Submitted:
05 May 2023
Posted:
06 May 2023
You are already at the latest version
Abstract
Keywords:
1. Introduction
3. Research methodology
3.1. Sampling and data collection
3.1.1. Selection criteria
3.1.2. Case and its participants description
3.2. Data analysis
3.3. Multiple triangulation-based validation
4. Root cause analysis: the multi-method results
4.1. Special tasks and organizational ambiguities
4.2. Process-related problems of claim management
4.3. Inadequate PBO design for organizational claims and its solution
4.3.1. Validation of the framework as build theory
5. Discussion and contributions
5.1. Contributions to theory
5.2. Practical implications
6. Conclusions
References
- Abdul-Malak, M.A.U.; Abdulhai, T.A. Conceptualization of the contractor’s project management group dynamics in claims initiation and documentation evolution. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2017, 9, 04517014. [Google Scholar] [CrossRef]
- Abdul-Malak, M.A.U.; Srour, A.H.; Demachkieh, F.S. Decision-making governance platforms for the progression of construction claims and disputes. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2020, 12, 04520025. [Google Scholar] [CrossRef]
- Acharya, N.K.; Dai Lee, Y.; Man Im, H. Conflicting factors in construction projects: Korean perspective. Engineering, construction and architectural management 2006, 13, 543–566. [Google Scholar] [CrossRef]
- Aladağ, H. and Işik, Z. Role of financial risks in BOT megatransportation projects in developing countries. Journal of Management in Engineering 2017, 33, 04017007. [Google Scholar] [CrossRef]
- Ali, B. , Zahoor, H. , Nasir, A.R., Maqsoom, A., Khan, R.W.A. and Mazher, K.M. “BIM-based claims management system: A centralized information repository for extension of time claims.” Automation in Construction, 2020, 110, 102937. [Google Scholar] [CrossRef]
- Alsamarraie, M.M.; Ghazali, F. Evaluation of organizational procurement performance for public construction projects: Systematic review. International Journal of Construction Management 2022, 1–10. [Google Scholar] [CrossRef]
- Anago, J.C. How do adoption choices influence public private partnership outcomes? Lessons from Spain and Portugal transport infrastructure. International Journal of Managing Projects in Business 2022, 15, 469–493. [Google Scholar] [CrossRef]
- Baatz, N. Problem management/dispute resolution in partnering contracts. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 2008, 161, 115–120. [Google Scholar] [CrossRef]
- Bakhary, N.A.; Adnan, H.; Ibrahim, A. A study of construction claim management problems in Malaysia. Procedia economics and finance 2015, 23, 63–70. [Google Scholar] [CrossRef]
- Barakat, M.; Abdul-Malak, M.A.; Khoury, H. Sequencing and operational variations of standard claim and dispute resolution mechanisms. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2019, 11, 04519012. [Google Scholar] [CrossRef]
- Bayramova, A., Edwards, D.J., Roberts, C. and Rillie, I. Enhanced safety in complex socio-technical systems via safety-in-cohesion. Safety Science 2023, 164. [CrossRef]
- Bortey, L., Edwards, D.J., Roberts, C. and Rillie, I. A Review of Safety Risk Theories and Models and the Development of a Digital Highway Construction Safety Risk Model. Digital 2022, 2, 206–223. [CrossRef]
- Chaphalkar, N.B.; Sandbhor, S.S. Application of neural networks in resolution of disputes for escalation clause using neuro-solutions. KSCE Journal of Civil Engineering, 2015, 19, 10–16. [Google Scholar] [CrossRef]
- Chau, K.W. “Application of a PSO-based neural network in analysis of outcomes of construction claims. ” Automation in Construction, 2007, 16, 642–646. [Google Scholar] [CrossRef]
- Charehzehi, A. , Chai, C. , Md Yusof, A., Chong, H.Y. and Loo, S.C. “Building information oulling in construction conflict management.” International journal of engineering business management, 2017, 9, 1847979017746257. [Google Scholar] [CrossRef]
