The aim of this study is to examine how data analytics can be used to evaluate manufacturing capacity feasibility under projected demand growth. Daily production data were used to assess output trends, variability, forecasting performance, demand-growth feasibility, and the relationship between labor efficiency and production output. Naïve, ARIMA, and TBATS forecasting models were compared using RMSE, MAE, and MAPE, with TBATS producing the lowest error among the tested models. The selected forecast indicated flat to slightly declining weekly output, below the level required to support a 20% demand increase. To quantify risk beyond the point forecast, the study added a forecast-anchored Monte Carlo simulation that generated plausible future weekly output paths using empirical TBATS residuals and PPHH-based productivity scenarios. Under current productivity, the simulated probability of meeting the 20% demand-growth target was 18.8% per week, and the expected weekly shortfall was 53.70 units. A 15% PPHH improvement raised this probability only to 29.4%, indicating that labor-productivity improvement alone is unlikely to close the capacity-feasibility gap. The findings show that the production system faces both output instability and a high risk of failing to meet projected demand. Managers should prioritize process stabilization and bottleneck diagnosis while evaluating flexible and permanent capacity options using additional cost, downtime, and station-level data.
Keywords: 
;  ;  ;  ;  ;  ;  ;  ;  

1. Introduction

Manufacturing companies should meet customer demand while keeping production systems stable, efficient, and cost effective. When demand increases, managers need to understand whether the current production system can support the additional workload or whether the system will begin to experience missed targets, bottlenecks, higher labor stress, or increased operating costs. This is not only a forecasting problem, but also a capacity planning problem. A production line may appear to have enough resources available, but actual output can still fall short because of downtime, labor constraints, material issues, process instability, or other operational disruptions.
This issue is especially important because manufacturing systems generate production data over time, and this data can be used to support better planning decisions. Time-series forecasting has become an important tool in industrial manufacturing systems because it allows organizations to use historical data to predict future production behavior, improve scheduling, optimize resources, and support operational decision-making [1]. Recent reviews of demand forecasting also show that machine learning and deep learning methods are increasingly used to improve forecasting accuracy under volatile supply-chain and demand conditions [2]. Instead of relying only on judgment or short-term observation, managers can use past production patterns to identify whether output is stable, declining, seasonal, or highly variable. This is important because each of these patterns leads to different managerial actions.
Capacity planning also becomes more difficult when demand is uncertain. Recent research has shown that data-driven methods, including machine learning, can improve production capacity prediction in complex manufacturing settings by enabling capacity decisions before all future conditions are fully known [3]. In these situations, inaccurate capacity planning can lead to either underinvestment or overinvestment in capacity leading to not being able to meet the customer demand or equipment/labor is added before the real source of the problem is understood.
This study focuses on a production line that is expected to experience a 20–30% increase in customer demand while operating with relatively fixed labor capacity and resources. The main concern is whether the current system can meet this expected demand growth under existing operating conditions. The available data includes daily production output and a labor-efficiency measure, PPHH (Parts Per Hundred Hours), which allows the analysis to evaluate both production capacity and workforce productivity. This distinction is important because a production shortfall may come from limited capacity, low labor efficiency, and/or unstable operations.
The purpose of this paper is to use daily production data to evaluate production trends, forecast future output, and assess whether the current production system can support projected demand growth. The analysis also examines the relationship between labor efficiency and output to determine whether improving productivity alone would be enough to close the demand gap. By combining time-series forecasting with capacity feasibility analysis, this study provides a data-driven basis for understanding whether the system is constrained by capacity, capability, or broader operational instability.
A point forecast is necessary but insufficient for capacity planning when historical production is volatile. Managers also need to understand the likelihood and severity of shortfalls around the expected forecast. Bootstrap and Monte Carlo approaches support this objective by translating historical forecast uncertainty into distributions of plausible future outcomes rather than a single deterministic value [4,5]. In manufacturing planning, this distinction is important because a capacity decision should be based not only on expected output but also on the risk of failing to satisfy the required service level under adverse but plausible operating conditions.
Accordingly, this study extends the forecasting and capacity-feasibility framework with a forecast-anchored simulation model. The model uses the selected time-series forecast as the expected weekly capacity, resamples empirical TBATS residuals to represent uncertainty, and tests whether PPHH improvements could materially reduce the probability and magnitude of demand shortfalls. This extension is consistent with research that integrates scenario generation into robust production planning when demand and capacity conditions are uncertain [6].
Figure 1. Integrated Production Capacity Feasibility Framework.
Figure 1. Integrated Production Capacity Feasibility Framework.
Preprints 242048 g001
This study contributes to applied manufacturing analytics by proposing and demonstrating an integrated capacity-feasibility assessment that combines production trend diagnostics, forecasting model comparison, demand-growth scenario testing, labor-efficiency analysis, and Monte Carlo capacity-risk simulation using real daily production data. Unlike studies that focus only on forecasting accuracy, this paper links forecasted production behavior and production uncertainty directly to a managerial capacity decision under projected demand growth.

