Preprint
Article

This version is not peer-reviewed.

Data-Driven Assessment of Wind Energy Potential in Borneo, Malaysia: Implications for Sustainable Renewable Energy Development

Submitted:

18 November 2026

Posted:

19 November 2026

You are already at the latest version

Abstract
Realistic view on potential wind energy harvesting in Borneo Sarawak is necessary and promising data should be gathered to support a government in green energy landscape. Recent research normally gathered a data from a height of less than 30 m, and it does not align with the model wind turbine that normally build with height more than 30 m. Mukah Sarawak is selected as a matter of fact significantly higher wind speed data from Meteorological Department (MET) Malaysia as compared to 6 others location. An accurate of 96.38% low-cost monitoring system has been applied at proposed location, and the data is gathered from October 2024 to March 2025 considering a potential stronger wind speed due to northeast monsoon. Beta distribution with α = 2.5; β = 6.8 is used for modeling wind speed frequency. As compared to others Normal, F, Gamma and Weibull distributions, MSE results of 0.66% for Beta distribution are the lowest. The trend indicates left skewed distribution, with lower wind speed occurring more frequently between 1.5 m/s to 4.0 m/s. The wind seems to gradually decrease after 4 m/s, showing stronger wind occur less frequently. Supporting peak wind hours (PWH) graph shows a potential wind speed of 2 hours but indicates lack of consistency and less predictable wind speed, therefore conclude Mukah is unsuited for harvesting wind energy. Future study should be expended to offshore areas that promise a stronger wind speed but challenge in marine environment should be considered for a profitable wind power station.
Keywords: 
;  ;  

1. Introduction

In recent years, Malaysian Government has attempted to enhance the utilization of renewable energy which aims to conserve the non-renewable sources from being depleted and to ensure the sustainability of energy supply. In accordance with Malaysia aims to reduce the greenhouse gas (GHG) emission by 45% in year 2030, some of the renewable energy alternatives are proposed [1]. The process of shifting from non-renewable energy using fuels and coals to renewable energy like biomass, biogas, hydro and wind is challenge since the demand for electricity in Malaysia is linearly increase over the years and expected to reach 7571 kWh/person in 2030 [2,3]. Nonetheless, the Government has begun to look at the potential of wind energy as one of the eligible energies for generating electricity in Malaysia [4].
Wind is one of the sources that can be used to generate electricity, and it is inexhaustible, fuel-free, energy resource without pollution. Wind power stations are also one of the ways that can be used to reduce greenhouse gas emissions [5]. Specifically, in Malaysia, Tenaga Nasional as energy consumer plan to widen the wind generation between 3.5 to 14% of total electricity demand. It is reported that low wind speeds experiences which is classify as class 1 as in Table 1 in major area in Peninsular Malaysia and Borneo has become a reason why another renewable source become an option. However, further study reveals the average wind speed of 15 m/s at Malaysian-Thailand border has increase the government interest to place the wind energy farm [6].
Malaysia holding around 2m/s wind speed which is not recommended to develop wind power station. From a Malaysian Meteorological Department (MMD) data collected between 2007 to 2011 at three stations namely Kudat, Kuching and Subang, the highest mean wind speed is reported in Kudat (2.5 m/s) followed by Kuching (2.1 m/s) and Subang (below than 2 m/s) [7]. The wind energy in Malaysia depends on the present of wind and it is varying from place to place. Therefore, preliminary study should be conducted at different places namely Peninsular Malaysia and Borneo to find the suitable locations for wind energy farm. The average wind speed should be more than 7.0 m/s to consider the placement of wind power station is good [8].
The anthropogenic climate change, a result from fossil fuel combustion, has become an important issue recently. With the increasing demand for electricity yearly, the use of fossil fuel needs to follow the trend to ensure the continuity of electricity. Alternative solutions such as the use of renewable energy indicate positive outcomes but the process of transition from fossil fuel to renewable is timely extensive [10,11] in accordance with high investment cost for renewable energy power stations.
The use of wind power station in Malaysia is still considered low, since other power station such as biomass (41%), solar (35%) and hydro (12%) is dominating the energy production [12]. Location is one of the issues to develop wind power stations. Based on Palanichamy et al. [13], the annual wind speed which is 2m/s in Malaysia is not suitable for to harnessing the wind energy since the minimum wind speed for electricity generation should be more than 7 m/s.
Data for wind speed in rural places, especially in Sarawak, is still lacking and outdated. Few studies estimate the mean wind speed at locations like Kuching, Sri Aman, Sibu, Bintulu and Limbang and this area is considered as low wind resource area [14]. In accordance, previous research is totally relied on wind speed data collected from Malaysian Meteorological Department (MMD) at 10 m height as in Figure 1. Therefore, none has conducted actual measurements at height greater than 10 m. A monitoring system for wind, especially in areas like Mukah, Sarawak should be proposed so that more information can be gathered for a potential wind power station location. Based on Figure 2, offshore data taken during the northeast monsoon is more appealing and is classified under class 7 than can be considered as excellent. The promising data from this offshore study in [15] indicates a potential wind for onshore wind turbines in coast area especially Mukah.
The objective of this research is to explore the new insight into recent studies and provide a preliminary wind data to state authorities for a future wind technology in Borneo. Therefore, the sub objectives are as follows:
  • To study the wind speed that is suitable for power station placement in rural area Sarawak;
  • To study the wind speed that is suitable for power station placement in rural area Sarawak;
  • To analyse the performance of wind speed using best frequency distribution for wind speed classification.
The scope of this project is that the speed is measured in m/s following the international standard of the World Meteorological Organization. For a sensing unit, an anemometer NPN output with supply of 10 to 30 VDC will be used to measure the wind speed. The sensor is situated 30 m located at the top of the Politeknik Mukah water tank tower (2.875162, 112.022140). Two point to point outdoor wireless access points, by means one antenna act as a transmitter is connected to wind sensor using CAT6E and another antenna as receiver is connected to PC. The sensor data has been processed by low-cost PIC microcontroller modelled renatta AT12M0R. The real-time monitoring system developed using SCADA is used to measure the wind speed with time intervals of a minute, an hour and a day and the data is displayed using PC. The analysis is conducted within Northeast Monsoon starting from October 2024 to March 2025.

2. Literature Review

2.1. Previous Studies

The use of renewable energy has its own advantages and disadvantages. One of the advantages of renewable energy power stations is low cost [17]. Once the power station is installed, only maintenance is needed because of using free sources. Renewable energy also produces small greenhouse gas emissions. However, the disadvantage in term of unstable energy such as solar power station only produce energy based on daylight while wind required a windy place. Irwanto et al. [18] has characterized the wind speed class into five categories. First class is poor and only can provide around 3.5 to 5.6 m/s wind speed. Second class is marginal, around 5.6 to 6.4 m/s wind speed. Third class is moderate, around 6.4 to 7.0 m/s wind speed. Fourth class is good, indicated 7.0 to 7.5 m/s wind speed. Fifth class is excellent, around 7.5 m/s and above wind speed. Among all these classes, only good and excellent conditions are recommended for wind power stations which need at least 7 m/s to generate electricity continuously. Ibrahim et al. [16] recommend a height of the turbine to generate electricity stably. Based on the studies, 30 m of wind sensor indicate less than 5.1 m/s of the wind speed which is in poor classes for a wind power station. For 50 m of sensor height, the wind speed reading accelerates to a maximum speed of 5.6 m/s. Malaysia is still categorized as Class 1 which is poor (wind speed < 5.6 m/s). That’s the main reasons Malaysia not widely adopt wind power station as energy resource.
Next, the performance of wind speed is measured over time. Study conducted by Wagner et al. [19] has made a comparison of wind speed between 1500hrs and 0300hrs. The study was conducted in Danish National Test Station, Denmark. For a 20m and 40m sensor height, there is no difference in wind speed for each hour. The differences can be noticed at 60 m, 80 m and 100 m of height. For overall, 0300hrs has the best performance of the wind speed. Albani & Ibrahim [20] also did a comparison in four different places in Malaysia. The comparison has been made in Kudat, Mersing, Langkawi and Kijal. Each state a different wind speed reading. In Kudat, 10 m = 3.2 m/s, 35 m = 5.26 m/s, 50 m = 6.08 m/s and 70 m = 6.67 m/s. In Mersing, 10 m = 2.95 m/s, 35 m = 3.65 m/s, 50 m = 4.58 m/s and 70 m = 4.79 m/s. In Langkawi, 10 m = 1.59 m/s, 35 m = 2.86 m/s, 50 m = 3.47 m/s and 70 m = 4.11 m/s. Lastly, in Kijal, 10 m = 2.77 m/s, 35 m = 3.44 m/s, 50 m = 3.81 m/s and 70 m = 4.57 m/s. Based on the data, Malaysia not recommended but still has a potential to develop wind power station. Besides, Malaysia has a lack of data about wind speed due to investment cost for wind speed study.
Ho [21] discover 369,597 MW of wind power capacity had been installed around the world. Approximately 38% of the global installed capacity is in Asia, and 80% of that can be found in China. In addition, Malaysia has the potential of wind power station especially in Sarawak and Sabah because of less congestion compared to peninsular Malaysia. With more studies, certain area in Malaysia can become a potential to use wind as an energy resource.

2.2. Beta Distribution

The Beta distribution is a continuous distribution that is often dubbed as the probability distribution of probabilities. The concept is defined within intervals 0 and 1, indicated by α and β. Beta distribution is used to infer the probability of an event considering the information about the volumes of successes and failure. The primary use of Beta distribution is being conjugated prior to Bayesian statistics to the Bernoulli distributions [22]. The expression of PDF for Beta distribution is as in equation (1).
f ( x , α , β ) = x α − 1 ( 1 − x ) β − 1 B ( α , β ) , {{ MDPIHEX 0010 } {{ MDPIHEX 0011 } {{ MDPIHEX 0012 } {{ MDPIHEX 0013 } {{ MDPIHEX 0014 } {{ MDPIHEX 0015 } {{ MDPIHEX 0016 } {{ MDPIHEX 0017 } {{ MDPIHEX 0018 } {{ MDPIHEX 0019 } 0 < x < 1
If the µ and σ2 has already been computes, the α and β can be calculates as in equations (2) and (3).
α = μ μ 1 − μ σ 2 − 1
β = α 1 − μ
Where x is random variable where 0≤ x ≤1, α and β are shape parameter (must be positive) and B(α, β) is the Beta function, which normalizes the distribution to ensure the total area under the curve is 1 [23,24].
The advantages of using Beta distribution are the flexibility in shape hence it is suitable to measure statistical dispersion namely variance, geometric variance and covariance and mean absolute difference [25]. The drawback of using Beta distribution is limited range, which is 1 and 0 make it not possible to estimate the four parameters of the beta distribution from the three values provided by the expert [26].2. Materials and Methods

3.1. Study Area and Setup

The wind speed study is conducted in Mukah Sarawak (2.875162, 112.022140). The location is the top of the Politeknik Mukah’s water tank tower as shown in Figure 3. The height of the water tank tower is 30 m and is the highest point in Politeknik Mukah.
Figure 4 shows the connection diagram of proposed wireless wind speed detection system. The wind speed sensor is located 30 m at top of water tank tower and is interconnect with low-cost PIC microcontroller modelled renatta AT12M0R using 50 m CAT5E cable in pump house. Through the CAT5E, 5V has been constantly supplied to a wind sensor to ensure the raw data received from the sensor is accurate in accordance with pre analysis recorded indicate the reliability of 5V data although the sensor supply should be within 10 to 30V. The wind sensor data is measured in m/s. Then, the data has been transmitted wireless using two point to point outdoor wireless access points located outside of water pump house (sender) and Department of Electrical Engineering (receiver). The access point (receiver) is then connected with personal computer through CAT5E, and the measurement is displayed in GUI developed using PIC SCADA. In GUI, the measurement of wind speed is displayed in the graph for minutes, hourly and daily. The storage unit in PC is used as a data logger and the measured data from October 2024 to March 2025 can be analyzed and characterize.

3.2. Wind Speed Data

Figure 5 illustrate the wind speed data from years 2023 to 2025 at Mukah Sarawak. That daily data has been provided by MET Malaysia, whereby the wind sensor is located near Mukah airport (2.889569, 112.043164) with the height of 38.3 m. In January 2023, the wind speed indicates by 2 m/s and increase to peak in March 2023 (2.6 m/s). A sharp decline happed on April 2023, 2024, and 2025 as well as for 2023 and 2025 reaching the lowest value of the year with 1.7 m/s and 1.9 m/s respectively. Within May to August for three for these three consecutive years, the value fluctuates mildly between 1.8 m/s and 2.2 m/s indicating a constant wind speed. The outcome concludes 2025 demonstrate a more stable and higher wind speed value compared to 2023 and 2024. The promising wind speed can be seen for the first quarters of year with highest wind speed indicate averagely 2.3 m/s and it may reflect to a northeast monsoon season.
The trend for average monthly wind speed in 7 different locations in Sarawak is illustrated in Figure 6. The highest wind speed is recorded by Mukah, typically between 1.9 to 2.4 m/s followed by Miri, generally between 2.0 to 2.3 m/s. The lowest wind speed is consistently indicated by Pertanian Sarekei with only 0.7 to 0.8 m/s. Coastal areas such as Mukah, Miri and Bintulu experiences higher wind speed between January and February as well as in November and December. Besides, the trend is more consistent compared to rural areas like Pertanian Sarekei and Limbang experience a sharp drop of 0.6 m/s in September making it the lowest monthly value among all locations.

3.3. Mean Squared Error (MSE) for Various Distributions

The reliability of data based on Mean Squared Error (MSE) for various distribution is compared. The use of MSE is for evaluating a statistical model based on average squared different between actual and predicted values computation as in equation (4). For the benchmarking purpose, 5 different distributions namely Normal, F, Beta, Gamma and Weibull are compared indicating the lowest MSE quantifies batter accuracy.
MSE = ∑ ( Actual i − Predicted i ) 2 n
Graph in Figure 7 illustrate the various distribution applied for wind speed results gathered at Mukah from January to December 2025. The sample from probability density function (PDF) used to fit the model is obtained from the graphical histogram. In finding the best distribution from various mathematical models, the reference line should fall approximately as the histogram [27]. For this case, the histogram is left skewed and distribution with varies shape such Beta, Gamma and Weibull are the best options compared to Normal that inhabit a bell shape.
Figure 8 to Figure 10 indicate the MSE with varies scale and shape parameters for Beta, Gamma and Weibull distributions. The lower MSE indicate a better approximation and the goodness of fit between actual and predicted values. The MSE for Normal distribution indicate 2.02% and it is 1.85% lower than computed F-distribution with numerator and denominator degrees of freedom r1=39, r2=326. Meanwhile, analysis using Beta, Gamma and Weibull distributions illustrate a faithful error. The shape parameter α is varies from 1 to 2.5 and β are from 3 to 6 and the outcome demonstrate that increasing α while maintaining moderate β improved the MSE to higher accuracy. The minimum MSE recorded for Beta distribution is 0.66% at α = 2 and β = 3, followed closely by 0.67% recorded when α = 2.5 and β = 4. When α and β are substantially higher, the MSE is also constantly increase hence aligning both α and β (i.e. < 2) may be the best options. Meanwhile computing α and β using equations (2) and (3) indicate the MSE less than 1%.
Unlike Beta distribution, Gamma distribution does not need to be normalizes below 1 hence the complexity is reduced. Using similar concept, α (shape parameter) and β (scale parameter) is varied to ensure the MSE is lowest. Taking the histogram of wind speed data in Figure 7, the distribution should be moderately right skewed and align α to a lower value is considerable. For a simplicity, the pre-determined parameter of α and β is computed using equations (2) and (3) and the outcome indicate MSE 1% higher than pre-determined parameters of Beta distribution. Based on Figure 8, increased the β to a higher value exhibit substantially higher MSE, suggesting poorer fitting performance. Even for a best fit parameters for Gamma distribution of α = 20 and β = 0.1 resulting MSE = 1.98%. Changing the α does not dramatically affect the MSE as compared to β. Despite the optimization, Gamma distribution unable to outperform the optimum Beta distribution and the MSE is nearer to Normal distribution.
Figure 8. MSE for varied α and β for Beta distribution.
Figure 8. MSE for varied α and β for Beta distribution.
Preprints 244896 g008
Figure 9. MSE for varied α and β for Gamma distribution.
Figure 9. MSE for varied α and β for Gamma distribution.
Preprints 244896 g009
Figure 10. This is a figure. Schemes follow the same formatting.
Figure 10. This is a figure. Schemes follow the same formatting.
Preprints 244896 g010
Unlike others distribution, Weibull is widely applied in wind speed model whereby λ is a scale parameter while k is shape parameter. Graph in Figure 10 shows the positive outcome of accuracy when λ is increased from 1 to 2. However, the MSE tends to linearly increase when λ > 2. For λ = 1, the MSE indicating a poor fit with error more than 4% for whole cases (k = 5 to 10). The results suggest the best fit for Weibull is when λ = 2 and k = 9 with MSE recorded is 1.78%. In summary, Beta distribution is selected as the best fit for wind speed data in Mukah. Other distributions namely Normal, F, Gamma and Weibull exhibit large errors with average MSE of 2.41%, indicating less suitability for wind speed model in Mukah.

4. Results

In an early wind power station development, capturing and analyzing the wind speed data for a certain location is a must. Previous studies are highly dependent on MET Malaysia data, and the sensor placement height is varied depend on certain locations. For an expanded height, prediction model such logarithmic wind profile was used, and it is exposed to an error [28]. For this case, the wind data is recorded from October 2024 to end of March 2025 at 30 m height. Figure 11 and Figure 12 illustrates the daily and hourly average wind speed in Mukah Sarawak Malaysia. The data has been recorded each day making 173 sampled sizes of daily data while hourly data is averagely taken making the sample size is 4152. Overall, the wind speed illustrated in Figure 11 and Figure 12 is moderately low ranging from 1.2 to 3.0 m/s, with a mean value around 2.0 m/s and fall under wind class 1. During December 2024 and January 2025, there are several inselberg trends occurring due to sudden changes in wind speed to wind class 3 for a short duration. For a similar location observed in Figure 12 with hourly average data trend exhibit similar fluctuations in December 2024 and January 2025, reaching approximately 7.0 to 8.0 m/s. Mostly, the wind speed for 6 months duration fall under wind class 1 ranging from 1.0 to 4.0 m/s. The outcome shows Mukah experiences predominantly wind class 1 to wind class 2, with short fluctuations of stronger wind.
The variation on wind speed in January 2025, with detailed observation within 24 January 2026 to 26 January 2026 are graphically shown in Figure 13. The line graph shows a stable wind speed throughout January 2025 fluctuating between 2.0 to 3.5 m/s. Within highlighted period within 24 January 2026 to 26 January 2026 for the hourly analysis as in Figure 13(b), there is an amplified deviation between 10:00 AM and 4:00 PM. There is a promise outcome within this period for a stronger wind circulation. On 26 January 2025 within 10:00 AM and 4:00 PM, the maximum wind speed has risen to 4.5 m/s at maximum. Following the peak trend after 4.00 PM shows a consistent speed varying between 1.0 m/s to 2.0 m/s till next morning.

5. Discussion

Figure 14 illustrates the wind speed frequency distribution fitted with Beta PDF within October 2024 to end of March 2025 in proposed location. The Beta PDF is fitted with shape parameters α = 2.5; β = 6.8 using pre-computes as in equations (2) and (3). The trend indicates left skewed distribution, with lower wind speed occurring more frequently between 1.5 m/s to 4.0 m/s. The wind seems to gradually decrease after 4 m/s, showing stronger wind occur less frequently. Considering the cut-in speed needed in a conventional wind power station to incorporate each of the sources [29], wind class 1 (<4.4 m/s) is considered low to ensure the wind turbine in on generator mode. For this current location, a small scale with low cut in speed wind turbine under cascade connections should be designed to ensure it can operate under low to medium wind class.
Figure 15 indicates the average output power for 3 months from 4.00 AM to 10.00 PM. The rated solar panel of 5.4 kWp is used to obtain the peak sun hours (PSH) and the results have been compared with the peak wind hours (PWH) gathered, assuming a common small wind turbine with a rated power of 5 kW, a typical cut-in speed of 3 m/s with rated wind speed = 12 m/s. Average results of PWH is taken within December 2024 to February 2025 considering northeast monsoon season in Sarawak for high wind energy harvesting. As comparison to solar energy harvesting, the PSH are at intervals from 9.30 AM to 2.00 PM (4.5 hours) [30] which is 2.5 hours more than PWH for wind energy harvesting (see Figure 15 and Figure 16). PSH exhibit smooth bell-shaped pattern while PWH is more irregular and stochastic. The PWH shows lack of consistency and less predictable wind speed with the peak is changes at different local areas.

6. Conclusions

The aim of this research is to study the wind speed in rural area of Sarawak for wind power station recommendation. The wind speed should be characterized as wind class 4 which is between 5.6 m/s to 6.0 m/s for 10 m height while 7.0 m/s to 7.5 m/s for 50 m height. The wind speed data in Sarawak was taken from MET Malaysia for 7 different locations namely Mukah, Miri, Bintulu, Kuching, Limbang, Sibu and Pertanian Sarekei. Due to the coastal geography with northeast monsoon season between December to March, Mukah shows a promising outcome with average wind speed of 2.3 m/s throughout the entire 2025. Besides, the wind speed in Mukah exhibits a consistent increment trend from 2023 to 2025, suggesting a potential of higher wind speed in 2026.
The low-cost monitoring system has been developed using PIC microcontroller modelled renatta AT12M0R. A wind speed sensor is placed at proposed location which is top of the Politeknik Mukah water tank tower with height of 30 m. Two point to point outdoor wireless access points are used to transmit 300 m data wirelessly to personal computer at Department of Electrical Engineering. The GUI developed using PIC SCADA indicates data with time intervals of a minute, an hour and a day. The acquire data were continuously recorded and stored in personal computer storage unit from October 2024 to March 2025. The accuracy of the system recorded is 96.38%.
Lastly, Beta distribution with α = 2.5; β = 6.8 is used for modeling wind speed frequency. Minimum MSE results of 0.66% from Beta distribution as compared to Normal, F, Gamma and Weibull distributions indicated this distribution is best fit for a left skewed trend in proposed location. The proposed location shows a potential wind speed for 2 hours, but results from PWH indicate lack of consistency and less predictable wind speed as compared to PSH in solar system. The outcome for proposed location in Mukah as well as MET Malaysia data in 7 different locations in Sarawak indicate low wind speed onshore and it is not recommend installing a wind power station since solar power stations from recent studies shows more potential.

Author Contributions

The research study was carried out successfully with contribution from all authors equally. The main research idea, hardware setup and manuscript preparation were contributed by Muhammad Sufyan Safwan Mohamad Basir and Mohamad Azizan Mohamad Said. Nur Adibah Raihan Affendy contributed on the research idea including data visualization, probability distribution analysis and error computation.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Data Availability Statement

The data presented in this study are available within the article.

Acknowledgments

The authors acknowledge the support from Politeknik Mukah Sarawak for providing the equipment’s for this research. Special thanks to MET Malaysia for proving a raw data for 7 different locations in East Malaysia from years 2023 to 2025.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

The following abbreviations are used in this manuscript:
MET Meteorological Department
PWH Peak wind hours
PSH Peak sun hours
GUI Graphical user interface

References

  1. Rashidi, N.A.; Chai, Y.H.; Yusup, S. Biomass energy in Malaysia: current scenario, policies, and implementation challenges. Bioenergy Res. 2022, 15, 1371–1386. [Google Scholar] [CrossRef] [PubMed]
  2. Ali, R.; Daut, I.; Taib, S. A review on existing and future energy sources for electrical power generation in Malaysia. Renew. Sustain. Energy Rev. 2012, 16, 4047–4055. [Google Scholar] [CrossRef]
  3. Bekhet, H.A.; Harun, N.H. Role of non-renewable and renewable energy for sustainable electricity generation in Malaysia. Int. J. Environ. Ecol. Eng. 2016, 10, 907–916. [Google Scholar]
  4. The Star. Sabah looks to wind and solar energy to reduce carbon footprint. Star Media Group Berhad. Available online: https://www.thestar.com.my/news/nation/2017/06/30/sabah-looks-to-wind-and-solar-energy-to-reduce-carbon-footprint (accessed on 19 August 2024).
  5. Ahmed, I.; Rehan, M.; Basit, A.; Hong, K.S. Greenhouse gases emission reduction for electric power generation sector by efficient dispatching of thermal plants integrated with renewable systems. Sci. Rep. 2022, 12, 12380. [Google Scholar] [CrossRef] [PubMed]
  6. Asia Wind Energy Association. Malaysia. Available online: https://www.asiawind.org/research-data/market-overview/malaysia (accessed on 30 August 2024).
  7. Shamsipour, R.; Fadaeenejad, M.; Radzi, M.A.M. Assessment of Wind Energy Potential in Three Different Locations of Malaysia. Appl. Mech. Mater. 2015, 785, 621–626. [Google Scholar] [CrossRef]
  8. Abd Samat, A.Q.; Lam, H.Y.; Makalis, A. Investigation of Wind Power Potential in Equatorial Area from the Meteorological Data Measurement in Universiti Tun Hussein Onn Malaysia, Johor. Adv. Comput. Intell. Syst. 2019, 1. [Google Scholar]
  9. Jakhrani, A.Q.; Rigit, A.R.H. Assessment of solar and wind energy resources at five typical locations in Sarawak. J. Energy Environ. 2012, 4. [Google Scholar]
  10. Mazzucato, M.; Semieniuk, G. Financing renewable energy: Who is financing what and why it matters. Technol. Forecast. Soc. Change 2018, 127, 8–22. [Google Scholar] [CrossRef]
  11. York, R.; Bell, S.E. Energy transitions or additions?: Why a transition from fossil fuels requires more than the growth of renewable energy. Energy Res. Soc. Sci. 2019, 51, 40–43. [Google Scholar]
  12. Sulaiman, F.; Abdullah, N.; Gerhauser, H.; Shariff, A. An outlook of Malaysian energy, oil palm industry and its utilization of wastes as useful resources. Biomass Bioenergy 2011, 35, 3775–3786. [Google Scholar] [CrossRef]
  13. Palanichamy, C.; Nasir, M.; Veeramani, S. Wind cannot be directed but sails can be adjusted for Malaysian renewable energy progress. In IOP Conference Series: Materials Science and Engineering; IOP Publishing, 2015; Volume 78, p. 012028. [Google Scholar]
  14. Jakhrani, A. Q.; Rigit, A.R.H. Assessment of solar and wind energy resources at five typical locations in Sarawak. J. Energy Environ. 2012, 4. [Google Scholar]
  15. Hashim, F.E.; Peyre, O.S.C.A.R.; Lapok, S.J.; Yaakob, O.M.A.R.; Din, A.H.M. Offshore wind energy resource assessment in Malaysia with satellite altimetry. J. Sustain. Sci. Manag. 2020, 15, 111–124. [Google Scholar] [CrossRef]
  16. Ibrahim, M.Z.; Hwang, Y.K.; Ismail, M.; Albani, A. Spatial analysis of wind potential for Malaysia. Int. J. Renew. Energy Res. 2015, 5, 201–209. [Google Scholar] [CrossRef]
  17. Maradin, D. Advantages and disadvantages of renewable energy sources utilization. Int. J. Energy Econ. Policy 2021, 11, 176–183. [Google Scholar] [CrossRef]
  18. Irwanto, M.; Gomesh, N.; Mamat, M.R.; Yusoff, Y. M. Assessment of wind power generation potential in Perlis, Malaysia. Renew. Sustain. Energy Rev. 2014, 38, 296–308. [Google Scholar] [CrossRef]
  19. Wagner, R.; Antoniou, I.; Pedersen, S.M.; Courtney, M.S.; Jørgensen, H.E. The influence of the wind speed profile on wind turbine performance measurements. Wind Energy: An International Journal for Progress and Applications in Wind Power Conversion Technology 2009, 12, 348–362. [Google Scholar] [CrossRef]
  20. Albani, A.; Ibrahim, M.Z. Wind energy potential and power law indexes assessment for selected near-coastal sites in Malaysia. Energies 2017, 10, 307. [Google Scholar] [CrossRef]
  21. Ho, L.W. Wind energy in Malaysia: Past, present and future. Renew. Sustain. Energy Rev. 2016, 53, 279–295. [Google Scholar] [CrossRef]
  22. Lee, J.C.; Sabavala, D.J. Bayesian estimation and prediction for the beta-binomial model. J. Bus. Econ. Stat. 1987, 5, 357–367. [Google Scholar] [CrossRef]