- Dang, C.N.; Chih, Y.Y.; Le-Hoai, L.; Nguyen, L.D. Project-based A/E/C firms’ knowledge management capability and market development performance: Does firm size matter. Journal of Construction Engineering and Management 2020, 146, 04020127. [Google Scholar] [CrossRef]
- De Valence, G. Reframing construction within the built environment sector. Engineering, Construction and Architectural Management 2019, 26, 740–745. [Google Scholar] [CrossRef]
- Duodu, B.; Rowlinson, S. Intellectual capital, innovation, and performance in construction contracting firms. Journal of Management in Engineering 2021, 37, 04020097. [Google Scholar] [CrossRef]
- Echternach, M.; Pellerin, R.; Joblot, L. Litigation management process in construction industry. Procedia Computer Science 2021, 181, 678–684. [Google Scholar] [CrossRef]
- Eisenhardt, K.M. Building theories from case study research. Academy of management review 1989, 14, 532–550. [Google Scholar] [CrossRef]
- Enshassi, A.; Mohamed, S.; El-Ghandour, S. Problems associated with the process of claim management in Palestine: Contractors’ perspective. Engineering, construction and architectural management 2009, 16, 61–72. [Google Scholar] [CrossRef]
- Fenn, P.; Lowe, D.; Speck, C. Conflict and dispute in construction. Construction Management & Economics 1997, 15, 513–518. [Google Scholar]
- Fisher, L.; Edwards, D.J.; Pärn, E.A.; Aigbavboa, C.O. Building design for people with dementia: A case study of a UK care home. Facilities 2018, 36, 349–368. [Google Scholar] [CrossRef]
- Fitriyanti, F.; Adly, E. Lessons Learned in the Use of Dispute Boards to the Settlement of Construction Service Disputes. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2022, 14, 04521041. [Google Scholar] [CrossRef]
- Fletcher, M.; Zhao, Y.; Plakoyiannaki, E.; Buck, T. Three pathways to case selection in international business: A twenty–year review, analysis and synthesis. International Business Review 2018, 27, 755–766. [Google Scholar] [CrossRef]
- Fulcher, M., Edwards, D.J., Lai, J.H.K. and Thwala, D.W. (Analysis and modelling of social housing repair and maintenance costs: A UK case study, Journal of Building Engineering, 2022, 52. [CrossRef]
- Gebken, R.J.; Gibson, G.E. Quantification of costs for dispute resolution procedures in the construction industry. Journal of professional issues in engineering education and practice 2006, 132, 264–271. [Google Scholar] [CrossRef]
- Gunduz, M.; Elsherbeny, H.A. Operational framework for managing construction-contract administration practitioners’ perspective through modified Delphi method. Journal of Construction Engineering and Management 2020, 146, 04019110. [Google Scholar] [CrossRef]
- Guévremont, M.; Hammad, A. Visualization of delay claim analysis using 4D simulation. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2018, 10, 05018002. [Google Scholar] [CrossRef]
- Gurgun, A.P. and Koc, K. (2022), “The role of contract incompleteness factors in project disputes: A hybrid fuzzy multi-criteria decision approach”, Engineering, Construction and Architectural Management, ahead-of-print No. ahead-of-print. [CrossRef]
- Hadi, I.Z. Building a management system to control the construction claims in Iraq. Al-Khwarizmi Engineering Journal 2018, 14, 108–117. [Google Scholar] [CrossRef]
- Havila, V.; Medlin, C.J.; Salmi, A. Project-ending competence in premature project closures. International Journal of Project Management 2013, 31, 90–99. [Google Scholar] [CrossRef]
- Haugen, T.; Singh, A. Dispute resolution strategy selection. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2015, 7. [Google Scholar] [CrossRef]
- Henning, C.H.; Wald, A. Toward a wiser projectification: Macroeconomic effects of firm-level project work. International Journal of Project Management 2019, 37, 807–819. [Google Scholar] [CrossRef]
- Hughes, M. Organisational ambidexterity and firm performance: Burning research questions for marketing scholars. Journal of Marketing Management 2018, 34, 178–229. [Google Scholar] [CrossRef]
- Ive, G. and Gruneberg, S., 2000. . The economics of the modern construction sector. Macmillan, London.