Forecast Uncertainty and Simulation in Capacity Planning

Aggregate production planning under demand uncertainty requires decision makers to evaluate both expected performance and the risk of not satisfying demand. Recent research has incorporated uncertainty explicitly into aggregated production planning through service-level and capacity constraints, demonstrating that deterministic plans can obscure shortage risk when future conditions are variable [7]. Simulation is particularly useful when data is insufficient for a fully specified stochastic optimization model, but historical performance can be used to construct plausible scenarios. For example, robust production-network planning has combined Monte Carlo scenario generation with stochastic modeling to account for incomplete and uncertain operational information [6]. In time-series applications, residual bootstrap methods provide a practical way to simulate future observations around a fitted forecast while preserving the empirical distribution of model error [4,5]. These approaches motivate the present study’s forecast-anchored simulation, which evaluates the reliability of capacity under demand-growth scenarios rather than treating the point forecast as certain.

2. Problem Definition

Because detailed labor-cost, overtime, machine-capacity, and investment-cost data are unavailable, the study does not estimate the least-cost optimum. Instead, it evaluates capacity risk by estimating the probability and expected severity of production shortfalls under alternative demand-growth and productivity scenarios.
To address the managerial problem, the study focuses on three research questions:
• What do observed trends, variability, and forecasting results indicate about future production output?
• What is the probability and expected severity of production shortfalls under the 20% and 30% demand-growth scenarios?
• How is PPHH associated with production output, and how sensitive are projected shortfalls to assumed PPHH improvements?

3. Research Methods

This study follows an applied quantitative case-study approach to determine whether the current manufacturing production system can support projected demand growth. The method connects the managerial problem with production records, forecasting, labor-efficiency evaluation, and capacity feasibility assessment. Recent manufacturing research shows that time-series forecasting is useful for production planning because it helps managers understand future system behavior from historical patterns [1]. Capacity planning also becomes more difficult when demand and production conditions are uncertain, making data-driven methods useful for supporting capacity-related decisions [3]. The overall methodology is shown in Figure 2.
The methodology began by identifying the main managerial problem: whether the production line can support a 20–30% increase in demand under current labor and resource conditions. The operational data was then reviewed and structured over time so production behavior could be evaluated as a trend rather than as isolated daily results.
Production trends and variability were assessed to understand whether the system was stable, declining, or highly inconsistent. Instability can make capacity planning more difficult, especially when output is affected by downtime, supply issues, labor availability, or changing system conditions [9]. Forecasting models were then compared to estimate future output and select the model that best represented the observed production pattern.
Next, the projected output was compared with the required production level under the demand growth scenario. This allowed the study to evaluate whether the current system had enough capacity to meet future demand. Finally, labor efficiency was assessed using PPHH to determine whether productivity improvements alone could close the gap, or whether additional capacity and process improvements would also be needed. The results were then used to support recommendations about capacity expansion, flexible capacity strategies, and operational improvement priorities.

3.1. Data Description

The dataset used in this study is sourced from a manufacturing production line within the organization. The data has been manually recorded by the value stream supervisor and captures daily operational performance over time. Specifically, daily production output has been consistently tracked since August 2024, providing a time-series dataset suitable for trend analysis and forecasting (Figure 3).
In addition to production output, a key performance indicator, PPHH (Parts Per Hundred Hours), was introduced in January 2026 to measure labor efficiency. This metric reflects the relationship between labor input (in terms of total hours worked) and production output, enabling a more detailed evaluation of workforce productivity and operational capability.
The dataset is structured as daily observations, incorporating production output, labor-related inputs, efficiency metrics.
The data spans partial year 2024, full year 2025, and partial year 2026, allowing for the analysis of seasonal patterns, production trends, and variability across different time periods.
Overall, this dataset supports multiple analytical objectives, including time-series trend and seasonality analysis, forecasting future production levels, evaluating capacity utilization and labor efficiency and assessing the feasibility of meeting increased demand under current operational conditions.

3.2. Data Preparation

3.2.1. Data Screening

Data preparation was conducted using R. The dataset was first structured by converting date fields into time-based variables such as Year, Month, Week, and Day, and recognized observations chronologically to support time-series analysis. Initial screening included checks for missing values, inconsistencies, and anomalies.
Production output data has been recorded since August 2024, while the efficiency metric PPHH (parts per hundred hours) has been available since January 2026. Given the primary focus on forecasting and capacity analysis, PPHH is treated as a supplemental variable.
Outliers were identified, particularly instances where PPHH equals zero, indicating that the production line was not operational in those days, it might be due to supply chain disruption or staffing constraints. These observations were retained, as they represent real operational conditions and are important for capturing system variability.

3.2.2. Data Transformation

No formal data reduction techniques were applied due to the limited number of variables. However, data was transformed to support analysis:
• Daily production data was aggregated into weekly totals
• Monthly and yearly summaries were generated for trend evaluation
• Weekly production data was converted into a time-series format to enable forecasting analysis
PPHH was maintained as a supplementary variable for evaluating labor efficiency alongside production output.

3.2.3. Validity and Reliability Analysis

The dataset originates from internal production records, ensuring strong validity as it directly reflects operational performance. The primary variables include:
• Production Output: Daily units produced, representing actual system output
• PPHH: Labor productivity metric, capturing efficiency of workforce utilization
The consistency of data collection and alignment with operational KPIs (Key Performance Indicators) supports the reliability of the dataset for analytical and forecasting purposes.

