvement in design change management.

Keywords

engineering procurement and construction project (EPC); project management; design changes; infrastructure development projects; construction management; New Zealand

Subject

Engineering, Architecture, Building and Construction

Comments (0)

We encourage comments and feedback from a broad range of readers. See criteria for comments and our Diversity statement.

Leave a public comment
Send a private comment to the author(s)
* All users must log in before leaving a comment
Views 0
Downloads 0
Comments 0
Metrics 0


×
Alerts
Notify me about updates to this article or when a peer-reviewed version is published.
We use cookies on our website to ensure you get the best experience.
Read more about our cookies here.