Version 1
: Received: 8 April 2020 / Approved: 9 April 2020 / Online: 9 April 2020 (16:25:36 CEST)
How to cite:
Przywara, D.; Rak, A. Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Preprints2020, 2020040162. https://doi.org/10.20944/preprints202004.0162.v1
Przywara, D.; Rak, A. Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Preprints 2020, 2020040162. https://doi.org/10.20944/preprints202004.0162.v1
Przywara, D.; Rak, A. Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Preprints2020, 2020040162. https://doi.org/10.20944/preprints202004.0162.v1
APA Style
Przywara, D., & Rak, A. (2020). Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Preprints. https://doi.org/10.20944/preprints202004.0162.v1
Chicago/Turabian Style
Przywara, D. and Adam Rak. 2020 "Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators" Preprints. https://doi.org/10.20944/preprints202004.0162.v1
Abstract
The Planning and implementation of construction projects are difficult processes and are burdened with many risk elements. The budget spread over time, which is developed on the basis of the schedule, presents the expected distribution of costs throughout the duration of the works, which during the implementation of the project is subject to constant changes resulting from time, cost and organizational factors. Managing construction contracts requires managers to be able to analyze on an ongoing basis the variances of production costs - from the values calculated in the offer cost estimate and assumed in the Budgeted Cost of Work Scheduled. The article attempts to analyze the emerging time and cost deviations using proprietary T/S and T/C monitoring, based on simple indicators of the EVM method. An example of construction of a multi-family housing development was used to study the variances of planned and incurred costs.
Keywords
Earned Value Method – EVM; time variances; cost variances; schedule
Subject
Engineering, Civil Engineering
Copyright:
This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.