- Jagannathan, M.; Delhi, V.S.K. Identifying focus areas to decode the decision to litigate contractual disputes in construction. Engineering, Construction and Architectural Management 2022, 29, 2976–2998. [Google Scholar] [CrossRef]
- Jagannathan, M.; Delhi, V.S.K. Litigation in construction contracts: Literature review. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 2020, 12, 03119001. [Google Scholar] [CrossRef]
- Jones, O.; Gold, J.; Claxton, J. Process improvement capability: A study of the development of practice (s). Business Process Management Journal 2019, 25, 1841–1866. [Google Scholar] [CrossRef]
- Karim, M.A.; Ong, T.S.; Ng, S.H.; Muhammad, H.; Ali, N.A. Organizational Aspects and Practices for Enhancing Organizational Project Management Maturity. Sustainability 2022, 14, 5113. [Google Scholar] [CrossRef]
- Kimchi, J.; Polivka, B.; Stevenson, J.S. Triangulation: Operational definitions. Nursing research 1991, 40, 364–366. [Google Scholar] [CrossRef]
- Kitzinger, J. The methodology of focus groups: The importance of interaction between research participants. Sociology of health & illness 1994, 16, 103–121. [Google Scholar]
- Kululanga, G.K.; Kuotcha, W.; McCaffer, R.; Edum-Fotwe, F. Construction contractors’ claim process framework. Journal of Construction Engineering and management 2001, 127, 309–314. [Google Scholar] [CrossRef]
- Kumaraswamy, M.M. “Conflicts, claims and disputes in construction. ” Engineering Construction and Architectural Management, 1997, 4, 95–111. [Google Scholar] [CrossRef]
- Kumar, R.; Iyer, K.C.; Singh, S.P. Understanding relationship between risks and claims for assessing risks with project data. Engineering, Construction and Architectural Management 2020, 28, 1014–1037. [Google Scholar] [CrossRef]
- Kumar Viswanathan, S.; Neeraj Jha, K. Entry mode sequencing model for emerging international construction firms. Journal of Management in Engineering 2020, 36, 05020002. [Google Scholar] [CrossRef]
- Law, R.C.K., Lai, J.H.K., Edwards, D.J. and Hou, H. COVID-19: Research Directions for Non-Clinical Aerosol-Generating Facilities in the Built Environment. Buildings 2021, 11. [CrossRef]
- Lee, C.K.; ou, T.W.; Cheung, S.O. Selection and use of alternative dispute resolution (ADR) in construction projects – Past and future research. International Journal of Project Management, 2016, 34, 494–507. [Google Scholar] [CrossRef]
- Lee, S.H.; Jeon, R.K.; Kim, J.H.; Kim, J.J. Strategies for developing countries to expand their shares in the global construction market: Phase-based SWOT and AAA analyses of Korea. Journal of Construction Engineering and Management 2011, 137, 460–470. [Google Scholar] [CrossRef]
- Lee, W.Y.; Lee, S.H.; Jin, C.; Hyun, C.T. Development of the RACI Model for Processes of the Closure Phase in Construction Programs. Sustainability 2021, 13, 1806. [Google Scholar] [CrossRef]
- Lehtovaara, J.; Seppänen, O.; Peltokorpi, A. Improving construction management with decentralised production planning and control: Exploring the production crew and manager perspectives through a multi-method approach. Construction Management and Economics 2022, 40, 254–277. [Google Scholar] [CrossRef]
- Leibenstein, H. X-efficiency, technical efficiency, and incomplete information use: A comment. Economic Development and Cultural Change 1977, 25, 311–316. [Google Scholar] [CrossRef]
- Liu, J. , Meng, F. and Fellows, R. An exploratory study of understanding project risk management from the perspective of national culture. International Journal of Project Management 2015, 33, 564–575. [Google Scholar] [CrossRef]
- Locatelli, G.; Konstantinou, E.; Geraldi, J.; Sainati, T. The dark side of projects: Dimensionality, research methods, and agenda. Project Management Journal 2022, 53, 367–381. [Google Scholar] [CrossRef]
- Maemura, Y.; Kim, E.; Ozawa, K. Root causes of recurring contractual conflicts in international construction projects: Five case studies from Vietnam. Journal of Construction Engineering and Management 2018, 144, 05018008. [Google Scholar] [CrossRef]
- Makarem, A., Abdul-Malak, M.A. and Srour, I., 2012. Managing the Period Preceding the Calling for a DAB’s Decision. In Construction Research Congress 2012: Construction Challenges in a Flat World ( 71-79).
- March, J.G. Exploration and exploitation in organizational learning. Organization science 1991, 2, 71–87. [Google Scholar] [CrossRef]
- Martek, I. , 2022. International Construction Management: How the Global Industry Reshapes the World.