  23. Gupta, A.K.; Nadarajah, S. Handbook of beta distribution and its applications; CRC press, 2004. [Google Scholar]
  24. Damgaard, C.F.; Irvine, K.M. Using the beta distribution to analyse plant cover data. J. Ecol. 2019, 107, 2747–2759. [Google Scholar] [CrossRef]
  25. Jones, M.C. Kumaraswamy’s distribution: A beta-type distribution with some tractability advantages. Stat. Methodol. 2009, 6, 70–81. [Google Scholar] [CrossRef]
  26. Pérez, J.G.; Martín, M.D.M.L.; García, C.G.; Granero, M.A.S. Project management under uncertainty beyond beta: The generalized bicubic distribution. Oper. Res. Perspect. 2016, 3, 67–76. [Google Scholar] [CrossRef]
  27. Ricci, V. Fitting distributions with R. Contrib. Doc. Available CRAN 2005, 96, 1–24. [Google Scholar]
  28. Sakagami, Y.; Santos, P.A.; Haas, R.; Passos, J.C.; Taves, F. F. Logarithmic wind profile: a stability wind shear term. arXiv 2014, arXiv:1405.5158. [Google Scholar]
  29. Arani, M.F.M.; El-Saadany, E.F. Implementing virtual inertia in DFIG-based wind power generation. IEEE Trans. Power Syst. 2012, 28, 1373–1384. [Google Scholar] [CrossRef]
  30. Megantoro, P.; Syahbani, M.A.; Sukmawan, I.H.; Perkasa, S.D.; Vigneshwaran, P. Effect of peak sun hour on energy productivity of solar photovoltaic power system. Bull. Electr. Eng. Inform. 2022, 11, 2442–2449. [Google Scholar] [CrossRef]
Figure 1. Malaysian onshore wind power density map at 10 m height. Reprinted from [16].
Figure 1. Malaysian onshore wind power density map at 10 m height. Reprinted from [16].
Preprints 244896 g001
Figure 2. Offshore mean annual wind speed estimates (2001-2010) for (a) Northeast Monsoon (October – March) and (b) Southwest Monsoon (May – September) [15].
Figure 2. Offshore mean annual wind speed estimates (2001-2010) for (a) Northeast Monsoon (October – March) and (b) Southwest Monsoon (May – September) [15].
Preprints 244896 g002
Figure 3. Politeknik Mukah’s 30 m water tank tower.
Figure 3. Politeknik Mukah’s 30 m water tank tower.
Preprints 244896 g003
Figure 4. System setup.
Figure 4. System setup.
Preprints 244896 g004
Figure 5. Monthly average data for Mukah from 2023 - 2025.
Figure 5. Monthly average data for Mukah from 2023 - 2025.
Preprints 244896 g005
Figure 6. Monthly average data for Mukah from 2023 - 2025.
Figure 6. Monthly average data for Mukah from 2023 - 2025.
Preprints 244896 g006
Figure 7. Probability density function for various distribution.
Figure 7. Probability density function for various distribution.
Preprints 244896 g007
Figure 11. Trend for daily average data in Mukah between October 2024 to May 2025.
Figure 11. Trend for daily average data in Mukah between October 2024 to May 2025.
Preprints 244896 g011
Figure 12. Trend for hourly average data in Mukah between October 2024 to May 2025.
Figure 12. Trend for hourly average data in Mukah between October 2024 to May 2025.
Preprints 244896 g012
Figure 13. Trend of wind speed (a) daily for January 2025, (b) hourly from 24 January 2025 to 26 January 2026 and (c) minutes for 25 January 2025.
Figure 13. Trend of wind speed (a) daily for January 2025, (b) hourly from 24 January 2025 to 26 January 2026 and (c) minutes for 25 January 2025.
Preprints 244896 g013
Figure 14. PDF for wind speed in Mukah.
Figure 14. PDF for wind speed in Mukah.
Preprints 244896 g014
Figure 15. Energy output on PSH (Megantoro et al., 2022).
Figure 15. Energy output on PSH (Megantoro et al., 2022).
Preprints 244896 g015
Figure 16. Energy output on PWH.
Figure 16. Energy output on PWH.
Preprints 244896 g016
Table 1. Classification of wind power densities and mean wind speed for different classes [9].
Table 1. Classification of wind power densities and mean wind speed for different classes [9].
Wind
Power
Class
10 m 50 m
Wind Power
Density (W/m2)
Mean Wind
Speed Range
(m/s)
Wind Power
Density (W/m2)
Mean Wind
Speed Range
(m/s)
1 < 100 < 4.4 < 200 < 5.6
2 100-150 4.4 - 5.1 200-300 5.6 - 6.4
3 150-200 5.1 – 5.6 300-400 6.4 – 7.0
4 200-250 5.6 – 6.0 400-500 7.0 – 7.5
5 250-300 6.0 – 6.4 500-600 7.5 – 8.0
6 300-400 6.4 – 7.0 600-700 8.0 – 8.8
7 > 400 > 7.0 > 700 > 8.8
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.
Copyright: This open access article is published under a Creative Commons CC BY 4.0 license, which permit the free download, distribution, and reuse, provided that the author and preprint are cited in any reuse.