3.3. Forecast-Anchored Monte Carlo Capacity-Risk Simulation

Point forecasts alone provide the expected weekly output but do not quantify the risk that realized production will be lower than the forecast. To incorporate uncertainty in operational performance, this study extended the selected TBATS forecasting model using a residual-bootstrap Monte Carlo simulation. Bootstrap predictive inference is an established method for representing forecast uncertainty by repeatedly resampling model errors and generating plausible future paths [4,5]. The approach is appropriate for the present production line because the historical output series is volatile and the data do not contain the station-level, downtime, staffing, or cost variables required for a detailed discrete-event or optimization model.
Daily production quantities were aggregated into 85 Monday-start weekly totals. A non-seasonal TBATS model was re-estimated directly from the weekly series. The selected model produced an eight-week point forecast of 177.19 units per week. Let denote the TBATS point forecast for week t, where t = 1, …, 8. Let denote a mean-centered in-sample TBATS residual drawn with replacement for simulation replication b. Simulated weekly output before applying the productivity scenario was calculated as:
Q t b = max 0 , Q ^ t + e ^ t b
Demand was evaluated under growth rates g ∈ {0.20, 0.30}. The weekly target was defined as:
D g = Q ¯ base 1 + g
Where Q ¯ base is the observed historical average weekly output. With Q ¯ base = 189.75 units, the 20% and 30% targets were 227.70 and 246.68 units per week, respectively.
To assess whether productivity improvement could reduce capacity risk, a sensitivity adjustment was derived from the observed PPHH-output relationship. The estimated regression was
Daily Output = 20.824 + 0.1695(PPHH)
based on the 68 available PPHH observations from January through April 2026. Let beta_hat denote the estimated PPHH coefficient, Pbar the mean observed PPHH, n the number of standard production days per week, and r_s the assumed PPHH improvement under scenario s. The simulated output was calculated as: In Equation (4), the PPHH scenario represents an additive change in expected weekly output; the sampled TBATS residual remains an additive error and is not multiplied by the PPHH adjustment.
Q ^ t b , s = max 0 , Q ^ t + e ^ b t ⋅ β ^ ⋅ P ¯ ⋅ n ⋅ r s }
The scenarios used rs ∈ {0, 0.05, 0.10, 0.15}. For every simulated week, shortfall was calculated as:
G ^ t b , s = max 0 , D g − Q ^ t b , s
The simulation generated three outputs for each demand-growth and productivity scenario: (1) the probability of meeting the weekly target, P Q ^ t b , s ≥ D g ; (2) the expected weekly shortfall, E G ^ t b , s ; and (3) the 95th percentile of the weekly shortfall distribution. A total of 100,000 replications was used. The model was structurally verified by checking that simulated output paths were nonnegative and that the no-improvement scenario was centered on the selected TBATS forecast. The PPHH scenarios are sensitivity analyses and should not be interpreted as causal estimates. Because residual independence, constant variance, and lack of autocorrelation have not been established here, the simulation estimates should be interpreted as conditional sensitivity results rather than validated prediction intervals.

4. Data Analysis

This section analyzes production behavior, evaluates forecast performance, investigates demand-growth feasibility, and estimates labor efficiency. The analysis first examines output trends and variability, then compares forecasting models, evaluates whether projected demand can be met, and finally assesses the relationship between labor efficiency and production output.

4.1. Production Trend and Variability Assessment

Daily and aggregated time-series analyses were conducted (Figure 2) to understand the behavior of the production system. Analyzing the data, daily production data demonstrates a downward trend from late 2024 through early 2026. Early periods show higher output and stability, where later periods show reduced average production and higher variability. This can suggest operational issues such as erosion of capacity utilization, more frequent production disruptions, increased inefficiency, or labor shortages. Reviewing monthly aggregation (Figure 4) underscores this trend; there is no consistent pattern that could be interpreted as consistent seasonality, but rather a systematic decline in output as time goes on.
The data shows a wide spread of production output, further demonstrating inconsistent daily operational performance. Some days exhibit very low or no output, indicating significant operational downtime. As Figure 5 shows, data is widely distributed, suggesting a lack of process control. The high variability of production levels suggests targets are being missed and planning and scheduling may be inadequate or inconsistent. Throughput can be disrupted or experiencing bottlenecks, and the overall process is unreliable.

4.2. Weekly Capacity Pattern Assessment

To assess capacity, daily data was aggregated into weekly production totals (Figure 6). This provides a more realistic view of available production capacity and the maximum output achievable under current operating conditions. Similar to the previous analyses, the weekly time-series showcases declining total output over time. Additionally, the sharp fluctuations indicate inconsistent weekly performance. Since staffing and scheduling plans are often built on a weekly cadence, this variability becomes a significant challenge for planning decisions.

4.3. Forecasting Model Comparison

The forecasting models were selected to compare simple, traditional, and more flexible time-series approaches. This comparison is important because recent evidence from smart manufacturing datasets shows that forecasting accuracy depends on the structure of the production data, the forecasting horizon, and the practical usability of the forecasting method [10]. The Naïve model was used as a baseline because it provides a simple reference point for judging the performance of the more advanced models. The ARIMA model was included because it is commonly used for time-series forecasting and can capture patterns based on past values and forecast errors. The TBATS model was included because it is designed for more complex time-series behavior, including changing trends, irregular patterns, and seasonal effects. This model comparison approach is appropriate because recent manufacturing forecasting research emphasizes that different time-series models can perform differently depending on the structure, variability, and stability of the production data [1]. TBATS was developed to forecast time series with complex seasonal structures so it is also suitable when production data may contain complex or irregular seasonal patterns [11]. More complex models, including deep learning, were not tested; therefore, the comparison establishes relative performance only among the three selected methods.
In order to predict future output, we evaluated multiple forecasting models: Naive model (baseline comparison), TBATS model (to accommodate trends), and ARIMA model (to capture autoregressive patterns). We assessed each model using Root Mean Square Error (RMSE), Mean Absolute Error (MAE), and Mean Absolute Percentage Error (MAPE).
Analyzing the results of these measures that have been shown in Table 1, we determined that the TBATS forecasting model performed best, achieving the lowest error across all three measures. This aligns with the patterns we saw in the data, since the TBATS model can handle non-linear trends and irregular fluctuations. These results indicate substantial forecasting error across the methods tested.
Although the TBATS model produced the lowest error values among the three tested models, the error metrics should still be interpreted carefully. The MAPE value of 24.26% indicates that the forecast is not exact. This is anticipated given the high variability in the historical production data. Therefore, the TBATS model should be interpreted as the best available forecasting model, rather than as a perfectly accurate prediction model. The difference between TBATS and ARIMA is modest (RMSE: 56.24 versus 57.44; MAE: 45.42 versus 48.34; MAPE: 24.26% versus 26.52%), so the practical advantage of TBATS should not be overstated. The manuscript does not establish whether Table 1 errors were calculated on a held-out temporal test set; this limits conclusions about out-of-sample accuracy.
Therefore, the TBATS model was selected as the final forecasting model to generate an 8-week forecast. The re-estimated non-seasonal TBATS model produced an eight-week point forecast of 177.19 units per week. Although the forecast remains substantially below both demand-growth targets, it should be interpreted as an expected production level rather than a guaranteed future output. Because the historical weekly series exhibits substantial residual variation (as shown in Figure 7), the point forecast alone provides incomplete decision support. The subsequent Monte Carlo simulation therefore uses the empirical TBATS residual distribution to estimate the probability and severity of future capacity shortfalls. Based on this 8-week forecast, the system exhibits a capacity-feasibility gap and high capacity risk under current operating conditions.

4.4. Demand Growth Scenario Evaluation

In order to determine whether the current system can support increased demand, a 20% demand growth scenario was tested. Target production level was calculated at the baseline average × 1.2. The baseline weekly production was approximately 189.75 units, resulting in a target of 227.70 units. To make the demand-growth comparison clearer, the required target output was compared directly against the forecasted weekly output. This comparison shows that the current system is not only slightly below the demand-growth target, but consistently below it across the forecast period. Since the forecasted production level remains at 177.19 units per week, while the required 20% demand-growth target is 227.70 units per week, the system would need a substantial increase in output to meet expected demand.
Then, forecasted output (Figure 8) was compared against that target production level, finding that forecasted production consistently falls below the target output level. This indicates a substantial expected gap between forecasted production and the required output level under the 20% demand-growth scenario.
A second scenario representing 30% demand growth was also evaluated. Based on the historical mean weekly output of 189.75 units, the 30% target was 246.68 units per week. The point forecast indicates a substantial expected gap relative to both demand-growth targets. However, because forecasting error and operational variability are material, the point forecast alone cannot determine how often the system may exceed or fall below a target. Therefore, a Monte Carlo simulation was conducted to quantify the probability of meeting demand and the expected magnitude of production shortfalls under current operating conditions.

4.5. Labor Efficiency and Output Relationship

To examine the role of labor productivity, the relationship between output and PPHH was analyzed using the available 2026 data. This analysis demonstrated a positive correlation between PPHH (0.625) and production output (Figure 9). This association, estimated from 68 observations, does not establish that increasing PPHH causes higher output or that there are diminishing returns. Other constraints, including equipment and materials, may influence production output.

4.6. Monte Carlo Capacity-Risk Simulation Results

The Monte Carlo simulation quantified the risk that future weekly production would fall below the projected demand-growth targets. Under current productivity conditions, the simulation estimated an 18.8% probability of meeting the 20% growth target of 227.70 units per week. The expected weekly shortfall was 53.70 units, while the 95th-percentile shortfall was 152.58 units. This indicates that under adverse but historically plausible production conditions, the weekly shortfall could exceed 150 units.
For the 30% growth target of 246.68 units per week, the probability of meeting demand declined to 7.0%. The expected weekly shortfall increased to 70.26 units, and the 95th-percentile shortfall reached 171.56 units. These results indicate that the system is not only below the demand target on average but also faces a high risk of large shortfalls when performance resembles lower-output historical weeks.
The productivity scenarios showed that moderate PPHH improvement reduces but does not eliminate capacity risk. A 5% PPHH improvement increased the probability of meeting the 20% target from 18.8% to 20.0%, while a 10% improvement increased it to 22.4%. Even under a 15% PPHH improvement scenario, the probability of meeting the 20% growth target was only 29.4%. For the 30% demand-growth target, the corresponding probability under the 15% productivity-improvement scenario was 14.1%. Under the assumed PPHH scenarios, the simulated capacity remains insufficiently reliable for either demand-growth target; these scenarios do not demonstrate the causal effects of productivity improvement. The complete Monte Carlo capacity-risk results for all demand-growth and productivity scenarios are presented in Table 2.
Figure 10 simulated weekly production distribution under productivity scenarios. The vertical reference lines represent the 20% and 30% demand-growth targets.

4.7. Summary of Analytical Findings

The simulation results reinforce the deterministic forecast comparison by quantifying the likelihood and severity of capacity shortfalls. Across all tested productivity scenarios, the probability of meeting the 20% and 30% demand-growth targets remained low, demonstrating that the capacity-feasibility concern persists when uncertainty is explicitly modeled.
Considering the full analysis, the production system is experiencing a declining and increasingly unstable production system with high variability. Forecasting results suggest future production levels will remain flat or decline slightly, and the TBATS model best captures the irregular pattern of the data. When compared with the projected demand-growth targets, forecasted output consistently falls below the required production levels, indicating that the system exhibits a capacity-feasibility gap and high-capacity risk under current operating conditions. Analyzing labor efficiency demonstrates that improving productivity could improve performance but would not be sufficient to offset the production gap required to meet increased demand.
Overall, the results show that the current production system is not in a strong position to absorb the projected demand increase. The trend and variability analysis indicate that production output has declined over time and has become less stable, while the forecasting results suggest that future output will remain flat or slightly decrease. When the forecasted output is compared with the 20% demand-growth target, the system shows a consistent production shortfall. The labor-efficiency analysis also suggests that higher PPHH is associated with higher output, but the relationship is not strong enough to indicate that productivity improvement alone would close the gap. Therefore, the findings suggest that the system needs both operational stabilization and capacity-related improvement before it can reliably support a 20–30% increase in demand.
These findings answer the research questions by demonstrating that: (1) the current system has a low probability of meeting either the 20% or 30% demand-growth target under observed operating variability; (2) the production pattern is characterized by instability rather than clear seasonality; and (3) although labor productivity is positively associated with output, plausible PPHH improvements do not sufficiently reduce the likelihood of capacity shortfalls. The evidence therefore supports a staged response involving process stabilization, bottleneck diagnosis, flexible capacity planning, and selective long-term capacity expansion.

5. Discussion

The results of this study show that the production system is not only facing a capacity issue, but also a stability issue. The declining production trend, high variability, and forecasted output below the 20% demand-growth target suggest that the current system cannot reliably support the expected increase in demand. This finding is consistent with recent manufacturing research showing that production planning becomes more difficult when output patterns are unstable and future capacity is uncertain [3].
The simulation results add an uncertainty-based interpretation to the forecasting findings. The point forecast indicates that expected production is below the demand-growth target, whereas the Monte Carlo analysis shows the operational risk surrounding that estimate. Under current conditions, the system met the 20% target in fewer than one out of five simulated weekly outcomes and met the 30% target in fewer than one out of ten outcomes. This indicates that the managerial issue is not only an average capacity gap but also a substantial exposure to severe shortfalls when production performance resembles historically weak weeks. The results therefore support stabilization and bottleneck diagnosis before management commits to permanent expansion, while also recognizing that flexible capacity actions may be needed in the short term.
Applying the proposed capacity feasibility framework (Figure 1) helps interpret the results as more than a forecasting issue. The framework shows that the production system faces both a demand-growth gap and an operational stability problem. Therefore, before making long-term capacity expansion decisions, management should first identify the sources of instability, such as downtime, material constraints, scheduling issues, or bottlenecks.
This study also supports the value of using time-series forecasting as a practical decision-support tool in manufacturing. This analysis connects forecasting results directly to a capacity feasibility question. Applied industry research similarly shows that forecasting becomes more useful when it is embedded into managerial decision processes rather than treated only as a technical prediction exercise [12]. This is important because recent work on industrial forecasting emphasizes that time-series methods can support production scheduling, resource planning, and operational decision-making when historical data is properly used [1].
Another important finding is that labor efficiency is associated with production output, but it does not fully explain the production gap. This suggests that improving PPHH may help improve performance, but it may not be enough to meet a 20–30% demand increase by itself. The system may also be affected by bottlenecks, downtime, supply constraints, or other process-level issues. This aligns with bottleneck research showing that manufacturing improvement requires identifying where throughput is constrained before selecting corrective actions [13].
The contribution of this study is that it combines production trend analysis, forecasting model comparison, demand-growth scenario evaluation, and labor-efficiency assessment into one applied capacity-feasibility framework. The results provide a data-driven way to determine whether a manufacturing system is mainly constrained by capacity, labor capability, or broader operational instability.

5.1. Managerial Implications

5.1.1. Production Instability and System Performance

The data shows that daily production output during the end of 2024 was more stable than the end of 2025 and early 2026. The analysis also indicates that the daily workload and output during the end of 2024 was higher than the end of 2025 and early 2026, this is shown by the gradual decline in production output throughout 2025 and into 2026. The outliers seem to increase as the observed decline in daily output continues.
The larger high and low spikes are an indicator that the production line is feeling shocks at different stages throughout the line- a good indicator that increasing production capacity by purchasing new machinery or hiring new personnel would help level load the workload per process. Further investigation into each specific stage of production, such as through per-stage time-studies and throughput statistics, as well as an overall queue analysis for WIP (Work in Process) items are all recommended in order to determine what aspects of production in particular are causing bottlenecks in overall production. This is also supported by recent bottleneck-management research, which emphasizes that bottleneck identification should consider shifting constraints, resource interdependencies, and system-level production flow rather than isolated station performance alone [14]. Additional resources should then be allocated to those stages to improve capacity while avoiding overspending. This is consistent with recent bottleneck detection research, which emphasizes the importance of identifying throughput bottlenecks before selecting improvement actions [13].

5.1.2. Capacity Expansion and Resource Utilization

While investing in machinery would be a step in the correct direction, it is also clear that efficiency should be addressed through the production floor. From a managerial perspective, permanently expanding the capacity of employees would level the production output. Also, utilizing resources within the company would reduce stress in select areas when they are constrained. Though both of these options are feasible and may be able to allow for increased production, improving resource utilization in this way may only be a temporary fix to a larger systemic problem with system instability. Recent work on production planning and control also highlights that manufacturing decisions should be connected to system design, planning structure, and operational conditions rather than treated as isolated resource-allocation decisions [15].

5.1.3. Need for Preliminary Diagnosis Before Throughput Improvement

Our results show that the current production system is highly unstable, with variable production outputs that sometimes drop to zero for an entire day, and a TBATS forecasted decrease in future system throughput. These observed issues seem to suggest that larger issues plague the system’s operation that should be resolved before capacity increases are considered, as an unstable process introduces unpredictable behavior which makes determining concrete system characteristics, such as production rate, significantly more difficult. Preliminary investigations regarding per-stage throughput, supply-chain stability analyses, and a review of current maintenance schedules’ efficiency are recommended to determine what specific aspect of production is causing such significant variability.
Specific improvement recommendations are dependent on the findings gleaned from the recommended preliminary investigations, however standardizing work procedures and implementing regular machining maintenance programs would go a long way to reducing variability and getting the system under control in most cases, if these systems are not already in place.

5.1.4. Stabilization Before Long-Term Capacity Decisions

In general, although capacity increases will likely balance the process out somewhat, there are clear systemic issues regarding system performance and stability that need addressing before throughput improvements should be considered. Ideally, investigations into what causes such extreme process variability should be performed, and improvements should be made, such that the process is stable before even considering trying to improve production rates by the desired 20-30%.
After stability has been reached, identified by broadly stable and normally distributed PPHHs and a neutrally forecasted future state via TBATS, system bottlenecks can be identified using time study and per-stage throughput data collected during the stability improvement stage. Identified bottlenecking stages can then be allocated financial resources, used to hire new personnel or buy new equipment as needed to improve throughput at that stage while ensuring that process stability is maintained. Over time, this should allow for a 20-30% increase in production for a more stable system which is easier to manage. This staged approach is also consistent with recent capacity-planning research showing that data-driven methods can support capacity decisions when production conditions are complex and uncertain [3].

5.1.5. Flexible Capacity and Long-Term Investment Strategy

To achieve this improved system state, a hybrid strategy featuring aspects of both permanent capacity expansion and flexibility is recommended, which will be much easier to maintain with a stable system. This recommendation is consistent with recent production-planning research showing that flexible manufacturing systems can help firms respond to demand surges when demand uncertainty makes fixed-capacity decisions risky [16].Short term flexibility should serve short-term, day-to-day process balancing needs, and should balancing proves insufficient long term permanent investment in improved machinery and increase personnel should be pursued in order to improve overall system throughput.

5.1.6. Risk-Based Capacity Planning

Managers should use the simulation outputs as a service-risk dashboard rather than relying only on a weekly point forecast. The current results show that a 20% demand-growth target cannot be supported reliably by moderate productivity improvement alone. In the short term, management should use the expected shortfall and upper-tail shortfall estimates to plan flexible responses, such as temporary staffing, overtime, cross-training, preventive maintenance, material-availability controls, and production smoothing, subject to cost and feasibility review. In the medium term, managers should collect machine availability, downtime, staffing, maintenance, WIP, and per-stage throughput data to identify the physical source of the risk. A permanent expansion decision should be modeled only after these variables and corresponding cost data are available.

5.2. Limitations and Future Research Directions

The analysis is based on one production line, so the findings may not fully generalize to other manufacturing systems or production environments. The available data mainly includes production output and PPHH, while other operational factors such as machine downtime, material shortages, employee scheduling, maintenance activities, WIP levels, and station-level throughput were not included. Because of this, the study can identify system-level instability and capacity concerns, but it cannot determine the exact root cause of the production variability. The reported forecasting errors are not identified as temporal holdout estimates, and rolling-origin validation, parameter details, residual diagnostic tests, and uncertainty estimates for the PPHH regression are not available in the present analysis. Accordingly, the model comparison and productivity scenarios should be interpreted as exploratory rather than causal or externally validated findings.
Future research should collect more detailed operational data to better identify the causes of output variation and bottlenecks. This could include per-stage cycle times, downtime records, labor shift information, maintenance history, supply-chain disruption records, and WIP movement through the production line. Future work could also compare additional forecasting and machine learning models using longer time-series data.
The simulation is a forecast-anchored capacity-risk model, not a discrete-event simulation of the complete production line. It does not explicitly represent machine failures, shift schedules, queues, inventory, material shortages, or station-level routing because these variables were not recorded. In addition, the PPHH scenarios are based on an observed association between productivity and output and should not be interpreted as causal effects. The model should therefore be used to compare risk scenarios, not to prescribe an exact productivity target or investment decision. Future research should validate the model prospectively by comparing simulated output distributions with subsequently observed weekly production, following established verification and validation practice [17].

6. Conclusions

This study used daily production data to assess whether a manufacturing line can support a projected 20–30% increase in demand. Trend and variability analysis showed declining and unstable output, while TBATS produced the best forecast accuracy among the tested models. The re-estimated TBATS point forecast of 177.19 weekly units remained below the required demand-growth targets. The forecast-anchored Monte Carlo simulation extended this finding by quantifying capacity risk under uncertainty. Under current productivity, the probability of meeting the 20% weekly demand target was 18.8%, and the probability of meeting the 30% target was 7.0%. Productivity sensitivity scenarios improved expected output but did not provide a reliable probability of satisfying either target. The results indicate that the line requires more than modest labor-productivity improvement. Management should first stabilize operations and identify bottlenecks, then evaluate flexible and permanent capacity options using additional operational and cost data. The combined forecasting, scenario, labor-efficiency, and simulation framework provides a practical approach for converting historical production records into risk-informed capacity decisions.

Author Contributions

Abbas Keramati: Conceptualization, Methodology, Supervision, Project administration, Writing – review & editing. Mike Hicks: Formal analysis, Investigation, Writing – original draft. Mellisa Lockwood: Formal analysis, Visualization, Investigation, Writing – original draft. Jake Burdick: Formal analysis, Visualization, Writing – original draft. Wayne Penales: Data curation, Investigation, Writing – original draft, Writing – review & editing. Safaraz Maheen: Investigation, Writing – original draft, Writing – review & editing. All authors have read and approved the final manuscript.

Funding

This research received no external funding.

Data Availability Statement

Data will be made available on request.

Conflicts of Interest

The authors declare that they have no known competing financial interests or personal relationships that could have appeared to influence the work reported in this paper.:

References

  1. Fatima, S. S. W.; Rahimi, A. A review of time-series forecasting algorithms for industrial manufacturing systems. Machines 2024, 12(6), 380. [Google Scholar] [CrossRef]
  2. Douaioui, K.; Oucheikh, R.; Benmoussa, O.; Mabrouki, C. Machine learning and deep learning models for demand forecasting in supply chain management: A critical review. Appl. Syst. Innov. 2024, 7(5), 93. [Google Scholar] [CrossRef]
  3. Mao, Y.; Holmström, J.; Cheng, Y. Applying machine learning to predict production capacity for engineer-to-order products: Learning from wind turbine industry. Technol. Forecast. Soc. Change 2025, 219, 124295. [Google Scholar] [CrossRef]
  4. Lai, Y.; Dzombak, D. A. Use of the autoregressive integrated moving average (ARIMA) model to forecast near-term regional temperature and precipitation. Weather Forecast. 2020, 35(3), 959–976. [Google Scholar] [CrossRef]
  5. Pascual, L.; Romo, J.; Ruiz, E. Bootstrap predictive inference for ARIMA processes. J. Time Ser. Anal. 2004, 25(4), 449–465. [Google Scholar] [CrossRef]
  6. Bruetzel, O.; Hörger, M.; Foran, A.; Benfer, M.; Nassehi, A.; Lanza, G. Robust planning of production networks at an automotive supplier. Int. J. Prod. Res. 2025, 63(9), 3365–3383. [Google Scholar] [CrossRef]
  7. Gómez-Rocha, J. E.; Hernández-Gress, E. S.; Santos-Borbolla, C. A. Improving aggregate production planning considering maximum inventory area and service level with demand uncertainty: a nearshoring context in Mexican companies. J. Ind. Prod. Eng. 2024, 41(5), 442–455. [Google Scholar] [CrossRef]
  8. Yan, X.; Hu, H. New product demand forecasting and production capacity adjustment strategies: Within-product and cross-product word-of-mouth. Comput. Ind. Eng. 2023, 182, 109394. [Google Scholar] [CrossRef]
  9. Koblasa, F.; Urban, M. Time prediction methods in production − a scoping review of the 21st century so far. Comput. Ind. Eng. 2026, 213, 111713. [Google Scholar] [CrossRef]
  10. Farahani, M. A.; Kalach, F. E.; Harper, A.; McCormick, M. R.; Harik, R.; Wuest, T. Time-series forecasting in smart manufacturing systems: An experimental evaluation of the state-of-the-art algorithms. Robot. Comput.-Integr. Manuf. 2025, 95, 103010. [Google Scholar] [CrossRef]
  11. De Livera, A. M.; Hyndman, R. J.; Snyder, R. D. Forecasting Time Series With Complex Seasonal Patterns Using Exponential Smoothing. J. Am. Stat. Assoc. 2011, 106(496), 1513–1527. [Google Scholar] [CrossRef]
  12. Harshvardhan, M.; Curtland, C.; Hwang, J.; VanDam, C.; Ghozeil, A.; Neto, P. A.; Marie, F.; Liu, C. Print Demand Forecasting with Machine Learning at HP Inc. Inf. J. Appl. Anal. 2025, 55(6), 469–483. [Google Scholar] [CrossRef]
  13. Skoogh, A.; Thürer, M.; Subramaniyan, M.; Matta, A.; Roser, C. Throughput bottleneck detection in manufacturing: a systematic review of the literature on methods and operationalization modes. Prod. Manuf. Res. 2023, 11(1), 2283031. [Google Scholar] [CrossRef]
  14. Tang, J.; Dai, Z.; Jiang, W.; Wu, X.; Zhuravkov, M. A.; Xue, Z.; Wang, J. A comprehensive review of theories, methods, and techniques for bottleneck identification and management in manufacturing systems. Appl. Sci. 2024, 14(17), 7712. [Google Scholar] [CrossRef]
  15. Kasper, A.; Land, M.; Bertrand, W.; Wijngaard, J. Designing production planning and control in smart manufacturing. Comput. Ind. 2024, 159-160, 104104. [Google Scholar] [CrossRef]
  16. Elyasi, M.; Altan, B.; Ekici, A.; Özener, O. Ö.; Yanıkoğlu, İ.; Dolgui, A. Production planning with flexible manufacturing systems under demand uncertainty. Int. J. Prod. Res. 2024, 62(1-2), 157–170. [Google Scholar] [CrossRef]
  17. Sargent, R. G. Verification and validation of simulation models. In Proceedings of the 2010 winter simulation conference, 2010. [Google Scholar]
Figure 2. Research Methodology.
Figure 2. Research Methodology.
Preprints 242048 g002
Figure 3. Daily Production Output Over Time.
Figure 3. Daily Production Output Over Time.
Preprints 242048 g003
Figure 4. Monthly Average Production by Year.
Figure 4. Monthly Average Production by Year.
Preprints 242048 g004
Figure 5. Distribution of Daily Production Quantity.
Figure 5. Distribution of Daily Production Quantity.
Preprints 242048 g005
Figure 6. Weekly Production Output.
Figure 6. Weekly Production Output.
Preprints 242048 g006
Figure 7. Eight Week Forecast of Weekly Production Output.
Figure 7. Eight Week Forecast of Weekly Production Output.
Preprints 242048 g007
Figure 8. Forecasted Weekly Production Output.
Figure 8. Forecasted Weekly Production Output.
Preprints 242048 g008
Figure 9. PPHH vs Daily Output.
Figure 9. PPHH vs Daily Output.
Preprints 242048 g009
Figure 10. Residual-Bootstrap Simulated Weekly Production Under Productivity Scenarios.
Figure 10. Residual-Bootstrap Simulated Weekly Production Under Productivity Scenarios.
Preprints 242048 g010
Table 1. Models Performance Comparison.
Table 1. Models Performance Comparison.
Models RMSE MAE MAPE
Naïve Model 107.56 92.63 44.34%
ARIMA Model 57.44 48.34 26.52%
TBATS Model 56.24 45.42 24.26%
Table 2. Final Monte Carlo capacity-risk results (100,000 replications).
Table 2. Final Monte Carlo capacity-risk results (100,000 replications).
Productivity scenario Demand target Probability of meeting target Expected weekly shortfall 95th-percentile shortfall
Current productivity 20% (227.70) 18.8% 53.70 152.58
PPHH +5% 20% (227.70) 20.0% 49.99 148.01
PPHH +10% 20% (227.70) 22.4% 46.39 143.43
PPHH +15% 20% (227.70) 29.4% 43.01 138.85
Current productivity 30% (246.68) 7.0% 70.26 171.56
PPHH +5% 30% (246.68) 10.6% 66.09 166.98
PPHH +10% 30% (246.68) 11.8% 62.02 162.40
PPHH +15% 30% (246.68) 14.1% 58.07 157.83
Note: The values above supersede all earlier simulation values. Minor differences of ±0.1 percentage points can arise if the random seed or software implementation changes; the substantive conclusion does not change.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.
Copyright: This open access article is published under a Creative Commons CC BY 4.0 license, which permit the free download, distribution, and reuse, provided that the author and preprint are cited in any reuse.