- Martinsuo, M.; Geraldi, J. Management of project portfolios: Relationships of project portfolios with their contexts. International Journal of Project Management 2020, 38, 441–453. [Google Scholar] [CrossRef]
- Matthews, R.L.; Tan, K.H.; Marzec, P.E. Organisational ambidexterity within process improvement: An exploratory study of four project-oriented firms. Journal of Manufacturing Technology Management 2015, 26, 458–476. [Google Scholar] [CrossRef]
- Mayer, B.S. The conflict paradox: Seven dilemmas at the core of disputes. John Wiley & Sons. 2015. [Google Scholar]
- Midler, C., Maniak, R. and de Campigneulles, T. Ambidextrous program management: The case of autonomous mobility. Project Management Journal 2019, 50, 571–586. [CrossRef]
- Mirzaee, A.M. , Hossieni, M.R. and Martek, I. Optimal Buyer Credit Arrangements for Chinese Procured Dam-building Projects: An Iranian Perspective. KSCE Journal of Civil Engineering 2022, 26, 4984–4996. [Google Scholar] [CrossRef]
- Mirzaee, A.M. , Hosseini, M.R., Martek, I., Rahnamayiezekavat, P. and Arashpour, M., 2022b. Mitigation of contractual breaches in international construction joint ventures under conditions of absent legal recourse: Case studies from Iran. Engineering, Construction and Architectural Management, ahead-of-print. [CrossRef]
- Miterev, M.; Engwall, M.; Jerbrant, A. Exploring program management competences for various program types. International Journal of Project Management 2016, 34, 545–557. [Google Scholar] [CrossRef]
- Miterev, M. , Turner, J. R. and Mancini, M. “The organization design perspective on the project-based organization: A structured review”, International Journal of Managing Projects in Business 2017, 10, 527–549. [Google Scholar] [CrossRef]
- Müller, R.; Drouin, N.; Sankaran, S. Modeling organizational project management. Project Management Journal 2019, 50, 499–513. [Google Scholar] [CrossRef]
- Nafe Assafi, M. , Hossain, M.M., Chileshe, N. and Datta, S.D. (2022), “Development and validation of a framework for preventing and mitigating construction delay using 4D BIM platform in Bangladeshi construction sector”, Construction Innovation, ahead-of-print No. ahead-of-print. [CrossRef]
- Obi, L.; Hampton, P.; Awuzie, B. Total interpretive structural modelling of graduate employability skills for the built environment sector. Education Sciences 2020, 10, 369. [Google Scholar] [CrossRef]
- O’Reilly, I.I.I. O’Reilly, I.I.I.; CA; Tushman, M.L. Organizational ambidexterity: Past, present, and future. In Academy of management Perspectives; 2013; Volume 27, pp. 324–338. [Google Scholar]
- Osei-Kyei, R.; Chan, A.P.; Yao, Y.; Mazher, K.M. Conflict prevention measures for public–private partnerships in developing countries. Journal of Financial Management of Property and Construction 2019, 24, 39–57. [Google Scholar] [CrossRef]
- Owusu-Manu, D.-G. , Ofori-Yeboah, E., Badu, E., Kukah, A.S.K. and Edwards, D.J. (2022), "Assessing effects of moral hazard -related behaviours on quality and satisfaction of public-private-partnership (PPP) construction projects: Case study of Ghana", Journal of Facilities Management, ahead-of-print No. ahead-of-print. [CrossRef]
- Parchami jalal, M.; Moradi, S.; Shirazi, M.Z. Claim management office maturity model (CMOMM) in project-oriented organizations in the construction industry. Engineering, Construction and Architectural Management 2023, 30, 74–104. [Google Scholar] [CrossRef]
- Parchami Jalal, M. , Yavari Roushan, T. , Noorzai, E. and Alizadeh, M. “A BIM-based construction claim management model for early identification and visualization of claims”, Smart and Sustainable Built Environment 2021, 10, 227–257. [Google Scholar] [CrossRef]
- Petro, Y.; Ojiako, U.; Williams, T.; Marshall, A. Organizational ambidexterity: A critical review and development of a project-focused definition. Journal of Management in Engineering 2019, 35, 03119001. [Google Scholar] [CrossRef]
- Project Management Institute (PMI) (2017), A Guide to the Project Management Body of Knowledge (PMI® Guide, 6th ed., Project Management Institute, Pennsylvania, PA.
- Rijke, J.; van Herk, S.; Zevenbergen, C.; Ashley, R.; Hertogh, M.; ten Heuvelhof, E. Adaptive programme management through a balanced performance/strategy oriented focus. International Journal of Project Management 2014, 32, 1197–1209. [Google Scholar] [CrossRef]
- Roberts, C. and Edwards, D.J. (2022) Post-occupancy evaluation: Identifying and mitigating implementation barriers to reduce environmental impact, Journal of Cleaner Production. [CrossRef]
- Shahhosseini, V. and Hajarolasvadi, H. “A conceptual framework for developing a BIM-enabled claim management system.” International Journal of Construction Management, 2018, 1-15. [CrossRef]
- Shalwani, A.; Lines, B. Using issue logs to improve construction project performance. Engineering, Construction and Architectural Management 2022, 29, 896–915. [Google Scholar] [CrossRef]
- Shao, J.; Müller, R.; Turner, J.R. Measuring program success. Project Management Journal 2012, 43, 37–49. [Google Scholar] [CrossRef]
- Shenhar, A.; Holzmann, V. The three secrets of megaproject success: Clear strategic vision, total alignment, and adapting to complexity. Project Management Journal 2017, 48, 29–46. [Google Scholar] [CrossRef]
- Senaratne, C.; Wang, C.L. Organisational ambidexterity in UK high-tech SMEs: An exploratory study of key drivers and barriers. Journal of Small Business and Enterprise Development 2018, 25, 1025–1050. [Google Scholar] [CrossRef]
- Seo, W.; Kang, Y. Performance indicators for the claim management of general contractors. Journal of Management in Engineering 2020, 36, 04020070. [Google Scholar] [CrossRef]
- Seo, W.; Kwak, Y.H.; Kang, Y. Relationship between consistency and performance in the claim management process for construction projects. Journal of Management in Engineering 2021, 37, 04021068. [Google Scholar] [CrossRef]
- Sinha, A.K.; Jha, K.N. Dispute resolution and litigation in PPP road projects: Evidence from select cases. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 2020, 12, 05019007. [Google Scholar] [CrossRef]
- Stamatiou, D.R.I.; Kirytopoulos, K.A.; Ponis, S.T.; Gayialis, S.; Tatsiopoulos, I. A process reference model for claims management in construction supply chains: The contractors’ perspective. International Journal of Construction Management 2019, 19, 382–400. [Google Scholar] [CrossRef]
- Tamayo-Torres, J.; Roehrich, J.K.; Lewis, M.A. Ambidexterity, performance and environmental dynamism. International Journal of Operations & Production Management 2017, 37, 282–299. [Google Scholar]
- Tan, H.C. Tan, H.C. and Anumba, C. 2010, December. Web-based construction claims management system: A conceptual framework. In Proceedings of the 8th International Conference on Construction and Real Estate Management (ICCREM 2010) ( 1-3).
- Taylor, K. , Edwards, D.J., Lai, J.H.K., Rillie, I., Thwala, W.D. and Shelbourn, M. (2022) Converting commercial and industrial property into rented residential accommodation: Development of a decision support tool, Facilities, ahead-of-print No. ahead-of-print. [CrossRef]
- Tellis, W. Application of a case study methodology. The qualitative report 1997, 3, 1–19. [Google Scholar]
- Tochaiwat, K.; Chovichien, V. Contractors construction claims and claim management process. Engineering Journal of Research and Development 2004, 15, 66–73. [Google Scholar]
- Trinkūnienė E. and Trinkūnas, V. Mediation as an alternative means to the business dispute resolution. Business and management 2022, 946–952.
- Trzeciak, M.; Kopec, T.P.; Kwilinski, A. Constructs of Project Programme Management Supporting Open Innovation at the Strategic Level of the Organisation. Journal of Open Innovation: Technology, Market, and Complexity 2022, 8, 58. [Google Scholar] [CrossRef]
- Turner, R. How does governance influence decision making on projects and in project-based organizations? Project Management Journal 2020, 51, 670–684. [Google Scholar] [CrossRef]
- Vanagunas, S. Max Weber's Authority Models and the Theory of X-Inefficiency: The Economic Sociologist's Analysis Adds More Structure to Leibenstein's Critique of Rationality. American Journal of Economics and Sociology 1989, 48, 393–400. [Google Scholar] [CrossRef]
- Wang, N.; Wu, G. A Systematic Approach to Effective Conflict Management for Program. Sage Open 2020, 10, 2158244019899055. [Google Scholar] [CrossRef]
- Wilms, R.; Winnen, L.A.; Lanwehr, R. Top Managers' cognition facilitates organisational ambidexterity: The mediating role of cognitive processes. European Management Journal 2019, 37, 589–600. [Google Scholar] [CrossRef]
- Wu, G.; Zhao, X.; Zuo, J.; Zillante, G. Effects of team diversity on project performance in construction projects. Engineering, Construction and Architectural Management 2019, 26, 408–423. [Google Scholar] [CrossRef]
- Ye, M.; Lu, W.; Flanagan, R.; Ye, K. Diversification in the international construction business. Construction management and economics 2018, 36, 348–361. [Google Scholar] [CrossRef]
- Yin, R.K., 2009. Case study research: Design and methods (Vol. 5). Sage.





| Row | Ongoing | Under closing |
| 1 | Continuous monitoring:
|
Closeout management:
|
| 2 | Intersection and/or termination in coordination with the legal and contract affairs departments | Alternative dispute resolution management |
| 3 | Documents evaluation by using document control center (DCC) system | Follow up on insurance and tax issues |
| 4 | Performing other tasks assigned by the senior managers of the organisation | File a lawsuit and litigation management |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |