Schedule Risk Analysis for Long-Lead Transmission Equipment Procurement

Submitted:

20 October 2026

Posted:

21 October 2026

You are already at the latest version

Abstract
Background: Most capital plans commit to a single date even though the arrival of a late transformer can delay energization of an entire transmission corridor. This study quantifies the schedule risk caused by long-lead transmission equipment, and compares the value for money of different procurement strategies. Method: A project-scheduling risk literature review and a supply chain risk literature review informed a structured synthesis, which in turn was used to develop a probabilistic model of a bulk-supply substation project, consisting of 23 activities and ten risks. A Monte Carlo simulation (20,000 trials for each scenario) was conducted to compare a baseline with four mitigation strategies: early award, a pooled strategic spare, dual sourcing, and a combination of the three. The comparison was facilitated by criticality indices, sensitivity analysis based on rank-correlation, and an expected-delay cost model. Results: The simulated mean energization date was 47.7 months, the eightieth percentile date was 51.0 months, and the probability of energization within 37 months was less than one percent. Half the slippage was due to the network structure and half due to discrete risk events. Award delay, transformer manufacturing time, factory congestion, and shipping delay were the most significant factors and the transformer chain was only critical in 56 percent of trials. Early award reduced the mean by 3.3 months, and produced the greatest net benefit assuming a delay cost. Conclusion: Confidence-based commitments, early award of critical equipment, and targeted protection give utilities more defensible long-lead procurement options. The case is illustrative, and the inputs are assumptions that can be adjusted using project data.
Keywords: 
;  ;  ;  ;  ;  
Subject: 
Engineering  -   Other

1. Introduction

1.1. Background and Problem Context

In today's era, electricity grid systems are being required to transport greater amounts of energy for longer distances with less time tolerance for delay than ever before in their history (U.S. Department of Energy, 2022). This is because the rapid adoption of EVs, heat pumps and renewables for large-scale power generation is creating pressure on networks designed for a different energy system, and as further progress is made in the clean energy transition, the International Energy Agency (2023) has cautioned that demand for electricity networks could begin to outpace supply if investment and delivery do not pick up pace. By 2040, the national energy goals are estimated to require tens of millions of kilometers of new lines or refurbishment, with a small number of intensive customized components per kilometer that are not available off the shelf (International Energy Agency, 2023).
The large power transformer, circuit breakers and Gas Insulated Switchgear, shunt reactors and the protection and control systems with which they are made operable are the items of transmission procurement that have a long lead. It is essential in almost all substations to step-up voltage to increase power transmission efficiency (to reduce transmission losses) and step-down voltage to provide power distribution. Each unit is built to a specific site rating, with a specific impedance and noise specification, and so cannot be manufactured until the rating is accepted and cannot be accelerated by paying for more labor. There are also limited numbers of qualified factories and reliance on specialized inputs like grain-oriented electrical steel, and a high degree of reliance on imports in several national markets (U.S. Department of Energy, 2022).
As a result, the delivery date of the equipment often determines the energization date of the entire project. Any late transformer is a late transformer, and any downstream activity is a late activity if the transformer is late. Civil works, line construction and secondary systems can generally be compressed or resequenced. Although schedule and cost overruns are not unique to any country or sector, they are not simply a matter of bad luck either as the evidence gleaned from large-scale infrastructure programs demonstrates (Flyvbjerg, 2006; Flyvbjerg, Holm, & Buhl, 2002; Sovacool, Gilbert, & Nugent, 2014).
Traditional planning methods have not caught up with this (Project Management Institute 2017). As described by Kelley and Walker (1959), the critical path method provides a single, deterministic finish date and implicitly assumes that all activity durations are certain. The result is a schedule that appears to be perfect, but lacks information about the likelihood of being met, which is exactly what the utility needs when they enter into a financing agreement, reserve an outage window and guarantee a generator a connection date.
In the United States these pressures are acute. The North American Electric Reliability Corporation (NERC) reports sharp increases in peak-demand forecasts and mounting pressure on transmission adequacy in its 2023 Long-Term Reliability Assessment, and it lists transformer supply chains among the developments that could affect future reliability, noting that lead times for distribution transformers often exceed two years (North American Electric Reliability Corporation, 2023). The U.S. Department of Energy’s 2022 supply chain review likewise identifies large power transformers as a customized, long-lead component on which the grid depends (U.S. Department of Energy, 2022). Procurement schedules are often trimmed to fit regulatory and financing calendars, and if delivery slips by six months when the connection is needed to serve load growth or generator interconnection, the cost of delay quickly exceeds the value of the contract itself. It is therefore useful for U.S. utilities, regulators and system planners alike to determine in advance, with defensible probabilities, when a substation is likely to be energized.
The timing is also significant, as the evidence base on grid supply chains has only recently started to become systematic. The trend toward manufacturing clusters, reliance on niche materials, and increasing lead times is now being captured in national assessments, and international analyses link this trend to the amount of investment required for clean energy transitions (International Energy Agency, 2023; U.S. Department of Energy, 2022). The missing link is the connection between such system-level concerns and the distribution of schedule outcomes and decisions at project level, which this study addresses.
Schedule risk, as defined by Hulett (2009), is the potential for a project to finish after the date upon which decisions, contracts and financing have been made and is separate from cost risk, but closely linked. In risk terms it can be represented as a set of scenarios, each with a likelihood and a consequence in months; the distribution of consequences is the exposure, and any single point on that distribution is the wrong measure of it (Kaplan & Garrick, 1981). The vocabulary is important because much of the confusion in practice stems from treating a most likely date as a commitment.
Grid projects have stakes greater than many capital projects. A late transmission asset not only slows down the asset that was supposed to be connected but it also keeps a congested corridor congested and extends the time consumers continue to pay for constraints that the older plant was supposed to retire. A review of cost overrun data from electricity infrastructure projects reveals that projects as a whole rarely achieve their targeted benefits, and the impact of cost overruns is often compounded throughout the lifetime of a program, as well as within a specific project (Sovacool et al., 2014).
Procurement strategy is the core of the problem as it defines the amount of schedule uncertainty that the owner can influence. Decisions about the time of tendering, the number of suppliers to qualify, whether to have spares and their wording of the contract are made before production begins and determine whether the owner gets into the factory queue first or last. Project risk guidance acknowledges procurement as a distinct knowledge area, but is rather limited in its approach to probabilistic scheduling for single source engineered equipment.
The boundaries of the study should be defined at the outset. The analysis focuses on the pre-energization schedule of a substation package, treats long-lead equipment as the main source of exposure and considers procurement-side mitigation rather than design or technology substitution. Cost is considered only in the form of delay cost and mitigation cost. These boundaries make the model tractable and focus attention on the decisions that owners can make at the procurement phase, but they leave out issues that arise in a broader consideration of grid planning.

1.2. Research Problem and Objectives

The central problem addressed here is how a utility, an engineering, procurement and construction (EPC) contractor or a development agency can quantify the schedule risk created by long-lead transmission equipment, and how it can decide which mitigation measures deserve funding. Two weaknesses in current practice motivate the work. First, risk registers are commonly scored qualitatively and rarely translated into a distribution of completion dates, a practice that Hubbard (2020) has criticized for creating an illusion of rigor. Second, supply chain mitigation studies tend to optimize inventory or sourcing decisions in isolation from the project network (Tomlin, 2006), so that the effect of a measure on the energization date remains implicit.
The study therefore pursues five objectives. The first is to synthesize the literature on schedule risk analysis and supply chain risk management as it bears on long-lead electrical equipment. The second is to formulate a transparent probabilistic model of a representative transmission substation project in which equipment lead times, factory test failures, shipping delays and award delays are explicit uncertainties. The third is to identify, through criticality and sensitivity analysis, the activities and risks that most strongly drive the energization date. The fourth is to compare four mitigation strategies, namely early award of the long-lead package, a pooled strategic spare, dual sourcing and a combination of these, in terms of both schedule and cost. The fifth is to translate the results into confidence-based contingency and procurement rules that planners can apply.
Meeting these objectives requires a model that is simple enough to be audited and rich enough to capture the interaction between risks and the network logic. The objectives are condensed into three research questions, introduced in the next subsection, and answered with evidence in Section 4 and with interpretation in Section 5.

1.3. Research Questions

The study is organized around three research questions. These are written in such a way that each can be answered from the output of the simulation and that, in order, they take the reader from a diagnosis of the problem to an identification of its causes and then to a consideration of remedies. As Tranfield, Denyer, and Smart (2003) note, explicit question framing helps to identify the relevant evidence and makes the conclusions easier to challenge.
RQ1: By how much does a deterministic critical-path schedule understate the energization date of a transmission substation project dominated by long-lead equipment, and how much of the shortfall arises from the structure of the uncertain network as opposed to discrete risk events? The question tackles the first of the weaknesses highlighted above. The answer to this question determines whether probabilistic analysis is a refinement or a necessity, and the structural and event-driven decomposition of the answer suggests what type of risk modeling is required in practice.
RQ2: Which activities and risk drivers contribute most strongly to energization delay, and how does the criticality of the equipment chains change once duration uncertainty and shared drivers are taken into account? The question changes from the magnitude of the exposure to the sources of the exposure. It tests whether the deterministic critical path is a reliable guide to management focus, and how important owner-related processes are compared with the factory and logistics risks that affect the final date.
RQ3: Which mitigation strategies, namely early award of the long-lead package, a pooled strategic spare, dual sourcing or a combination of these, most effectively and most economically reduce the probability and magnitude of energization delay?
The question relates the schedule analysis to a decision. It demands that each strategy be described in terms of a change to the model, be assessed on the same random draws and be compared in terms of both the number of months saved and money spent, and asks whether the strategies reinforce or substitute for each other.
The three questions are mutually dependent. The effort of RQ2 is warranted by the large answer to RQ1 and the drivers identified in RQ2 suggest which strategies are likely to be important in RQ3. A mapping of questions to methods to results is presented in Section 3.6 and the answers are synthesized in Section 4.6 and then discussed in detail in Section 5.1.
The research-question format was chosen instead of hypothesis testing because the case is not a statistical sample but a model-based exploration. Hypotheses would also allow for inferences to be made about a population of projects while the simulation generates conditional statements about a specific system with assumed conditions. Questions that ask by how much, which factors and which strategies are better suited to that kind of evidence, which are congruent with the way in which decision makers use probabilistic schedules.

1.4. Contributions and Structure of the Paper

The paper makes three contributions. It connects two literatures that traditionally are read in isolation, the project-scheduling literature on stochastic networks, and the supply chain literature on disruption and mitigation and highlights where one stream leaves a void to be filled by the other. It provides a complete and repeatable case model with inputs specified in tables and outputs reported at a variety of confidence levels. It shows the practicality of comparing the mitigation strategies by expected delay cost, and the decision can be justified in the same units as the project budget.
The rest of the paper proceeds as follows: The literature review is found in Section 2. Section 3 outlines the evidence-gathering process, the case system, the risk register, the process of the simulation and the mitigation scenarios. Section 4 presents the results as probability distributions, criticality indices, sensitivity rankings and cost–benefit comparisons. The implications for practice, as well as the limitations of the analysis, are discussed in Section 5 and the conclusion is presented in Section 6.

2. Literature Review

2.1. Long-Lead Transmission Equipment in the Grid Investment Context

The lead times of the components that make up the transmission projects vary by an order of magnitude (International Energy Agency, 2023). The lowest level of the hierarchy is standard components like insulators and hardware, which are available from stocks or within a few weeks. At the top are engineered-to-order assets like power transformers, reactors and gas-insulated switchgear, with lead times of a year or more, and whose supply is determined not by the buyer's willingness to pay, but by the factory's capacity. Figure 1 shows these assets in the chain from generation to end user and illustrates why a delay at a single substation can propagate through an entire region.

2.1.1. Large Power Transformers

High costs, long manufacturing lead times and logistics issues (International Energy Agency, 2023) have made large power transformers the most widely discussed component. They are listed by the U.S. Department of Energy (2022) as an important grid component with a narrow manufacturing base, a large international dependence on materials and a high reliance on imports to satisfy demand. Failures and replacements are expensive because the units are not standardized and each is tailored to a specific installation, impedance, voltage ratio and cooling requirement (CIGRE Working Group A2.37, 2015).
Reliability data bear this out. CIGRE surveys of transformer populations indicate that, although in-service failures are rare per unit, they involve long outages because replacing a failed unit requires either a rare compatible spare or a new manufacturing cycle (CIGRE Working Group A2.37, 2015). The risk is thus twofold. Before commissioning, the schedule is exposed to design iteration, factory congestion and test failure; after commissioning, a failed unit with no spare means an extended outage. An analysis that addresses only the first exposure will not capture the value of strategic inventory.
Technical specificity is exacerbated by market concentration. If only a few factories produce a particular class of unit, the buyer's bargaining position is weak when order books are full, and a project that reaches the market when demand is high may find factory slots booked several years ahead. Recent assessments describe a limited manufacturing footprint and high levels of dependence on specialized steel and imports in some national markets (International Energy Agency, 2023; U.S. Department of Energy, 2022).
Lead times also respond to demand with a time lag, and a self-reinforcing response is possible. Higher order volumes increase backlog, which pushes buyers to order earlier and in larger volumes to secure capacity, which in turn increases backlog further. This resembles the amplification of demand signals in supply chains, a long-established phenomenon, and it makes inventory and ordering policies for slow-moving, high-cost items considerably more complicated than those for fast-moving items (Lee, Padmanabhan, & Whang, 1997; Silver et al., 2017).

2.1.2. Switchgear, Reactors and Secondary Systems

Gas-insulated switchgear, high-voltage circuit breakers and shunt reactors share the long lead times of transformers but differ in some respects. Their manufacturing cycles are a little shorter, their designs are more modular and there are generally several qualified suppliers, which allows supplier diversification where it is often not possible for the largest transformers. Protection, control and supervisory systems have shorter lead times but involve integration risk, because they are not tested end-to-end until the primary equipment is installed.
From a practical perspective, long-lead equipment should not be treated as a single block. The uncertainties that govern each stage differ, and mitigation measures act on specific stages rather than on the schedule as a whole; a realistic schedule model should therefore separate design approval, manufacture, factory acceptance testing, and shipping and installation for each equipment class.

2.1.3. Structures, Conductors and Line Materials

Apart from substation equipment, line materials are generally less schedule critical, but have an impact when quantities are large, or there is a need for specialized conductors for uprating. The structural and insulation components of a typical overhead line include the lattice tower or steel pole, the insulator strings and the conductors that span high-voltage corridors. Their procurement risk typically concerns volume, quality, and logistics rather than the manufacturing time of a single item.

2.1.4. Investment Demand and the Planning Horizon

The significance of procurement performance is set against the backdrop of the massive investment needed over the next two decades. To achieve the energy and climate targets, there is a need to add and/or refurbish tens of millions of kilometers of grid by 2040, while at the same time supply chains for vital grid components, such as transformers and cables, are being constrained in the delivery process (International Energy Agency, 2023). The same analysis calls for firm and transparent project pipelines so that manufacturers have forward visibility of demand.
When planning horizons are added, there is a time dimension to the exposure. Procurement decisions made early in the development of a transmission line are a part of a long process that can lead to energization in several years, and the owner is committed to the process before conditions on site and permits are determined. The uncertainty in project estimates, uncertainty in project goals and uncertainty in the relationship between the parties are distinguished in the literature on uncertainty in projects and the owner is exposed to all three in long-lead procurement (Atkinson, Crawford & Ward, 2006; Ward & Chapman, 2003).

2.2. Supply Chain Risk Management for Infrastructure Projects

2.2.1. Disruption, Vulnerability and Resilience

The risks described above are the subject of the supply chain risk literature. Chopra and Sodhi (2004) pointed out that delays, disruptions and forecast errors interact in the chain, that supply chains fail when these interactions are poorly managed, and that mitigation always involves a trade-off between efficiency and robustness. Kleindorfer and Saad (2005) suggested a systematic approach to disruption risk assessment and mitigation, using quantitative analysis and strategic concepts and Tang (2006) listed effective strategies such as postponement strategies, strategic stock and supplier management. These studies show that supply risks can be analyzed, ranked and managed in much the same way as other project risks.
Later work shifted from prevention to resilience. Christopher and Peck (2004) emphasized visibility and agility, and Sheffi and Rice (2005) emphasized the mix of redundancy and flexibility in their concept of the resilient enterprise. Empirical research indicates that the impact of a disruption is related to the design of the supply network as well as what resources are available to detect and recover from the disruption (Craighead, Blackhurst, Rungtusanatham and Handfield 2007).
Announcements of supply chain disruption can severely damage shareholder value, which shows that delay is not only a technical event but also a financial one (Hendricks & Singhal, 2005).
The taxonomy of risk sources (Chopra & Sodhi, 2004) is a useful starting point. Wagner and Bode (2008) separate demand, supply, regulatory, infrastructure and catastrophic risk, and show that each dimension affects performance differently. Literature reviews distinguish macro-level risks outside the firm from micro-level risks internal to it, and observe that supply-side risk dominates the quantitative models (Ho, Zheng, Yildiz, & Talluri, 2015). The risk register for transmission procurement developed later in this paper draws on these classes.
There are several ways to measure the consequences of disruption. The negative impact on shareholder value has been reported to be substantial from event studies of announced supply chain disruption events and impacts are long lasting following the announcement (Hendricks & Singhal, 2005). Research on levels of disruption reveals that the level of damage is related to the design of the supply system (its density and complexity) and to mitigating measures available (such as early warning and recovery options) (Craighead et al., 2007). All the findings point in the same direction: Exposure is related not only to the individual event, but also to the system; thus, a network model is a better medium for exposure than a list of risks.

2.2.2. Bibliometric Evidence on Risk Analytics

The volume of research on supply chain risk analytics has been rapidly increasing (Ho et al., 2015). Publication output has grown steadily since the early 2000s, following the pattern described in previous reviews (Fahimnia et al., 2015), and it is concentrated in a small number of operations and production research journals, which indicates a methodologically mature literature that is only weakly connected to construction and project journals (Ghadge, Dani, & Kalawsky, 2012). This concentration helps explain why findings from the supply chain literature are seldom exposed to the project management audience.
Consistent conclusions can be drawn from the quantitative literature reviews. Fahimnia et al. (2015) identified that the quantitative analysis of supply chain risk is growing quickly and that research is focusing on identifiable streams, while Snyder et al. (2016) demonstrated that models of disruption focus on inventory, sourcing and facility decisions. Sodhi et al. (2012) concluded from their survey of researchers that the gap between theory and practice is large. This is an important gap for the present study, because few models relate supply risk with the completion date of a particular capital project.
Supply chain risk management is also available as a book-length treatment with a managerial perspective (Sodhi & Tang, 2012). Sodhi and Tang (2012) explain that firms employ operational strategies (e.g., inventory buffers and flexible capacity) as well as financial hedges and strategic choices (e.g., network structure) and that the combination of these strategies depends on the nature and size of the risk. Applied to long-lead equipment, the rule is that if the delays are high frequency and low impact, like a little shipping slippage, then schedule buffers can absorb them, but if the delay is low frequency and high impact, like a supplier failure, then structural protection is required (Tang, 2006).

2.2.3. The Risk Management Process

The processes outlined in the literature all follow a pattern of identification, assessment, mitigation and monitoring (AACE International, 2009). Figure 2 outlines this five-phase cycle: Identify and classify risks, assess the risks in terms of likelihood, duration and impact, avoid, prevent, reduce, transfer or protect risks, and monitor the risks as internal and external drivers evolve. The cycle is similar to the one that is used in the project risk standards (Hallikas, Karvonen, Pulkkinen, Virolainen, & Tuominen, 2004; Project Management Institute, 2017) and supplier network studies.
This paper focuses on the assessment phase of quantitative schedule risk analysis and on the mitigation phase that follows it. The combination of the two is intentional. If a mitigation measure is not capable of being expressed as a duration, probability or cost, then it cannot be evaluated and a risk assessment that is never linked to a decision will not change behavior (Zwikael & Ahn, 2011).
Resilience research adds a capability perspective to the vocabulary of risk. Beyond formal risk assessment, it identifies supply chain visibility, rapid response and a culture of collaboration as attributes that distinguish resilient from fragile chains (Christopher & Peck, 2004). For long-lead equipment, visibility means knowing the suppliers' order books, material receipts and test schedules, and responsiveness means having options to expedite or substitute when slippage is detected (Sodhi & Tang, 2012).

2.2.4. Risk in Energy and Infrastructure Supply Chains

Energy infrastructure presents distinctive risk attributes. Projects are capital intensive, technologies are specialized, and the largest components have few suppliers, so that when one supplier fails it is difficult for others to absorb the demand. There is evidence for cross-country variation in cost overruns for electricity infrastructure projects and that the size of overruns is strongly related to technology, with the largest and most complex projects the worst offenders (Ansar, Flyvbjerg, Budzier, & Lunn, 2014; Sovacool et al., 2014).
Similar patterns appear in the hydropower literature, where very large projects have been found to suffer from large and persistent overruns in cost and time, and where the authors argue that the fat-tailed distribution of outcomes undermines conventional appraisal that relies on expected values (Ansar et al., 2014; Flyvbjerg, 2006). The simulation output presented later in this paper shows the same feature for a transmission substation: most outcomes are moderately late and a few are very late.
Reference-class forecasting has been proposed as a remedy for the inside-view bias that produces such outcomes (Flyvbjerg et al., 2002). The approach is to place a project in a class of similar projects and then use the outcome distribution in the class to "calibrate" the forecast, thereby reducing the tendency to focus on the specific features of the project at hand and to ignore the track record of similar projects (Flyvbjerg et al., 2003). The reference class for transformer procurement consists of past orders with similar ratings and market conditions, and the owner's own delivery history is its most relevant part.
The supply chain view complements the statistical view with an explanation of mechanisms. Wagner and Bode (2008) found measurable differences in supply-side operational outcomes across the risk dimensions modeled in this paper, which indicates that these risks are an empirical phenomenon and not only a theoretical construct. The two views complement each other: reference-class data provide the calibration, and mechanism-based models provide the framework in which a mitigation can be examined.

2.3. Schedule Risk Analysis Methods

2.3.1. From Critical Path to PERT

The formal scheduling of networks started in the late 1950s with two parallel developments. Kelley and Walker (1959) developed the critical path method with deterministic durations, while Malcolm et al. (1959) used three-point estimates to describe uncertainty in a large defense development program, in which they introduced the program evaluation and review technique (PERT). PERT treated each activity duration as a random variable and summed the expected values along the longest path, an approximation that Van Slyke (1963) showed to be biased because a path other than the nominal critical path can turn out to be the longer one.
The bias is not a matter of technicality. If the lengths of several paths are similar, the expected duration of the project exceeds the duration of the longest expected path, because the more paths run in parallel with near-equal lengths, the more likely it is that at least one of them turns out longer than the nominal critical path (Van Slyke, 1963; Elmaghraby, 2000). Deterministic and PERT estimates are therefore specifically the type of estimates that are most misleading in procurement dominated networks.
Williams (2003) points out that the role of mathematical modeling in project management has long been debated. Models are most effective for structuring thinking and exploring scenarios, not for producing forecasts that are believed literally, and their use requires transparency and a good fit to the decision problem. That is the position taken in this paper: the model is a tool for comparison under stated assumptions, and its numbers are conditional on those assumptions.
The historical context explains why the two techniques were so closely tied to large capital programs. PERT was developed for a defense development project in which hundreds of contractors supplied components of unknown duration, which is very similar to the situation today, when many factories supply engineered electrical components. The paradox is that PERT has frequently been used in its simplified form, in which expected durations are summed along a single path, and the bias of this simplification was recognized soon after the method was introduced (Van Slyke, 1963).
The methods become concrete with three formulas. The PERT approximation gives each activity a mean and variance as in Equation (1), while the triangular distribution used in the remainder of this paper has the mean and variance in Equation (2), where a, m and b are the minimum, most likely and maximum duration of activity j (Malcolm et al., 1959).
μ j = a + 4 m + b 6 , σ j 2 = b − a 6 2
μ j = a + m + b 3 , σ j 2 = a 2 + m 2 + b 2 − am − ab − mb 18
For transformer manufacture, with a = 10, m = 13 and b = 20 months, Equation (1) yields a PERT mean of 13.7 months with a standard deviation of 1.7 months and Equation (2) yields a mean of 14.3 months, with a standard deviation of 2.1 months. The triangular mean matches the simulated base mean of 14.4 months found in Section 4, and it is 1.3 months longer than the mode, the source of the structural upward shift of expected duration that is quantified later in the paper (Van Slyke, 1963).
The merge bias identified by Van Slyke can be written as Equation (3), where X and Y are the completion times of two parallel paths (Van Slyke, 1963). For two independent chains with identical normal completion times and standard deviation σ, the expected maximum exceeds the common mean by σ/√π, about 0.56σ. With the 2.1-month standard deviation implied by the transformer manufacturing range, the expected finish is 1.2 months later than either chain alone would suggest, and every additional parallel chain enlarges the excess (Elmaghraby, 2000).
E [ max ( X ,   Y ) ]   ≥   max ( E [ X ] ,   E [ Y ] ) ; E [ max ] = μ + σ π

2.3.2. Monte Carlo Simulation

To remove the merge bias, Monte Carlo simulation resamples the activity durations repeatedly, recomputes the network for each trial and accumulates a distribution of network completion dates. Hulett (1996) proposed that simulation of the critical path schedule is the most feasible method for creating a confidence based date, while Hulett (2009) detailed the data requirements, rules for correlation treatment and interpretation. Kwak and Ingall (2007) showed in project management applications that the technique is usable by practitioners with typical software.
The typical outcome of this analysis is a histogram of finish dates, a cumulative curve and percentile markers, as shown in Figure 3 for the baseline scenario of the case model developed in Section 3. As the figure shows, the deterministic critical-path date lies far below the bulk of the simulated distribution, the median and eightieth-percentile dates lie well beyond it, and the standard deviation of the finish date is over four months. The pattern is common to risk-loaded networks, and is one of the reasons to base commitments on confidence levels instead of deterministic dates (Hulett, 2009).
The baseline statistics reported in Table 7 can be used to quantify the shape of the distribution in Figure 3. The mean energization date is 47.67 months, the standard deviation is 4.26 months, the median is 47.27 months, the 80th percentile is 50.99 months, and the deterministic critical-path date of 36.5 months lies below the first percentile of the simulated distribution. The percentiles of the distribution would follow Equation (4) if it were normal, with μ and σ the mean and standard deviation of the distribution, respectively, and zq the standard normal quantile of order q (Hulett, 2009).
Pq ≈ μ + zq σ
With z0.80 = 0.842, a normal distribution with a standard deviation of 4.26 months would have an eightieth percentile about 3.6 months above the mean, compared with 3.3 months in the simulated baseline, which is roughly 8 percent lower. The ninetieth percentile shows the opposite pattern: it lies 5.7 months above the mean in the simulation, against 5.5 months for a normal distribution (z = 1.282). The median is also 0.4 months below the mean, so the distribution is right-skewed, with a thinner body than a normal curve and a longer extreme upper tail. A normal curve would place the deterministic date, which lies 2.6 standard deviations below the mean, at about the 0.4th percentile, whereas the simulation places it below the first percentile. The normal approximation is therefore suitable for rough planning near the median and the eightieth percentile, but it understates the extreme upper tail.

2.3.3. Criticality, Sensitivity and the Critical Chain

After simulating a network, the analyst must know what activities are important. Williams (1992) defined the criticality index as the probability that the activity is on the critical path and Elmaghraby (2000) concluded that criticality is not the same as sensitivity, meaning that an activity can be very critical but not very sensitive to its own duration. Following Saltelli et al. (2008), global sensitivity methods such as rank correlation and variance-based indices give complementary information about the strength of the influence of each input.
Resource-constrained scheduling adds a further layer. Heuristics for the resource constrained project scheduling problem were reviewed by Kolisch and Hartmann (2006) and heuristics for scheduling under uncertainty were surveyed by Herroelen and Leus (2005) and they distinguished between proactive and reactive approaches, where the former adds robustness to the baseline schedule and the latter repairs it after disruption. The critical chain method of Goldratt (1997) recommends aggregated buffers rather than padded activity durations, which is similar in spirit to the confidence-based contingency used in this paper.

2.3.4. Distributional Assumptions and Expert Judgment

Following Hulett (2009), the choice of distribution shapes the results of any simulation. The triangular distribution is the workhorse of schedule risk analysis because it is derived from three numbers and is easy to explain, but its bounded tails mean that it cannot represent very rare, very large delays. Beta or lognormal distributions give longer tails but require more difficult elicitation (Kwak & Ingall, 2007). Where a decision depends on tail outcomes, the sensitivity of the results to the choice of distribution should be examined.
Expert judgment, the traditional source of inputs, is subject to well-documented biases (Hubbard, 2020). Experts tend to be overconfident and give ranges that are too narrow, and they anchor on an initial value around which they cluster their estimates. Hubbard (2020) criticizes qualitative risk scoring and argues for calibration training and feedback on past forecasts rather than more complex scales. Reviews of construction risk modeling agree that even sophisticated models are only as credible as the data and judgment on which they are based (Taroun, 2014).

2.3.5. Integrated Cost and Schedule Risk

Delay imposes costs in two ways: through time-dependent costs such as site supervision and financing, and through penalties or lost revenue. Integrating cost and schedule uncertainty in one simulation reveals correlations that separate analyses cannot show (AACE International, 2009; Hulett, 2009). In such a model each trial produces both a finish date and a total cost, so the output is a joint distribution of the two rather than two separate distributions.
The percentile check of Equation (4) applies to cost distributions in the same way as to date distributions. When a distribution is closer to lognormal, its log-scale dispersion can be recovered from two percentiles using Equation (5) (Hulett, 2009).
σ ln = ln ( P 80   /   P 50 ) z 0.80
Applied to the baseline energization-date distribution in Figure 3, with a median of 47.27 months and an eightieth percentile of 50.99 months, Equation (5) gives ln(50.99/47.27)/0.842 = 0.090, consistent with the coefficient of variation of 4.26/47.67 = 8.9 percent. When time-dependent costs are themselves uncertain, delay and burn-rate uncertainty compound, so the cost distribution has a wider log-scale dispersion than the schedule distribution that drives it (Hulett, 2009).
The joint confidence level is the percentage of trials that satisfy both the cost and the date targets, and it is usually below either of the individual confidence levels (Hulett, 2009).
If FT and FC denote the probabilities of meeting the date target and the cost target, the joint confidence level (JCL) must fall within the Fréchet bounds of Equation (6).
max(0, FT + FC − 1) ≤ JCL ≤ min(FT, FC)
The lower bound applies when cost and date outcomes are as negatively dependent as possible, the upper bound when they are perfectly positively dependent, and the product FT × FC when they are independent. The position of an observed JCL within this range shows how strongly cost depends on time, which is the information an owner needs when setting cost and schedule contingencies together (AACE International, 2009).
Earned value management complements this in the execution phase by comparing planned and actual progress, and Vanhoucke (2010) demonstrated how schedule-risk information can improve its forecasts. Combined, the two approaches enable planners to move from a probabilistic pre-award baseline to a monitoring system that signals when observed performance falls outside the simulated range (Project Management Institute, 2017).
Table 1 compares the methods discussed in this section. The comparison shows that no single technique dominates. Consistent with Kwak and Ingall (2007), deterministic scheduling is transparent but silent about risk, PERT is simple but biased, simulation is flexible but dependent on credible inputs, and critical chain methods address behavior as well as arithmetic. The model developed in this paper adopts simulation because it is the only one of these methods that can represent event-driven risks, shared drivers, and mitigation scenarios in a single framework (Herroelen & Leus, 2005; Hulett, 2009).
Another consideration is that, in supplier networks, risks tend to propagate through relationships and are not confined to a single firm (Sheffi & Rice, 2005). Hallikas et al. (2004) emphasize the need to understand risks at both the buyer and the supplier level and to identify and review them collaboratively. For an equipment order, this means regular joint reviews of factory loading, material availability and test scheduling, which turn a one-off purchase into a monitored relationship and give the buyer early notice of delay.
A key question for any of these techniques is whether they affect decision-making (Hubbard, 2020). A schedule that is created, approved and filed has little value, but one that is used to evaluate procurement options and to set contingencies for what is purchased, and when, is very useful. As with Zwikael and Ahn (2011), research on the effectiveness of risk management indicates that the benefits depend on the inclusion of risk analysis in planning and on the readiness of project leaders to act on it. The comparison of strategies in this paper is intended to demonstrate such integration.

2.4. Mitigation Strategies for Long-Lead Equipment

2.4.1. Early Procurement and Advance Ordering

Early procurement is an action that puts an order (or at least secures an order in the factory slot) before the remaining portion of the project package is finished. The idea is straightforward: starting the longest chain earlier shortens the project. In supply chain terms, it is a commitment made before uncertainty is resolved, which buys time at the expense of flexibility, and its value depends on the kind of disruption and on the cost of changing the ordering decision later (Tang & Tomlin, 2008; Tomlin, 2006).
The earliest the order can be placed is constrained by practical considerations. Technical specifications should be sufficiently detailed, financing should be secured, and the owner should be willing to take the risk of a change in design. Research on project risk planning has demonstrated that there is a need to match the planning effort with the uncertainty and complexity of the project (Atkinson et al., 2006; Zwikael & Ahn, 2011).

2.4.2. Strategic Inventory and Pooled Spares

Strategic stock turns a long lead time into a short one for the affected item, but at the cost of capital outlay, storage and obsolescence risk. Inventory theory (Silver et al., 2017) offers a starting point, but transformer spares are not a typical inventory problem, because demand is infrequent, units are costly, and compatibility matters more than quantity. One way for utilities to address the challenge is to pool spares of a common design that is stored centrally and shared, which makes it more likely that a compatible unit will be available (U.S. Department of Energy, 2022).

2.4.3. Supplier Diversification and Flexibility

Diversification lowers the risk that the failure of one supplier will affect the project. Babich et al. (2007) showed that sourcing from multiple suppliers can reduce default risk even when prices differ, while Tang and Tomlin (2008) found that a small degree of flexibility, such as a second qualified supplier or a limited capacity to switch volume, captures most of the benefit of full flexibility. Qualification costs, design interfaces and lost volume discounts offset these gains (Tomlin, 2006).

2.4.4. Contractual and Informational Measures

Contract structure influences behavior. Delivery-linked payments, liquidated damages, slot-reservation payments and performance bonds tie supplier incentives to the program, and visibility of backlog and test schedules helps the owner forecast delays. Digital monitoring technologies are increasingly discussed in the risk analytics literature as a way of improving visibility, but their added value depends heavily on the owner's ability to act on the information (Baryannis, Validi, Dani, & Antoniou, 2019; Ivanov, Dolgui, & Sokolov, 2019).
There are opportunities as well as threats when making mitigation decisions. Ordering a factory slot early responds to a threat but can also create an opportunity for an earlier start of site works or for releasing float elsewhere in the program. Risk processes that focus only on the downside neglect these opportunities, and the uncertainty management literature calls for a symmetrical treatment of risk and opportunity (Hillson, 2002; Ward & Chapman, 2003). This is reflected in the scenario analysis in Section 4, where each strategy is assessed on its net effect in reducing downside events as well as on its effect on the distribution of completion dates.

2.4.5. Risk Transfer and Contractual Allocation

Owners and suppliers share risks under contracts, and the way risk is shared affects behavior. Liquidated damages for late delivery shift some of the delay cost to the supplier, but they may also lead suppliers to prioritize orders that carry stricter liquidated damages, and they rarely compensate the owner for the actual delay costs. Research on supply chain disruptions suggests that contracts alone seldom remove the risk of single sourcing, which is why structural measures such as dual sourcing are used alongside contractual ones (Babich et al., 2007; Tomlin, 2006).
Insurance and financial instruments offer a limited form of transfer. They can cover some physical damage in transit or in the factory, but delay caused by congestion, raw-material shortage or test failure is difficult to insure on reasonable terms. Transfer is therefore treated as one option among others, considered only after avoidance and reduction, since it does not remove the inherent schedule exposure (Hillson, 2002).

2.5. Synthesis and Research Gap

Table 2 presents an overview of the major streams of literature, examples of their representation and the gaps each stream leaves for the current analysis. The pattern of the streams is consistent when taken together. Research on project scheduling has well developed tools to model stochastic networks, but only recently began to explicitly model supply side events, and research on supply chains has richer models to capture the effects of disruptions but rarely connects them to project completion dates (Fahimnia et al., 2015; Herroelen & Leus, 2005; Ivanov & Dolgui, 2020).
Three gaps follow. First, there is limited evidence available regarding schedule risk in long-lead transmission procurement, and it tends to be qualitative. Secondly, there is little or no common time and cost basis for comparing mitigation measures. Thirdly, the dependence among award delay, factory delay and shipping delay, which share common drivers, is rarely taken into account. The next section describes a method that addresses these gaps.

3. Methodology

3.1. Research Design and Evidence Protocol

3.1.1. Overall Design

The study design combines a structured synthesis of the literature with a simulation-based case analysis. The synthesis provides the conceptual framework for the risk model and provides the terms for understanding risks and mitigation options. That structure is then operationalized for the case analysis in a quantitative network model whose outputs can then be compared between strategies. As recommended by Tranfield et al. (2003), combining the two is consistent with the idea of management knowledge being constructed from transparent and replicable evidence, not from selective reading. The simulation part follows standard probabilistic scheduling practice, in which a critical path model is run many times with a defined degree of uncertainty (Hulett, 2009).
Two aspects of the design deserve emphasis. First, the case is hypothetical but realistic: it is parameterized to be representative of a typical bulk-supply substation project, and its inputs are presented as planning assumptions and not as observations from a named project. Second, the random draws used as a basis for each scenario are the same, which is a variance-reduction device that allows differences across scenarios to be attributed to the strategy and not to sampling noise.

3.1.2. Evidence Identification and Screening

Following Page et al. (2021), evidence was collated in a staged process of identification, screening, eligibility assessment and inclusion, and the flow of evidence was reported in line with the PRISMA statement. Figure 4 sets out the order of decisions followed in this study. It reports only the final number of sources retained; counts at the intermediate stages are not reported, and the diagram is included to record the order of decisions and not the numerical yield (Tranfield et al., 2003).
Eligible sources were those that focused on one or more of four themes: probabilistic project scheduling, risk and resilience of the supply chain, supply chain of grid equipment, or cost and schedule performance of infrastructure projects. Only peer-reviewed journal articles, authoritative books, and official documents from energy agencies were included and sources lacking a clear methodology or provenance were omitted (Tranfield et al., 2003). The final evidence base includes the 58 sources cited in this paper that are from the operations research, project management, supply chain management and energy policy fields, which offers triangulation across disciplines.
The information from each retained source was captured in a matrix recording its focus, method, main finding and relevance to long-lead procurement, and was then summarized into the streams in Table 2. A matrix-based abstraction makes it easier to see where the literature is dense and where it is silent, and it underpins the gap statements in Section 2.5 (Tranfield et al., 2003).

3.1.3. Scope, Boundaries and Key Assumptions

Several assumptions underpin the analysis, each of which is a deliberate simplification. Activities are assumed to begin as soon as their predecessors are complete; there is no idle time other than that represented explicitly through outages, approvals or unavailable crews. Durations are counted from the beginning of the procurement process, and the energization milestone is considered realized when commissioning tests have been passed. The network logic is finish-to-start throughout, which is the most common logic in procurement schedules and avoids the complications of lags and overlaps (Kelley & Walker, 1959).
Another set of assumptions relates to the market. The baseline assumes a congested market for heavy electrical equipment, as highlighted in recent assessments (U.S. Department of Energy, 2022); the probabilities of factory congestion and shipping delay would be lower in a slack market. The absolute level of risk matters less than the relative structure of the risk, and the robustness analysis in Section 4.5 shows how sensitive the results are to the level of risk.

3.2. Case system and Activity Network

3.2.1. System Description

The case project is a greenfield bulk supply substation with a high voltage tie line to the grid. The scope comprises a transformer package, a package of gas-insulated switchgear and circuit breakers, a shunt reactor package, protection, control and supervisory systems, site civil works and the line connection. The deliberate simplicity of the system makes the approach transferable to other utilities and contractors with similar scopes elsewhere. The energization target is defined as the deterministic critical-path time to energization rounded up to the nearest calendar month from the start of the procurement process - the contract target is set at 37 months.
The equipment classes for the case and the planning ranges adopted for each stage are summarized in Table 3. The ranges are assumptions based on the qualitative picture in the literature, where the manufacturing times of transformers and reactors are the longest and most variable, switchgear is somewhat shorter, and secondary systems are the shortest (CIGRE Working Group A2.37, 2015; U.S. Department of Energy, 2022). Any reader wanting to use the method should substitute their supplier quotations and historical data with structured expert judgment where data are less available (Hubbard, 2020).

3.2.2. Activity Network

The project is modeled as an activity-on-node network with 23 activities with their predecessors and three-point durations as given in Table 4. Procurement activities form the front end of the network and are followed by three parallel equipment chains (transformers, switchgear and reactors), each consisting of design approval, manufacture with factory acceptance testing, and shipping with customs clearance. A site chain (survey, foundations and control building) runs in parallel, and all streams converge at installation, pre-commissioning and energization.
The deterministic critical path passes through specification, tender evaluation, contract award, transformer design approval, transformer manufacture, transportation, transformer installation, pre-commissioning and energization, and its length is 36.5 months. In the deterministic case there is float in the switchgear and reactor chains, so a deterministic analysis would suggest that only the transformer chain needs attention. One of the questions the simulation answers is whether that conclusion holds under uncertainty.

3.2.3. Input Elicitation and Calibration

The credibility of a probabilistic schedule depends mainly on the quality of its inputs. Three-point estimates should be obtained from individuals with experience of similar projects, in a structured workshop in which the minimum and maximum are asked for first and the most likely value last, in order to reduce anchoring on the mode and the tendency to give overly narrow ranges. As Hubbard (2020) has noted, calibration training and comparison of forecasts with outcomes are required for any method to be trusted. In the case model, the ranges in Table 4 were made wider on the upside, in line with the evidence of optimism in infrastructure forecasting.
History-based calibration is better than blind estimation. As suggested by Flyvbjerg et al. (2003), an owner who keeps a record of the time it takes to deliver a transformer in the past can estimate the distribution of the ratio of the actual time to the planned time directly and use it as a reference class for new projects. When records are not available, the literature on the critical chain suggests that the aggregated buffers with a size derived from the project-level uncertainty are more defensible than the padded activity estimates as the latter are often absorbed by behavior (Goldratt, 1997).

3.3. Risk Register and Probabilistic Model

3.3.1. Risk Identification

To identify the risks, the categories of risk in the supply chain risk literature were combined with the activities of the network, which resulted in 10 risks. They comprise supply-side events (factory congestion, raw-material shortage and supplier failure), technical events (design approval iteration and factory test failure), logistics events (shipping and customs delay), commercial events (award delay and price renegotiation) and site events (civil works delay and right-of-way delay for the line). The classification follows the separation between supply and process or environmental risk used in empirical studies of the dimensions of supply chain risk (Wagner & Bode, 2008) and the definition of risk as a combination of scenario, likelihood and consequence (Kaplan & Garrick, 1981).

3.3.2. Quantifying Probability and Impact

Every risk is treated as an independent event with a probability of occurrence and a conditional impact. For most risks the impact is a multiplier on the duration of the affected activities, and the multiplier follows a triangular distribution with minimum, most likely and maximum values. The remaining impacts are additive delays in months: if a factory test fails, a retest period is added to the relevant manufacturing activity; if a supplier fails, a recovery period is added to the transformer manufacturing time; and in the case of price renegotiation, a period is added to the contract award. The parameters are given in Table 5. The triangular form is common when only three-point judgments can be provided, but it does not accommodate the heavier tails found in real disruptions (Hulett, 2009).
The probabilities listed in Table 5 are planning assumptions based on the condition of a congested market for heavy electrical equipment that is the focus of recent evaluations of grid supply chains (International Energy Agency, 2023; U.S. Department of Energy, 2022). The highest probabilities are given to factory congestion and award delay because they are common and because they impact multiple activities. Supplier failure is given a low likelihood and a high impact, which places it at the low-frequency, high-impact extreme that quantitative models often handle poorly.
Shared Drivers and Correlation
One distinctive aspect of the model is that an event may affect several activities at once. In other trials, for instance, it takes longer to manufacture the transformer, the switchgear, and the reactor due to factory congestion; and due to shipping delay, all three shipments take longer. Representing risks as shared drivers results in positive correlation between activity durations, without having to include an explicit correlation matrix, and avoids an underestimation of total risk that would occur if activity durations were assumed to be independent (Hulett, 2009). The correlation coefficient for these two durations for transformer and switchgear manufacture is around 0.29, which is not a strong correlation but is important, and independent sampling would remove it.
Estimation Bias and Optimism
The model also addresses the possibility of optimism bias in the estimates of the modes. Empirical research on megaprojects and electricity infrastructure has reported a long history of underestimated costs and durations, which have been attributed to psychological and strategic factors (Flyvbjerg et al., 2002; Sovacool et al., 2014). The model uses right-skewed three-point ranges, with the maximum end point being further from the mode than the minimum end point, to represent optimism, with the mean duration being greater than the modal duration even without the effects of any discrete risk event. This is in line with the reference-class approach used to correct forecasts made from the inside view (Flyvbjerg et al., 2003).

3.4. Monte Carlo Simulation Procedure

This simulation was programmed in Python and simulated 20,000 trials for each scenario. For each trial, it selects a base duration for each activity from the triangular distribution, then it selects the risk events that occur and the impacts of those events, and then applies the corresponding multipliers and additive delays to the activity durations and performs a forward pass through the network to calculate the energization date. If the network is traced backward from the last activity, the activities on the critical path in that trial can be identified, and the criticality index (Williams, 1992) is the proportion of trials in which an activity is critical.
Sensitivity was determined using the Spearman rank correlation between each uncertain input and the energization date. Rank correlation, as discussed by Saltelli et al. (2008), is robust to nonlinearity and to the skewed distributions of schedule data, and it gives a simple ordering of drivers that can be communicated to non-specialists. Results are presented as the mean, standard deviation and 10th, 50th, 80th and 90th percentiles, together with the probability of meeting the contract target and the probability of exceeding it (AACE International, 2009).

3.4.1. Mathematical Formulation

Let N be the number of trials and n be an index of a trial. The base duration bj of each activity j is drawn from a triangular distribution; for each risk k, the occurrence indicator is a random variable Bk that takes the value 1 with probability pk, and the impact of the risk is a random variable that takes the value of a multiplier Mk or an additive delay Ak. The realized duration of activity j is then defined by Equation (7) - the product is over the multiplicative risks that impact the duration of activity j and the sum is over additive risks that affect the duration of activity j (Hulett, 2009).
d j = b j ∏ k 1 + B k M k − 1 + ∑ k B k A k
Completion times are determined by the forward pass of Equation (8) in which P(j) contains the set of predecessors of j and EF(j) is the earliest finish time for j. The energization date in trial n is the earliest completion date of the last activity, Tn = EF23. The recursion visits each activity only once, with the first activity having no predecessor and hence its earliest start is zero, making the number of computation steps proportional to the number of precedence relations; this makes the procedure inexpensive, with 20,000 trials being sufficient.
EFj = maxi ∈P(j)(EFi) + dj
The summary statistics are calculated from the empirical distribution function of Equation (9), and the qth percentile is the smallest t such that the empirical distribution function is at least equal to q. The criticality index of Equation (10) is the proportion of trials where activity j is on the critical path CPn traced back from energization, and the sensitivity of the date to an input is measured by the Spearman rank correlation of Equation (11), where di is the difference between the rank of the input and the rank of the date in trial i (Elmaghraby, 2000; Saltelli et al., 2008; Williams, 1992).
F N t = 1 N ∑ n = 1 N 1 ( T n   ≤   t )
CI j = 1 N ∑ n = 1 N 1 ( j   ∈   CP n )
ρ = 1 − 6   ∑ i d i ² N ( N 2 − 1 )
Sampling error is controlled through the standard error of the mean in Equation (12), where s is the sample standard deviation. For the baseline, s = 4.26 months and N = 20,000, so the standard error is 0.030 months. The standard error of a percentile of order q is approximately the square root of q(1 − q)/N divided by the density at that percentile, which gives 0.043 months for the eightieth percentile when the normal density is used. The difference between scenarios of a few tenths of a month is thus several times the standard error.
SE = s N

3.4.2. Verification And Stability Checks

Three checks were carried out to gain confidence in the implementation. First, when all discrete risks are deactivated, the resulting distribution has a minimum close to the deterministic duration and a mean 5.4 months above the deterministic duration. This is typical of the combined effect of right-skewed estimates and merge bias in a network with many near-critical paths (Van Slyke, 1963). Second, the mean energization date varied by about 0.1 months when the same baseline run was repeated with different random seeds, and the eightieth percentile varied by a similar amount; the same was true when the number of trials in the baseline run was varied between 5,000 and 20,000. Third, in the deterministic case the critical path obtained through the backward trace was identical to the longest path calculated by hand, as expected from the critical path method (Kelley & Walker, 1959).
These checks are numerical consistency checks; they do not validate the input assumptions against field data. This type of validation will need to be based on a history of actual times taken on similar projects, and it should be a priority for organizations using this method (Hubbard, 2020).

3.4.3. Computational Implementation and Reproducibility

The model was coded in Python using vectorized sampling so that all 20,000 trials of a scenario are processed simultaneously. Fixed seed and common random numbers are employed which means that any variation between two scenarios is not due to a random variation in the random variables, but to a variation in the assumptions. Results are exported to a spreadsheet workbook in which the scenario statistics, cumulative distributions, criticality indices and sensitivity coefficients are available, as well as native spreadsheet charts.
Reproducibility is treated as a design criterion. All inputs are described in Table 3 to 6, the algorithm is described in this section, and the reporting is based on the principle that the reader should be able to repeat the analysis and reach the same conclusions within sampling error. The workbook separates out the assumptions that can be edited from the results that will be computed, and re-calculates the cost–benefit comparison if the cost of delay is changed, or if the mitigation costs are changed.

3.4.4. Statistical Treatment of Simulation Output

The main reporting statistics are percentiles of the simulated distribution, which reflect the manner of the commitments. The fiftieth percentile is the date that has an equal chance of being exceeded or met, and the eightieth and ninetieth percentiles are dates that would be met with high confidence. It is standard practice in probabilistic scheduling to report the probability of achieving the target in addition to several percentiles so that a decision maker can select an appropriate level of confidence to match a consequence of delay (AACE International, 2009).
With 20,000 trials, the sampling error of the mean is small compared with the differences between scenarios. The mean of the baseline is known to within approximately 0.03 months, a precision roughly an order of magnitude finer than the smallest difference reported between strategies. Another way to minimize the error of paired comparisons is to use common random numbers since each scenario comes from the same draws. These properties are important because differences of a few tenths of a month can then be interpreted as differences in strategy and not as noise.

3.5. Mitigation Scenarios and Economic Evaluation

3.5.1. Scenario Definitions

Four mitigation scenarios are compared with the baseline, and Table 6 defines them. The first, early award, reduces factory congestion and price renegotiation through early slot reservation, and allows design approval of transformers, switchgear and reactors to commence after a short advance award rather than after full tender evaluation. The second, a pooled strategic spare, assumes that a compatible transformer is available from a shared pool and can be released and delivered in three to seven months. The third, dual sourcing, qualifies a second supplier, which reduces the chances of congestion, supplier failure and test failure but increases design interface effort (Babich et al., 2007). The fourth combines the other three.
Each scenario is a bundle of changes to probabilities, durations and network logic, and each is evaluated with the same random draws as the baseline. Consistent with Tomlin (2006), the design of the scenarios reflects the distinction between mitigation strategies, which are put in place before a disruption, and contingency strategies, which are triggered after it. All four scenarios are mitigation measures in this sense.

3.5.2. Cost Model and Decision Metric

The economic comparison uses a simple but transparent cost model. Expected delay cost is the average delay beyond the 37-month target multiplied by an assumed cost of delay of 1.2 million USD per month (liquidated damages, financing carry, and loss of transmission revenue). The assumed mitigation costs for scenarios S1 to S4 are $0.9 million, $2.4 million, $1.1 million and $3.9 million respectively. The net benefit of a scenario is the reduction in expected delay cost relative to the baseline minus its mitigation cost. The cost parameters are indicative only, and a sensitivity analysis of the delay cost is presented in Section 4.5.3, because the ranking of strategies depends on the cost of delay.
From a formal point of view, if T* represents the target of the contract, the expected delay after the target for the scenario s is expressed by the Equation (13), in which Tn,s is the energization date of the trial n under the scenario s. The net benefit of a scenario and the delay cost at which it breaks even are given by Equations (14) and (15), in which c is the cost of delay per month, Cs is the mitigation cost and E[D0] is the expected delay of the baseline.
E [ D s ] = 1 N ∑ n = 1 N max ( T n , s − T * ,   0 )
NBs = c(E[D0] − E[Ds]) − Cs
c * s = C s E [ D 0 ] − E [ D s ]

3.5.3. Limitations Built Into the Method

Several simplifications should be acknowledged at the outset. Resource limitations are not modeled explicitly (Kolisch & Hartmann, 2006); it is assumed that installation crews and outage windows are available as required. Duration distributions are triangular and risk events are independent except for shared drivers. The model does not capture cost uncertainty beyond the delay cost. These decisions were taken to keep the model auditable, and each of them can be relaxed in an extension.

3.6. Mapping of the Methods to the Research Questions

Each research question is responded to by a particular bit of method. The deterministic critical-path duration is compared with the simulated distribution of the baseline, and the difference is broken down by running a simulation in which the individual risk events are turned off. The criticality indices indicate how often each activity is on the critical path, and the rank correlations indicate the strength of the relationship between each input or driver and the final date.
The scenario comparison is conducted with the same random draws as the baseline and each mitigation scenario is a set of changes to probabilities, durations and network logic. The schedule results are then translated into the expected delay cost and the expected net gain in the economic evaluation. Supplementary runs, with probabilities scaled up or down and spare availability changed, test the stability of the answers to the three questions.
The mapping also indicates the limits of each answer. RQ1 depends mainly on the structure of the network and the shape of the duration distributions, RQ2 on the register of events and their shared drivers, and RQ3 on the assumed effects and costs of the strategies. Readers who wish to challenge a conclusion should therefore look first at the inputs that govern the relevant question, which are documented in Table 3 to 6.

4. Results

4.1. Baseline Probabilistic Performance

4.1.1. Distribution of the Energization Date

The deterministic critical path method gives an energization date of 36.5 months and a contract target of 37 months. The probabilistic baseline tells a very different story. In 20,000 trials the average energization date is 47.7 months, the median is 47.3 months, and the 10th and 90th percentiles are 42.6 months and 53.3 months, respectively. Fewer than 1 in 100 trials reach the 37-month mark, so the chance of meeting the date promised by the deterministic schedule is practically zero. The full set of summary statistics is listed in Table 7 for the baseline and the four mitigation scenarios.
The cumulative distribution of the energization date for all five cases is shown in Figure 5. The baseline curve (shown in black) reaches a cumulative probability of 0.28 at 45 months and reaches 0.8 only at about 51 months, which means that a commitment requiring 80 percent confidence implies 14 months of contingency above the 37-month target. The spread of the distribution, with an interquartile range of about five months and a maximum trial duration of 69.5 months, indicates that the downside is significantly greater than the upside, which is typical of projects that rely on a few critical suppliers.
Table 7. Simulated energization date by scenario (months from contract start; 20,000 trials per scenario; target 37 months).
Table 7. Simulated energization date by scenario (months from contract start; 20,000 trials per scenario; target 37 months).
Scenario Mean Std dev P10 P50 P80 P90 Min Max Prob. of meeting target Mean delay vs target
S0 Baseline 47.67 4.26 42.57 47.27 50.99 53.32 36.15 69.45 0.0% 10.67
S1 Early award 44.35 3.58 40.04 44.05 47.21 49.06 34.18 66.33 0.6% 7.35
S2 Pooled spare 46.67 3.96 41.88 46.36 49.83 51.84 35.53 69.45 0.1% 9.67
S3 Dual sourcing 47.04 3.94 42.29 46.68 50.19 52.24 36.45 68.06 0.0% 10.04
S4 Combined 43.82 3.45 39.62 43.57 46.61 48.38 34.09 60.81 0.9% 6.83
Note: probability of meeting the target is the share of trials with energization at or before 37 months. 
Several quantitative checks help to put the baseline distribution in perspective. The probability that no event happens in a trial is the product in Equation (16), the three probabilities in the factory test are considered separately, and the expected number of events that occur per trial, E[K], is the sum of the probabilities. The twelve probabilities give P0 = 0.018 and E[K] = 3.23.
P 0 = ∏ k 1 − p k , E [ K ] = ∑ k p k
The result implies that 98.2 percent of trials contain at least one risk event and that the average number of events per trial is about three. Even the 1.8 percent of trials without any event still carry appreciable duration uncertainty; with all events switched off, the mean is 41.9 months, which is still well beyond the 37-month target. This is why the probability of achieving the 37-month target is below one percent, even though roughly one trial in fifty-six has no risk events.
The percentiles are close to those of a normal distribution with the same mean and standard deviation. Equation (4) with μ = 47.67 and σ = 4.26 predicts 42.2, 51.3 and 53.1 months for the tenth, eightieth and ninetieth percentiles, against simulated values of 42.6, 51.0 and 53.3 months, a difference of 0.4, −0.3 and 0.2 months. The differences are greater than the sampling error of 0.04 months, but they are small in practice, although the distribution is not exactly normal. The upper limit of 69.5 months is 5.1 standard deviations above the mean, which indicates that the extreme tail is far heavier than that of a normal distribution.

4.1.2. Sources of the Gap Between Plan and Expectation

The gap between the 36.5-month deterministic duration and the 47.7-month mean can be decomposed into two parts. If the discrete risk events are turned off and only the three-point uncertainty is kept, the mean rises to 41.9 months, which is 5.4 months above the deterministic duration; this is caused by the right-skewed duration estimates and by the merging of near-critical paths (Elmaghraby, 2000). The discrete events add a further 5.8 months. Even in a project with no identifiable risk events, about half of the expected slippage would remain, because the mathematics of uncertain networks does not preserve the modal path (Van Slyke, 1963).
The decomposition has a practical implication for risk registers. A model that includes only the three-point ranges would capture about half of the expected overrun, while a model that lists only discrete events and uses them to adjust a deterministic schedule would capture the other half. Both parts are important, and overruns on capital projects are systematic and larger than informal risk assessment suggests (Flyvbjerg et al., 2002).
In symbols, the shortfall can be written as Equation (17), where the first term is the structural component and the second the event-driven component. The simulated values are 47.67 − 36.50 = 11.17 months, made up of 41.86 − 36.50 = 5.36 months for the structural component and 47.67 − 41.86 = 5.81 months for the event-driven component, or 48 and 52 percent of the shortfall respectively.
E[T] − Tdet = Δstruct + Δevent
Typical activity-level results show the mechanism. The modal duration of transformer manufacture is 13 months, the base duration is 14.4 months (after sampling the triangular range), and the realized duration is 16.7 months (after the effects of congestion, steel shortage and test failure). Transformer shipping has a modal duration of 3 months and an average realized duration of 4.7 months, and tender evaluation and award together take 8.6 months on average against a combined modal duration of 6 months. In relative terms, therefore, slippage is larger in the procurement front end and in logistics than in manufacturing, although manufacturing slips more in absolute months.
Across the distribution there are three zones. Below about 42 months (the tenth percentile), the project benefits from favorable draws on most uncertain durations and no major events. The central range (42 to 53 months) is where combinations of moderate congestion, shipping and award delays dominate. Above 53 months, the outcome is typically driven by a supplier failure, a long test failure or compound delays in several chains. The upper tail is also where contractual penalties, financing costs and political consequences are concentrated, and it is the area that deterministic planning never shows.
Percentile targets are interpreted differently depending on the shape of the distribution. The distance between the median and the eightieth percentile is 3.7 months, and between the eightieth and ninetieth percentiles it is 2.3 months, so each additional level of confidence requires an increasingly large buffer in the tail. Moving from the 80th to the 90th percentile commitment adds 2.3 months for ten additional points of confidence, whereas the first thirty points (from the median to the 80th percentile) cost 3.7 months.
Variability should be discussed separately for each scenario. The standard deviation of the energization date falls by about 16 percent (from 4.3 to 3.6 months) under early award and by about 19 percent (to 3.5 months) under the combined strategy. A narrower distribution is beneficial in itself, because it reduces the contingency that must be held and simplifies the coordination of outage windows, financing drawdowns and generator commissioning. The effect of mitigation on the spread should therefore be considered alongside its effect on the mean.
The lower part of the distribution also shifts. The tenth percentile drops from 42.6 to 40.0 months under early award and to 39.6 months under the combined strategy, so the best outcomes improve by approximately three months. Even so, the tenth percentile under the best strategy remains about three months longer than the 36.5-month deterministic duration.

4.1.3. Probability of Meeting Intermediate Dates

The cumulative distribution at selected dates illustrates how quickly confidence accumulates. The probability of energization at 42 months is 0.07, at 46 months 0.37, at 48 months 0.57 and at 50 months 0.74, and exceeds 0.90 only at about 54 months. A lender needing a 90% chance of completion would then need to accept the "date" approximately 17 months after the deterministic date.
The slope of the cumulative curve also carries information. Between 44 and 50 months the baseline probability rises from 0.20 to 0.74, which means that most of the probability mass is concentrated in a six-month window. The compactness of the central region contrasts with the long upper tail, in which the probability rises only from 0.92 to 1.00 between 54 and 69 months, and demonstrates that the risk of very late completion is concentrated in a small number of severe combinations of events.

4.2. Criticality and Sensitivity Analysis

4.2.1. Criticality Indices

Table 8 gives the criticality index of each activity that is critical in at least 10 percent of trials (Williams, 1992). All of the front-end activities, namely specification, tender evaluation and contract award, are critical in every trial, and energization and pre-commissioning are critical in every trial or nearly so, because every chain converges on them. In 56 percent of trials the critical path runs through the transformer chain. In the remaining 44 percent it runs through the switchgear, reactor or site chains, or through the installation activities that follow them.
The same indices are presented graphically in Figure 6, and show the structure of the network. Three groups are identified: a near-certain group of critical activities at the front and back of the project; a group of activities that can be described as a transformer chain, with a value of around 0.56; and a long tail of switchgear activities, reactor and site activities, with values between 0.10 and 0.18. The tail is the part of the analysis which a deterministic analysis would miss. Switchgear and reactor activities carry float in the deterministic schedule, but under uncertainty they take over the critical path in some trials, so the project remains vulnerable to delay if only the transformer is protected.
The finding supports a cautious reading of conventional float. Computed float assumes that all modal estimates are accurate and says little about the likelihood that an apparently non-critical chain becomes critical. The criticality indices measure that likelihood directly, and they are a better guide to where management focus should go in a procurement program with several parallel equipment packages.
Summing the criticality indices of Equation (10) over all activities gives the expected number of critical activities, which is 8.82 in the baseline, compared with nine activities on the deterministic critical path. Although the totals are similar, the composition differs. Five activities have a criticality index near one (the deterministic path), four have an index of 0.56, and the remaining fourteen have a total criticality index of around 1.6.

4.2.2. Sensitivity of the Energization Date

Table 9 provides a ranking of the 12 most influential inputs, based on the magnitude of their Spearman rank correlation with the energization date. Award delay is the strongest single driver with a coefficient of 0.35, followed by the base duration of transformer manufacture (0.33), factory congestion (0.30) and shipping delay (0.27). Only around three percent of the trials fail due to supplier failure, but the impact of this failure is so great that it is ranked sixth at 0.22. The other discrete drivers are Price renegotiation, steel shortage and design approval iteration.
With N = 20,000 trials the t-statistic of a rank correlation ρ is t = ρ√((N − 2)/(1 − ρ²)). For award delay, ρ = 0.347 gives t = 52, and even the twelfth-ranked input with ρ = 0.13 gives t = 18.5, so every listed correlation is statistically significant. Significance is guaranteed in a simulation by the sample size and is therefore not the criterion of importance; the magnitude of ρ, which expresses how strongly an input and the date move together, is what ranks managerial priority.
Three observations are noted. First, four of the 12 leading inputs lie in the procurement front end: award delay, tender duration, contract negotiation duration and specification duration. They are not production risks, but they contribute directly to the energization date, which means that shortening the owner's own processes is as valuable as improving supplier performance. Second, the manufacturing time of the transformer is the most significant purely technical driver. Third, logistics risk appears twice in the ranking, as shipping delay and as transformer shipping duration, which is consistent with the importance of the port and customs interface.
A tornado analysis, which measures the days gained if each risk were removed entirely, would complement these rank correlations. The days saved by removing a risk are the marginal value of eliminating it completely, whereas the rank correlation measures the association of a risk with the outcome over the simulated range. Where the two measures agree on the ordering of the leading drivers, confidence that the prioritization is stable is higher.

4.3. Comparison of Mitigation Scenarios

4.3.1. Early award of the Long-Lead Package

Early award is the most effective single measure. It reduces the mean energization date from 47.7 to 44.4 months, a gain of 3.3 months, and lowers the eightieth percentile from 51.0 to 47.2 months. The standard deviation falls from 4.3 to 3.6 months, so the strategy narrows the distribution as well as shifting it. In Figure 5 the corresponding curve lies to the left of the baseline throughout, and at 45 months the cumulative probability rises from 0.28 to 0.60.
The mechanism is visible in the criticality and sensitivity results. Because the front-end activities are critical in every trial and carry several of the strongest sensitivities, bringing the start of equipment design forward removes a long segment of the critical path from exposure to tender delay, and the slot reservation that accompanies an advance order reduces the probability of factory congestion and price renegotiation. The strategy does not alter the manufacturing time itself, but it advances the point at which manufacture can begin.

4.3.2. Pooled Strategic Spare

The pooled spare produces a mean improvement of only 1.0 month and an eightieth-percentile improvement of 1.2 months. The modest result reflects two features of the assumption set. A compatible unit is available in only half of the trials, so that in the other half the project proceeds exactly as in the baseline, and even when a spare is available the shipping and installation steps remain. The spare is therefore powerful in the trials where it applies but dilutes quickly when averaged across all trials.
The standard deviation falls from 4.3 to 4.0 months, and the maximum outcome is unchanged at 69.5 months because the worst trials are those in which a spare is not available and several risks coincide. Pooled spares are better understood as a protection for the transformer chain than as a general schedule accelerator, and their value increases with the probability that a compatible unit exists, which is a function of standardization across the participating utilities.

4.3.3. Dual Sourcing

Dual sourcing yields the smallest improvement among the four scenarios, a reduction of 0.6 months in the mean and 0.8 months in the eightieth percentile. Lower probabilities of congestion, supplier failure and test failure are partly offset by the additional design interface effort, which lengthens each design approval by eight percent. The result is consistent with theoretical findings that the value of diversification depends on the reliability and cost differences between suppliers and that a small amount of flexibility captures much of the benefit (Babich et al., 2007; Tang & Tomlin, 2008).
The figures understate the strategic value of dual sourcing in one respect. The model treats supplier failure as a rare event with a probability of three percent in the baseline, and the benefit of diversification in this case is a reduction to one percent. Supplier failure is a heavy-tailed risk whose true probability is difficult to estimate, and a more pessimistic assumption would raise the value of a second source considerably. The qualitative lesson is that dual sourcing is a hedge against the tail rather than a way of improving the central estimate.

4.3.4. Combined Strategy

The combined strategy delivers the largest schedule benefit, reducing the mean to 43.8 months and the eightieth percentile to 46.6 months and lowering the standard deviation to 3.5 months. At 48 months the cumulative probability rises from 0.57 in the baseline to 0.88. The improvement over early award alone is only 0.5 months in the mean, however, which shows that the spare pool and the second source add little once the front-end delay has been removed. Strategies are not additive, because each acts on part of the same critical path.

4.3.5. Probability Gains at Selected Dates

The effect of the strategies is clearest when they are compared at fixed dates. At 46 months the probability of completion is 0.37 in the baseline, 0.70 under early award, 0.46 under the pooled spare, 0.42 under dual sourcing and 0.75 under the combined strategy. At 48 months the corresponding values are 0.57, 0.85, 0.66, 0.63 and 0.88, and at 50 months they are 0.74, 0.93, 0.81, 0.79 and 0.95. Early award and the combined strategy therefore nearly double the chance of finishing by 46 months, whereas the physical measures alone add less than ten percentage points.
The spread between the median and the eightieth percentile provides a compact measure of how much extra time is needed to move from an even chance to high confidence. It is 3.7 months in the baseline, 3.2 months under early award, 3.5 months under the pooled spare and dual sourcing, and 3.0 months under the combined strategy. The narrowing is modest, which shows that the main contribution of the strategies is to shift the distribution to the left, with a smaller contribution from compressing it.
A further reading concerns downside protection. At 54 months the baseline probability of completion is 0.92, whereas under early award and the combined strategy it is 0.99, so that the chance of exceeding 54 months falls from eight percent to one percent. For owners whose principal concern is avoiding extreme lateness, the reduction in the upper tail may be as valuable as the improvement in the mean.

4.4. Economic Evaluation and Integrated Cost–Schedule Interpretation

4.4.1. Cost–Schedule Interaction

Schedule risk is also cost risk, and an integrated analysis makes the link explicit (Hulett, 2009). In the case model, cost depends on the energization date through the delay-cost rate, so cost is a monotone function of date: every trial falls on a single line, cost and date are perfectly rank-correlated, and the joint confidence level equals the Fréchet upper bound of Equation (6), min(FT, FC). Real projects lie between this extreme and independence, depending on the share of time-dependent cost and the uncertainty of the burn rate (AACE International, 2009).
Including burn-rate uncertainty would loosen the relation between cost and date and make the cost distribution more skewed, because delay and cost uncertainty multiply when time-dependent costs are themselves uncertain (Hulett, 2009). This is common in transmission projects with long periods of site supervision and financing.
Applying this to the present case would require data on supervision, financing and escalation costs. The simplified delay-cost model used here captures the first-order effect and is sufficient for comparing strategies, provided that the delay cost is treated as an input to be tested.

4.4.2. Cost-Effectiveness of the Mitigation Strategies

The schedule results are combined with the assumed cost parameters and shown in Table 10. Early award reduces expected delay cost by 3.98 million dollars at a mitigation cost of 0.9 million dollars, giving a net benefit of 3.08 million dollars. The combined strategy gives a net benefit of 0.71 million dollars, with 4.61 million dollars saved and 3.9 million dollars spent. The pooled spare and dual sourcing have negative net benefits of −1.20 and −0.34 million dollars respectively at the assumed delay cost. The same comparison is presented graphically in Figure 7.
Equations (14) and (15) reproduce the figures in Table 10. For early award, E[D0] − E[D1] = 10.67 − 7.35 = 3.32 months, so the saving is 1.2 × 3.32 = 3.98 million dollars, the net benefit is 3.98 − 0.90 = 3.08 million dollars and the break-even delay cost is 0.90/3.32 = 0.27 million dollars per month. The benefit–cost ratio of Equation (18) is 4.4 for early award, 0.5 for the pooled spare, 0.7 for dual sourcing and 1.2 for the combined strategy.
BCR s = c E [ D 0 ] − E [ D s ] C s
The break-even analysis makes these rankings clearer. Early award pays for itself if the delay cost exceeds approximately 0.27 million dollars per month, and the combined strategy beats the baseline if the delay cost exceeds approximately 1.0 million dollars per month. The pooled spare breaks even at approximately 2.4 million dollars per month and dual sourcing at about 1.75 million dollars per month. An incremental step from early award to the combined strategy is warranted only if the delay cost is approximately 5.8 million dollars per month, which would be the case for a project that generates very high revenues.
The results should not be read as a rejection of spares and diversification. Their benefits in this model are confined to the pre-commissioning schedule and do not include the avoided outage costs that spares and second sources provide after energization, when a failed transformer would otherwise be replaced only after a new manufacturing cycle (CIGRE Working Group A2.37, 2015). A whole-life evaluation would add those benefits and could change the ranking.

4.4.3. Confidence-Based Contingency

Schedule contingency can be derived directly from the distribution. At the baseline, the delays beyond the target at the median, 80th and 90th percentiles are 10.3, 14.0 and 16.3 months respectively. For early award they are 7.1, 10.2 and 12.1 months, and for the combined strategy 6.6, 9.6 and 11.4 months. These values can be used to establish confidence-based commitments for the owner or lender: a common practice is to use the 80th percentile for external commitments and the 50th percentile for internal targets (AACE International, 2009).
Formally, the contingency at confidence level q is given by Equation (19), where Pq is the percentile of order q from the empirical distribution of Equation (9). For the baseline, C0.80 = 50.99 − 37 = 13.99 months, and for early award C0.80 = 47.21 − 37 = 10.21 months. The contingency released by early award is therefore 3.78 months at the eightieth percentile and 4.26 months at the ninetieth percentile, since 53.32 − 49.06 = 4.26.
Cq = Pq − T*
The results also point to where management attention is best placed. The time gained by compressing the tender and award process, securing factory capacity early and monitoring shipping is greater than what could be gained by trying to shorten manufacturing durations, which are largely governed by physical constraints. Owners who concentrate their effort on rushing factories may therefore be working on the wrong end of the network.
The results can also be put in monetary terms. The baseline expected delay cost of $12.8 million is large relative to the $0.9 million cost of early award, which explains the strong net benefit of that strategy. The finding does not depend on aggressive assumptions about the cost of time, as the finding would be marginally positive if the cost of delay was simply one quarter of the assumed cost.
The effect of shared drivers can be illustrated by the correlation between activities. In the baseline, the correlation between the sampled durations of transformer and switchgear manufacture is about 0.29, which is the consequence of the single congestion driver that acts on both. The correlation raises the probability that several chains are late at the same time, and it explains why the criticality of the non-transformer chains is higher than independent sampling would suggest.
The decomposition of delay by chain reinforces the same point. The mean realized duration of transformer manufacture exceeds its mean base duration by 2.3 months, that of reactor manufacture by 1.9 months and that of GIS manufacture by 1.2 months, while site foundations are lengthened by one month. Differences in slippage among chains are partly the effect of different multipliers and partly the effect of different event frequencies, and they mean that the criticality of a chain depends on the combination of its nominal length and its exposure to risk.
The results for the lower end of the distribution deserve a brief comment. The minimum simulated outcome in the baseline is 36.2 months, almost equal to the deterministic duration, and it occurs in a very small share of trials in which every uncertain duration is drawn near its lower bound and no event occurs. The existence of such trials confirms that the deterministic plan is not impossible, but that it corresponds to the most favorable extreme of the distribution and not to an expected outcome.
The right skew of the distribution can be quantified from the percentiles. The distance from the median to the tenth percentile is 4.7 months, whereas the distance from the median to the ninetieth percentile is 6.1 months, so that the upper tail is about thirty percent longer than the lower. The asymmetry is the signature of schedules in which delays are bounded below by technical minimum durations but unbounded above in practice, and it explains why symmetric measures such as the standard deviation understate the risk of lateness.

4.5. Robustness of the Findings

4.5.1. Scaling the Probabilities of Risk Events

To assess the sensitivity of the conclusions to the level of risk (a planning assumption), the analysis was repeated with all event probabilities multiplied by a constant factor, using the same random draws, to see how far the conclusions change. The baseline mean is 44.9 months at 50 percent of the assumed probabilities and it is 50.4 months at 1.5 times the assumed probabilities, while the baseline 80th percentile is 47.7 months at the 50 percent probability and 54.0 months at 1.5 times the probability. Even in the least risky case, the mean is more than eight months longer than the deterministic duration, thus verifying the above discussion of the structural component of slippage which is not dependent on the event register.
The benefit of early award rises with the level of risk. Its mean improvement is 2.6 months at half of the assumed probabilities, 3.3 months at the assumed values and 4.1 months at one and a half times those values, while the corresponding improvement in the eightieth percentile rises from 2.9 to 3.8 and then 4.9 months. The ordering of the strategies is therefore stable, and the strategy that delivers the most value is the one that addresses the largest and most certain segment of the critical path, as theory on the value of mitigation would predict (Tomlin, 2006).
The combined strategy retains its advantage in every case but the margin over early award alone remains small, between 0.3 and 0.7 months in the mean across the five levels of risk. The finding supports the earlier conclusion that additional measures produce diminishing returns once the largest exposure has been removed, and that the incremental measures need a high delay cost or a high tail-risk concern to be justified.

4.5.2. Availability of Pooled Spares

The pooled spare is assumed to be 50 percent available, and a supplementary run shows how critical this value is to its performance. The mean improvement rises from zero at 0 percent availability to 0.5, 1.0, 1.5 and 2.0 months at 25, 50, 75 and 100 percent availability, while the eightieth-percentile improvement reaches 2.4 months at full availability. An always-available spare would therefore deliver about 2.0 months of mean improvement, roughly 60 percent of the benefit of early award.
Because the spare replaces transformer manufacture only in the trials in which it is available, the expected date is linear in the availability α, as in Equation (20), where δ is the mean improvement when a spare is always available. The runs give δ = 1.99 months (47.67 − 45.68), so availabilities of 0.25, 0.50 and 0.75 predict improvements of 0.50, 1.00 and 1.49 months, which match the simulated values.
E[TS2](α) = E[T0] − αΔ
The sensitivity illustrates the role of standardization. Availability depends on how many utilities share a common design and on whether a spare is held within a feasible transport distance, and policy efforts to standardize transformer specifications therefore have a direct bearing on the schedule value of pooled spares. A utility that cannot influence availability should regard the spare as insurance against post-commissioning failure more than as a tool for schedule acceleration.

4.5.3. Delay Cost and Break-Even Analysis

The cost conclusions depend on the assumed cost of delay, and the break-even values in Table 10 allow them to be tested without running the simulation again. The results of the schedule are not affected by the delay cost, so that a decision maker with a different estimate can read the answer directly off the break-even column. The spare, dual sourcing and combined strategies need delay costs of approximately 1.0 to 2.4 million dollars per month or more to break even, whereas early award is justified at any plausible delay cost.
The cost of delay is seldom fixed. Liquidated damages may be capped, financing costs increase steadily, and lost profits depend on the generation or load that the new capacity would have served. For projects that connect new renewable generation or relieve congested corridors, the cost of delay may well exceed the assumed value, and the combined strategy could then be justified.

4.6. Summary of Findings by Research Question

Regarding RQ1, the deterministic critical path of 36.5 months is 11.2 months shorter than the simulated mean of 47.7 months, and the probability of meeting the 37-month target is less than one percent. About 5.4 months of the shortfall arise from the structure of the uncertain network (right-skewed estimates and the merging of near-critical paths), and about 5.8 months arise from discrete risk events. When the event probabilities are scaled between half and one and a half times their assumed values, the mean energization date rises from 44.9 to 50.4 months, so the finding does not depend on a specific level of risk.
As for RQ2, the criticality analysis shows that the transformer chain is critical in 56 percent of trials, while the switchgear, reactor and site chains are each critical in 10 to 18 percent of trials. According to the sensitivity ranking, award delay, transformer manufacturing time, factory congestion and shipping delay are the most significant drivers, with rank correlations between 0.27 and 0.35. The owner's own award process is therefore among the most important causes of delay.
For RQ3, the best and cheapest solution is early award, which decreases the mean by 3.3 months and the eightieth percentile by 3.8 months, giving a net benefit of 3.1 million dollars at the assumed delay cost of 1.2 million dollars per month and a mitigation cost of 0.9 million dollars. The pooled spare, dual sourcing and combined strategy reduce the mean by 1.0, 0.6 and 3.9 months respectively, with net benefits of −1.2, −0.3 and +0.7 million dollars at the assumed delay cost. The strategies are not additive, because they all act on the same critical path.

5. Discussion

5.1. Responses to the Research Questions

The three research questions posed in Section 1 are answered in turn in this section. For each, the quantitative answer is restated, the mechanism behind it is explained, and the answer is related to the existing literature and to the decisions that it informs. The treatment is deliberately more extensive than a summary, because the questions are intended to be the organizing thread of the paper and the discussion is where their meaning for practice is drawn out.

5.1.1. Research Question 1: How Large Is the Gap Between Plan and Expectation?

The answer to the first question is that the deterministic schedule understates the energization date by more than eleven months in the case examined, a shortfall of about 31 percent of the planned duration, and that the probability of meeting the planned date is effectively nil. The result is larger than might be expected from a network in which only about ten risks have been identified, and it is explained by the interaction of two mechanisms that operate at the same time. Neither mechanism is exotic, which is the reason the result should be taken seriously: both appear in any network with right-skewed estimates and several parallel paths.
The first mechanism is structural. When the duration estimates of activities are right-skewed, as they are whenever the worst case lies further from the most likely value than the best case, the mean of each activity exceeds its mode, and the sum of means along a path exceeds the sum of modes (Elmaghraby, 2000). The merging of parallel paths then adds a further increment, because the project finishes at the latest of several uncertain completion times and the expectation of a maximum exceeds the maximum of the expectations. The simulation attributes about 5.4 months to these effects alone, which is roughly half of the total shortfall.
The second mechanism is event-driven. Congestion in factories, shortages of materials, iterations in design approval, test failures, shipping delays and award delays each have a probability of occurring and a consequence, and their combined effect is a further 5.8 months on average. Because several events act on more than one activity at once, their effects accumulate on the same paths and are positively correlated, which widens the distribution. The pattern is consistent with the empirical record on infrastructure projects, in which delays and overruns are not isolated incidents but recurrent features (Flyvbjerg et al., 2002; Sovacool et al., 2014).
The implication for practice is that a deterministic date should be understood as the lowest conceivable estimate and not as a central estimate. Organizations that commit to such dates in contracts or financing agreements accept a high probability of breach, and the commitments are fragile for reasons unrelated to the quality of the project team. The robustness runs show that the finding is not an artifact of the assumed risk level, since even at half of the assumed probabilities the mean exceeds the deterministic duration by more than eight months.

5.1.2. Research Question 2: Which Activities and Risks Drive the Delay?

The response to the second question is that the drivers are wider than the deterministic critical path indicates. In 56 percent of trials the critical path runs through the transformer chain, and in the remaining 44 percent it runs through the switchgear, reactor or site chains, or through the installation activities that follow them. If management attention were confined to the transformer, the project would therefore be exposed in about 44 percent of trials. This follows directly from the chains being similar in length.
The sensitivity ranking shows that the front end of the procurement process is among the most influential parts of the network. Award delay has the highest rank correlation with the final date, and the base durations of tender evaluation, contract negotiation and specification are all among the twelve highest-ranked inputs. They are influential because they lie on every path and share a common driver, owner-side delay. This finding departs from the notion that the factory is the only place where schedule risk arises.
The findings also show the role of common causes. Factory congestion and shipping delay each act on all three equipment chains at once, which gives them a strong influence on the final date even though their individual probabilities are similar to those of several other events. Supplier failure has a probability of only three percent, but its impact is large, so it still ranks sixth. The ranking therefore reflects probability, breadth and severity together (Kaplan & Garrick, 1981).
The managerial interpretation is that attention should be distributed according to criticality and sensitivity under uncertainty, rather than according to float calculated from modal durations. Practical measures include tracking near-critical chains, speeding up owner decisions, recording factory loading and shipping dates in the same detail as manufacturing progress, and maintaining contingency plans for rare but significant events. Each of these corresponds to one of the leading drivers and can be done without large investment.

5.1.3. Research Question 3: Which Strategies Are Effective and Economical?

Early award is the most effective and cost-efficient option, while the other measures have value mainly under particular circumstances. It reduces the mean by 3.3 months, reduces the eightieth percentile by 3.8 months, reduces the standard deviation and gives an estimated net benefit of 3.1 million dollars at the assumed delay cost. Its break-even delay cost of about 0.27 million dollars per month means that it is justified for almost any project in which delay has a non-trivial cost.
The pooled spare and dual sourcing are less effective when judged on schedule performance alone. The spare reduces the mean by 1.0 month, and its value varies with the likelihood that a compatible unit is available, rising roughly linearly from zero to 2 months of mean improvement as availability goes from zero to certain. Dual sourcing reduces the mean by 0.6 months, because the lower probabilities of congestion, supplier failure and test failure are partly offset by the added interface effort. At their assumed costs, these measures are not worth their price in schedule terms unless the delay cost exceeds approximately 1.8 to 2.4 million dollars per month.
The combined strategy is best on all schedule metrics, reducing the mean by 3.9 months and the eightieth percentile by 4.4 months, but its incremental return over early award alone is only half a month in the mean. The additional measures have a marginal cost of $3.0 million and a break-even delay cost of approximately $5.8 million per month. Because the strategies are substitutes that act on the same critical path, an owner should sequence them by cost effectiveness.
A marginal analysis sharpens the comparison between the two best strategies. The incremental benefit–cost ratio of moving from early award to the combined strategy is given by Equation (21). With E[D1] − E[D4] = 7.35 − 6.83 = 0.52 months, c = 1.2 and C4 − C1 = 3.9 − 0.9 = 3.0 million dollars, the ratio is 0.21, which means that each additional dollar spent on the spare pool and second source returns about twenty-one cents of expected delay cost. Any rule that accepts projects with a ratio above one would therefore stop at early award.
Δ BCR = c E [ D 1 ] − E [ D 4 ] C 4 − C 1
The result should be qualified in two respects. First, the model measures benefits only up to energization, whereas spares and second sources also protect the system after commissioning, when the failure of a transformer without a spare can cause an extended outage (CIGRE Working Group A2.37, 2015). Second, the effects of the strategies, though plausible, are assumptions and should be tested with supplier evidence. Within those qualifications, the answer to RQ3 is robust to the level of risk and to the cost of delay over a wide range.

5.2. Interpretation of the Findings

5.2.1. Deterministic Dates Are Not Commitments

The most striking result is the distance between the deterministic schedule and the probabilistic expectation. A plan whose critical path is 36.5 months long has, under plausible assumptions about a congested equipment market, almost no chance of being achieved, and an eighty-percent commitment would sit more than a year later. The magnitude is comparable in kind to the overruns documented across large infrastructure programs, where optimism and strategic misrepresentation combine with genuine uncertainty to produce persistent underestimation (Ansar et al., 2014; Flyvbjerg et al., 2002). In line with Van Slyke (1963), the present analysis adds that, for long-lead equipment, a substantial part of the shortfall is arithmetic rather than behavioral: it arises whenever uncertain parallel paths merge, even if every estimate is unbiased in the modal sense.
The implication for contracts and financing is direct. A utility that signs a connection agreement on the basis of a deterministic date accepts, knowingly or not, a high probability of breach. Lenders and regulators that rely on such dates inherit the same exposure. Confidence-based dates, backed by a simulation that is open to audit, give all parties a more honest basis for allocating risk and pricing delay.

5.2.2. The Procurement Front End as a Hidden Driver

The sensitivity ranking shows that award delay, tender duration and negotiation time rank alongside manufacturing time and shipping among the strongest drivers of the final date. The finding is a reminder that the supply chain begins before the first order is placed. Owners often regard the tender as an administrative step and the factory as the source of risk, whereas the results suggest that months can be lost, or recovered, in the owner's own office. The literature on risk planning supports the point, noting that risk management effort is often misallocated relative to where uncertainty actually resides (Zwikael & Ahn, 2011).
The result also explains why early award performs so well. It does not make the factory faster; it removes the owner-side delays from the critical path and secures capacity before competing orders absorb it. In a market where the IEA has called for firm and transparent project pipelines to enable resilient supply chains, advance commitment is the project-level counterpart of a policy-level response (International Energy Agency, 2023).

5.2.3. Strategies Are Substitutes More Than Complements

The comparison of strategies shows that benefits do not add. Consistent with Tang and Tomlin (2008), early award captures most of the available improvement, and the further gain from a spare pool and a second source is small once the front-end delay has been eliminated. The explanation is structural: each measure shortens or protects a segment of the same critical path, and once the largest segment has been addressed the remaining segments are shorter and less likely to bind. The same logic appears in the theoretical literature, where the value of an additional mitigation measure declines as other measures are already in place (Tomlin, 2006).
Practitioners therefore need a sequencing rule rather than a shopping list. The results suggest beginning with process measures such as early award and slot reservation, which are cheap and effective, moving next to targeted protection of the most critical equipment through spares or diversification where the delay cost is high, and treating the full combination as appropriate only for projects whose delay cost is very large.

5.2.4. Relation to Earlier Evidence

The size of the gap between plan and expectation is consistent with the broader record. Consistent with Flyvbjerg et al. (2002), studies of large public projects document average overruns that are both substantial and persistent, and they attribute them partly to optimism and partly to the deliberate understatement of risk at the approval stage. Studies of electricity infrastructure find that overruns vary by technology, and they stress that schedule slippage and cost escalation go together because delay prolongs time-dependent costs (Ansar et al., 2014; Sovacool et al., 2014). The present analysis contributes a mechanism that is specific to procurement-dominated networks and that can be tested against project records.
The findings also connect to the resilience literature. Consistent with Sheffi and Rice (2005), the distinction between redundancy and flexibility drawn by earlier work maps onto the strategies compared here: the pooled spare and the second source are forms of redundancy, whereas early award and slot reservation are forms of flexibility in the sense that they preserve options and bring forward decisions. That the flexible measure outperformed the redundant ones within the pre-commissioning window is consistent with the finding that a modest amount of flexibility captures much of the value of mitigation (Tang & Tomlin, 2008).

5.2.5. Whole-Life and Resilience Considerations

The analysis stops at energization, but long-lead equipment continues to matter afterwards. A transformer that fails in service can interrupt supply for months if no spare exists, and survey evidence shows that failures are rare but severe in duration (CIGRE Working Group A2.37, 2015). A whole-life view would add the avoided outage cost of a spare or a second source to the schedule benefit calculated here, and could reverse the ranking of strategies for critical substations.
In line with Ivanov and Dolgui (2020), a further consideration is the interaction with network resilience at system level. Grids that depend on a few heavily loaded substations are more exposed to the failure of a single unit, and the digital and analytical tools now available for monitoring supply networks may improve the detection of such exposures before they materialize (Ivanov et al., 2019). Whether those tools reduce the probability or the impact of the risks modeled here is an empirical question that deserves attention.

5.3. Contributions to Theory and Method

The study contributes to theory by connecting two bodies of work that are usually developed in isolation. Network scheduling research supplies the mathematics of uncertain durations and criticality, and supply chain research supplies the vocabulary of disruption, resilience and mitigation. By expressing supply chain strategies as modifications of a stochastic project network, the analysis shows that the value of such strategies is conditional on where they act on the critical path, a point that models of inventory or sourcing alone cannot reveal.
The study also contributes a decomposition that is useful in method. Separating the structural component of expected delay from the event-driven component clarifies what risk registers can and cannot capture, and offers a diagnostic for assessing whether a given schedule risk analysis is likely to understate exposure. Consistent with Hulett (2009), practitioners who build simulations with only event risks, or only three-point estimates, can use the decomposition to estimate what they are missing.
A further contribution lies in the evaluation approach. Using common random numbers, reporting distributions at several confidence levels, and converting schedule effects into expected delay cost and break-even values provides a template that can be adopted for other procurement decisions, such as the choice between expediting and re-sequencing. The template is deliberately transparent so that it can be audited and challenged, in keeping with the view that models should support deliberation more than they replace it (Williams, 2003).

5.4. Positioning Against Alternative Approaches

The method adopted here can be compared with the main alternatives. The critical chain approach replaces activity-level padding with aggregated buffers and emphasizes behavioral causes of delay such as multitasking and the tendency to use up any slack (Goldratt, 1997; Herroelen & Leus, 2005). Its buffers are conceptually close to the confidence-based contingency used in this paper, but their size is typically set by rule of thumb, whereas simulation derives it from the assumed uncertainty. Consistent with Kwak and Ingall (2007), for a procurement-dominated network with event-driven risks, simulation provides a richer basis for sizing the buffer, although the behavioral insights of the critical chain remain valuable for managing the work itself.
Resource-constrained scheduling methods address a different weakness of simple network models, namely the assumption that crews, cranes and outage windows are always available (Herroelen & Leus, 2005). In line with Kolisch and Hartmann (2006), heuristics for the resource-constrained project scheduling problem have been compared extensively and perform well on benchmark instances. Combining such heuristics with stochastic durations would allow the present model to represent installation bottlenecks, which is a natural extension and one that is likely to raise the criticality of the installation activities relative to the equipment chains.
Consistent with Pettit et al. (2019), resilience-oriented approaches take a broader view of the system and emphasize capabilities such as visibility, flexibility and collaboration. They provide principles for design and management that are not captured by a schedule model, and the strategies evaluated here can be seen as instances of those principles: early award is a form of flexibility, pooled spares and second sources are forms of redundancy, and shared monitoring is a form of visibility (Christopher & Peck, 2004; Sheffi & Rice, 2005). The quantitative evaluation complements the principles by showing which of them pays off for a specific exposure.
Digital and data-driven approaches may eventually reshape how such analyses are done. Consistent with Baryannis et al. (2019), reviews of artificial intelligence in supply chain risk management point to applications in risk identification, prediction, and monitoring, while cautioning that data quality and interpretability limit adoption. For long-lead equipment, where each order is a rare event, the quantity of data is small, and structured expert judgment combined with reference classes is likely to remain the foundation for some time (Hubbard, 2020).

5.5. Portfolio-Level and Policy Reflections

Looking beyond the single project, the results suggest that the risks of long-lead procurement are correlated across a portfolio. If several utilities approach the same few factories at the same time, congestion is a common driver, and the delay that one project experiences is partly a consequence of others' orders. Consistent with International Energy Agency (2023), early commitments by one utility may improve its own position while worsening the position of others, which is a reason for coordination of procurement timing and for pipelines that are visible to manufacturers.
Policy instruments can reduce that correlation. Framework agreements that give factories predictable demand over several years, shared standards that permit the interchange of spares, and public support for capacity expansion in critical components all lower the probability or the impact of the drivers identified in the sensitivity analysis. The value of each can be assessed with the same probabilistic tools, by changing the event probabilities in the register and observing the effect on the distribution of completion dates (U.S. Department of Energy, 2022).
Regulators who approve utility investment plans might also consider whether the cost of early procurement should be treated as prudent. If advance commitments are disallowed or delayed pending full tender evaluation, the regulatory process itself becomes a source of schedule risk, and the analysis shows that this source can be one of the most influential. Aligning regulatory practice with the evidence on risk could therefore speed delivery without raising the cost of equipment.

5.6. Wider Interpretation of the Evidence

One way of interpreting the results is through the logic of option value (Tang & Tomlin, 2008). Early award does not make manufacture faster, but it preserves the option of starting design while the rest of the package is still being finalized, and it secures a place in the factory queue before competing orders arrive. The value of preserving such options is greatest when the environment is volatile, which is why the benefit of early award rises with the assumed level of risk in the robustness runs.
A second interpretation concerns information. Many of the delays modeled arise because the owner learns of a problem late: a factory falls behind, a material shortage emerges, or a shipment is held at a port. Visibility mechanisms, such as shared dashboards, milestone audits and independent inspection, convert late surprises into early warnings and give the owner time to use contingency options. The sensitivity of the final date to events that can be observed in advance suggests that investment in visibility is likely to be among the cheaper ways of reducing exposure.
A third interpretation concerns responsibility. The results show that substantial schedule risk lies with owner-side processes and with shared market conditions that neither owner nor supplier controls, while contracts typically allocate delay risk mainly to suppliers. A mismatch between where the risk arises and where it is contractually placed produces disputes, claims and defensive behavior, and an evidence-based allocation grounded in simulation could reduce them.
A final interpretation concerns the time value of information from probabilistic analysis. The simulation costs little relative to the stakes, and it can be rerun cheaply as assumptions change, so that it supports an adaptive approach to procurement in which strategies are revisited as supplier quotations, market conditions and project scope evolve. Such an approach is consistent with the view of project risk management as an ongoing process of learning and not a one-off assessment performed at approval.
A closing reflection on the three questions concerns how they relate to one another in practice. The size of the gap found in RQ1 would be of limited use if the drivers in RQ2 were diffuse and impossible to manage, and the strategies in RQ3 would be hard to choose if the drivers were not understood. It is the combination that gives the analysis its practical value: a quantified exposure, a ranked list of causes and a costed set of responses can be presented together to a project board in a single discussion.
The three answers also suggest a sequence for organizations that are new to probabilistic scheduling. They should begin by quantifying the exposure of one or two important projects, as in RQ1, so that the extent of the problem is visible. They should then use criticality and sensitivity results, as in RQ2, to find the cheap process changes that matter most, and only then evaluate physical measures such as spares and second sources, as in RQ3, where costs are higher and benefits depend more heavily on assumptions that need local evidence.

5.7. Implications for Practice

5.7.1. Owners and Utilities

For utilities, the first implication is to adopt probabilistic scheduling as a standard step in capital planning. The models are not difficult to build, and the data they require, namely three-point duration estimates and a short register of events with probabilities, can be obtained from supplier discussions and project histories. Outputs should be reported as confidence levels, not single dates, and the assumptions should be recorded so that the model can be recalibrated when actual performance becomes known.
Consistent with International Energy Agency (2023), the second implication is to treat procurement strategy as part of grid planning. Utilities that standardize equipment designs enable pooled spares and shorten design approval, and those that publish long-term demand pipelines give manufacturers the confidence to reserve capacity. Policy analyses of grid supply chains reach similar conclusions, emphasizing predictable demand signals and domestic or regional capacity as the foundation of resilience (U.S. Department of Energy, 2022).

5.7.2. EPC Contractors and Equipment Suppliers

Contractors carry schedule risk under lump-sum contracts, and the results indicate where it concentrates. The criticality analysis suggests that contractors should protect the transformer chain but also monitor the switchgear, reactor and site chains, which become critical in a substantial minority of trials. Early engagement with suppliers, transparent exchange of test schedules and shared monitoring of backlog improve visibility and give both sides earlier warning of slippage.
Suppliers have a role as well. Reliable communication about slot availability and test readiness reduces the variance of delivery dates, which is valuable to buyers even when the mean is unchanged. Contract forms that reward early information and share the cost of design change align incentives more effectively than forms that merely penalize delay.

5.7.3. Lenders, Regulators and Policymakers

For lenders and regulators, the analysis shows how a probabilistic date can be translated into a contingency allowance. Setting the commitment at the eightieth percentile, as in the contingency analysis above, provides a transparent and defensible rule, and the cost of the associated buffer can be compared with the expected cost of delay. Regulators that approve capital expenditure may wish to require probabilistic schedules for projects dominated by long-lead equipment, and to recognize advance procurement and slot reservation as prudent costs.
Consistent with U.S. Department of Energy (2022), at the policy level, the findings support the case for coordinated programs that reduce the fragility of equipment supply chains, including standardization, strategic reserves and diversified manufacturing. The analysis suggests that these measures generate value primarily by reducing tail risk, and that their benefit is therefore best assessed with distributional metrics rather than with averages.

5.7.4. Organizational and Governance Implications

Probabilistic scheduling changes conversations as well as numbers. When a project team is asked to defend a distribution rather than a date, optimism becomes visible, and the discussion shifts from whether the plan is achievable to what would have to be true for it to be achieved. Consistent with Zwikael and Ahn (2011), studies of risk planning suggest that such changes in practice are what separate projects that benefit from risk management from those that merely comply with it.
Governance arrangements should reflect the asymmetry between those who bear the delay and those who control the early decisions. The tender and award process is typically owned by procurement functions that are not accountable for the energization date, and the sensitivity results suggest that this separation of responsibility is costly. Integrating schedule risk into procurement approvals, and giving the project sponsor authority to authorize early award within an agreed envelope, would align incentives with the outcomes that matter.
Transparency with lenders and regulators is also valuable. Reporting probabilistic dates with the assumptions behind them, rather than single dates, builds credibility over time because the outcomes can be compared with the forecasts. Over a portfolio of projects, the proportion of actual dates that fall below the stated eightieth percentile should be close to eighty percent, and persistent deviations indicate bias that can be corrected (Hubbard, 2020).

5.7.5. Implications for the Energy Transition

The speed at which new transmission is delivered will help determine whether national energy targets are met. If most projects with long-lead equipment are planned on deterministic dates, systematic slippage will accumulate across the portfolio and delay the connection of generation and demand that the plans assume. Consistent with International Energy Agency (2023), portfolio-level probabilistic planning would give system planners a more realistic view of when capacity will be available and allow them to sequence investments and outages accordingly.
Equipment manufacturers and governments also have a role in shortening the tail. Multi-year framework agreements that guarantee demand allow factories to invest in capacity, standard designs shorten approval cycles, and strategic reserves protect against rare failures. Each measure acts on one of the drivers identified in the sensitivity analysis, and the combination offers a systemic counterpart to the project-level strategies evaluated in this paper.
Consistent with Ivanov et al. (2019), finally, the integration of digital monitoring into procurement offers a route to earlier detection of slippage. Real-time data on factory progress, test results and shipment status can be fed into the simulation so that the probabilistic forecast is updated continuously, giving the owner time to trigger contingency actions before the critical path is affected. Developments in analytics and artificial intelligence broaden what can be monitored, although the value of the information depends on the willingness and the contractual ability of the owner to act (Baryannis et al., 2019).

5.8. Robustness, Limitations, and Future Research

5.8.1. Limitations

The study has several limitations. The case is hypothetical, and although its structure is realistic its parameters have not been calibrated against a data set of completed projects. The triangular distributions understate tail risk, and the independence of events beyond the shared drivers is a simplification. Resource constraints, such as limited outage windows or installation crews, are omitted, and so are the effects of schedule compression, which could shorten some activities at a price (Kolisch & Hartmann, 2006; Taroun, 2014).
The cost model is also simple. It prices delay linearly, whereas real delay costs may be non-linear if liquidated damages are capped or if a missed seasonal window causes a step change in cost (Hubbard, 2020). The mitigation costs are assumed, not quoted. Finally, the reuse of illustrative figures from other projects, introduced to show the form of integrated analysis outputs, illustrates presentation formats and is not evidence about the present case.

5.8.2. Directions for Future Research

Four directions appear promising. Empirical work should gather expected and actual durations for different types of transformer, switchgear and reactor from several utilities, in order to calibrate distributions and correlations. Model extensions should draw on the literature on scheduling under uncertainty and include resource constraints and reactive recovery policies (Herroelen & Leus, 2005). Whole-life analyses should include post-commissioning outage risk so that spares are valued appropriately.
A second direction concerns the representation of dependence among risks. The shared-driver device described here models positive correlation due to common causes but not sequential dependence; for example, a late design decision may move a transformer into a busier part of the factory schedule. Such feedback can be modeled with conditional probabilities or dynamic simulation, which could be used to extend the present model.
Behavioral factors also need to be investigated. Optimism, anchoring and the desire to present good schedules influence the three-point estimates on which every simulation rests, and critics of qualitative risk practice have noted that, unless inputs are calibrated with feedback from past outcomes, sophisticated models can simply reproduce the biases of their users (Hubbard, 2020). Field experiments could test whether the discipline outlined in this paper improves forecast accuracy in practice, with estimators given feedback on their earlier forecasts and probabilistic commitments tracked over a set of projects.
Lastly, cross-region comparisons would help to determine how transferable the results are. Markets differ in their import reliance, in the number of domestic manufacturers able to meet demand and in the efficiency of their port and customs services, all of which shift the probabilities and impacts in the register (U.S. Department of Energy, 2022). With regional calibrations built from utility records, the framework could be applied by planners across U.S. regions and utilities.

6. Conclusions

Long-lead equipment determines when new transmission capacity can be energized, yet its delivery is usually scheduled as if it were certain. In this paper, a synthesis of the project-scheduling and supply chain risk literature has been combined with a Monte Carlo case analysis to quantify the exposure and to compare four mitigation strategies. In the case studied, the deterministic critical path is 36.5 months, while the probabilistic mean is 47.7 months and the eightieth percentile date is 51.0 months, and fewer than one trial in a hundred meets the 37-month target.
The three research questions have clear answers. The deterministic plan is about 11 months shorter than the expected energization date, with around 50 percent of the gap due to the structure of the network and around 50 percent to discrete events. The owner's own award process is one of the drivers, and factory congestion and shipping risk are also important, with the transformer chain critical in only 56 percent of trials. Early award is the most effective and economical mitigation, while spares and second sources are better justified by tail risk and reliability after commissioning.
About half of the expected slippage is due to the structure of uncertain networks, even if no risk events are identified, and the other half is due to discrete supply, logistics and commercial events. Criticality analysis indicates that the transformer chain is critical in only 56 percent of trials, and the switchgear, reactor and site chains are critical often enough to warrant attention. Delay in awarding the contract, transformer manufacturing time, factory congestion and shipping delay are the most significant drivers found through sensitivity analysis, and the procurement front end is among them.
Early award of the long-lead package is the most cost-effective mitigation option, giving a 3.3-month improvement in the mean and a 3.8-month improvement in the eightieth percentile at a cost of $0.9 million. In terms of schedule benefit, pooled spares and dual sourcing bring only small improvements in the pre-commissioning window; they are best supported by the protection they give against tail risks and post-commissioning failures, and when paired with early award they add little further schedule benefit.
The paper therefore recommends that utilities and contractors adopt confidence-based dates instead of single-point dates, treat the owner's own tender and award time as a risk, prioritize mitigation measures in order of cost effectiveness, and update the model with actual performance data (Hubbard, 2020). The accompanying workbook and the explicit statement of assumptions are designed to support repeatability and to invite challenge. The capacity to measure and control the risks to schedules will be a key skill of the organizations that deliver transmission capacity on time in future, as investment in the grid continues to grow and equipment markets tighten.

References

  1. AACE International. Recommended practice 57R-09: Integrated cost and schedule risk analysis using Monte Carlo simulation of a CPM model; AACE International, 2009. [Google Scholar]
  2. Ansar, A.; Flyvbjerg, B.; Budzier, A.; Lunn, D. Should we build more large dams? The actual costs of hydropower megaproject development. Energy Policy 69 2014, 43–56. [Google Scholar] [CrossRef]
  3. Atkinson, R.; Crawford, L.; Ward, S. Fundamental uncertainties in projects and the scope of project management. Int. J. Proj. Manag. 2006, 24(8), 687–698. [Google Scholar] [CrossRef]
  4. Babich, V.; Burnetas, A. N.; Ritchken, P. H. Competition and diversification effects in supply chains with supplier default risk. Manuf. Serv. Oper. Manag. 2007, 9(2), 123–146. [Google Scholar] [CrossRef]
  5. Baryannis, G.; Validi, S.; Dani, S.; Antoniou, G. Supply chain risk management and artificial intelligence: State of the art and future research directions. Int. J. Prod. Res. 2019, 57(7), 2179–2202. [Google Scholar] [CrossRef]
  6. Chopra, S.; Sodhi, M. S. Managing risk to avoid supply-chain breakdown. MIT Sloan Manag. Rev. 2004, 46(1), 53–61. Available online: https://sloanreview.mit.edu/article/managing-risk-to-avoid-supplychain-breakdown/.
  7. Christopher, M.; Peck, H. Building the resilient supply chain. Int. J. Logist. Manag. 2004, 15(2), 1–14. [Google Scholar] [CrossRef]
  8. CIGRE Working Group A2.37. Transformer reliability survey (Technical Brochure 642); CIGRE, 2015; Available online: https://www.e-cigre.org/publication/642-transformer-reliability-survey.
  9. Craighead, C. W.; Blackhurst, J.; Rungtusanatham, M. J.; Handfield, R. B. The severity of supply chain disruptions: Design characteristics and mitigation capabilities. Decis. Sci. 2007, 38(1), 131–156. [Google Scholar] [CrossRef]
  10. Elmaghraby, S. E. On criticality and sensitivity in activity networks. Eur. J. Oper. Res. 2000, 127(2), 220–238. [Google Scholar] [CrossRef]
  11. Fahimnia, B.; Tang, C. S.; Davarzani, H.; Sarkis, J. Quantitative models for managing supply chain risks: A review. Eur. J. Oper. Res. 2015, 247(1), 1–15. [Google Scholar] [CrossRef]
  12. Flyvbjerg, B. From Nobel Prize to project management: Getting risks right. Proj. Manag. J. 2006, 37(3), 5–15. [Google Scholar] [CrossRef]
  13. Flyvbjerg, B.; Bruzelius, N.; Rothengatter, W. Megaprojects and risk: An anatomy of ambition; Cambridge University Press, 2003. [Google Scholar] [CrossRef]
  14. Flyvbjerg, B.; Holm, M. S.; Buhl, S. Underestimating costs in public works projects: Error or lie? J. Am. Plan. Assoc. 2002, 68(3), 279–295. [Google Scholar] [CrossRef]
  15. Ghadge, A.; Dani, S.; Kalawsky, R. Supply chain risk management: Present and future scope. Int. J. Logist. Manag. 2012, 23(3), 313–339. [Google Scholar] [CrossRef]
  16. Goldratt, E. M. Critical chain; North River Press, 1997. [Google Scholar]
  17. Hallikas, J.; Karvonen, I.; Pulkkinen, U.; Virolainen, V.-M.; Tuominen, M. Risk management processes in supplier networks. Int. J. Prod. Econ. 2004, 90(1), 47–58. [Google Scholar] [CrossRef]
  18. Hendricks, K. B.; Singhal, V. R. An empirical analysis of the effect of supply chain disruptions on long-run stock price performance and equity risk of the firm. Prod. Oper. Manag. 2005, 14(1), 35–52. [Google Scholar] [CrossRef]
  19. Herroelen, W.; Leus, R. Project scheduling under uncertainty: Survey and research potentials. Eur. J. Oper. Res. 2005, 165(2), 289–306. [Google Scholar] [CrossRef]
  20. Hillson, D. Extending the risk process to manage opportunities. Int. J. Proj. Manag. 2002, 20(3), 235–240. [Google Scholar] [CrossRef]
  21. Ho, W.; Zheng, T.; Yildiz, H.; Talluri, S. Supply chain risk management: A literature review. Int. J. Prod. Res. 2015, 53(16), 5031–5069. [Google Scholar] [CrossRef]
  22. Hubbard, D. W. The failure of risk management: Why it's broken and how to fix it, 2nd ed.; Wiley, 2020. [Google Scholar] [CrossRef]
  23. Hulett, D. T. Schedule risk analysis simplified. PM Netw. 1996, 10(7), 23–30. [Google Scholar]
  24. Hulett, D. T. Practical schedule risk analysis; Gower, 2009. [Google Scholar]
  25. International Energy Agency. Electricity grids and secure energy transitions: Enhancing the foundations of resilient, sustainable and affordable power systems. IEA. 2023. Available online: https://www.iea.org/reports/electricity-grids-and-secure-energy-transitions.
  26. Ivanov, D.; Dolgui, A. Viability of intertwined supply networks: Extending the supply chain resilience angles towards survivability. Int. J. Prod. Res. 2020, 58(10), 2904–2915. [Google Scholar] [CrossRef]
  27. Ivanov, D.; Dolgui, A.; Sokolov, B. The impact of digital technology and Industry 4.0 on the ripple effect and supply chain risk analytics. Int. J. Prod. Res. 2019, 57(3), 829–846. [Google Scholar] [CrossRef]
  28. Kaplan, S.; Garrick, B. J. On the quantitative definition of risk. Risk Anal. 1981, 1(1), 11–27. [Google Scholar] [CrossRef]
  29. Kelley, J. E., Jr.; Walker, M. R. Critical-path planning and scheduling. Papers presented at the Eastern Joint Computer Conference, 1959; ACM; pp. 160–173. [Google Scholar] [CrossRef]
  30. Kleindorfer, P. R.; Saad, G. H. Managing disruption risks in supply chains. Prod. Oper. Manag. 2005, 14(1), 53–68. [Google Scholar] [CrossRef]
  31. Kolisch, R.; Hartmann, S. Experimental investigation of heuristics for resource-constrained project scheduling: An update. Eur. J. Oper. Res. 2006, 174(1), 23–37. [Google Scholar] [CrossRef]
  32. Kwak, Y. H.; Ingall, L. Exploring Monte Carlo simulation applications for project management. Risk Manag. 2007, 9(1), 44–57. [Google Scholar] [CrossRef]
  33. Lee, H. L.; Padmanabhan, V.; Whang, S. The bullwhip effect in supply chains. MIT Sloan Manag. Rev. 1997, 38(3), 93–102. Available online: https://sloanreview.mit.edu/article/the-bullwhip-effect-in-supply-chains/. [CrossRef]
  34. Malcolm, D. G.; Roseboom, J. H.; Clark, C. E.; Fazar, W. Application of a technique for research and development program evaluation. Oper. Res. 1959, 7(5), 646–669. [Google Scholar] [CrossRef]
  35. North American Electric Reliability Corporation. 2023 long-term reliability assessment. NERC. 2023. Available online: https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_LTRA_2023.pdf.
  36. Page, M. J.; McKenzie, J. E.; Bossuyt, P. M.; Boutron, I.; Hoffmann, T. C.; Mulrow, C. D.; et al. The PRISMA 2020 statement: An updated guideline for reporting systematic reviews. BMJ 372 2021, n71. Available online: https://www.bmj.com/content/bmj/372/bmj.n71.full.pdf.
  37. Pettit, T. J.; Croxton, K. L.; Fiksel, J. The evolution of resilience in supply chain management: A retrospective on ensuring supply chain resilience. J. Bus. Logist. 2019, 40(1), 56–65. [Google Scholar] [CrossRef]
  38. Project Management Institute. A guide to the project management body of knowledge (PMBOK guide), 6th ed.; Project Management Institute, 2017. [Google Scholar]
  39. Saltelli, A.; Ratto, M.; Andres, T.; Campolongo, F.; Cariboni, J.; Gatelli, D.; Saisana, M.; Tarantola, S. Global sensitivity analysis: The primer; Wiley, 2008. [Google Scholar] [CrossRef]
  40. Sheffi, Y.; Rice, J. B., Jr. A supply chain view of the resilient enterprise. MIT Sloan Manag. Rev. 2005, 47(1), 41–48. Available online: https://sloanreview.mit.edu/article/a-supply-chain-view-of-the-resilient-enterprise/.
  41. Silver, E. A.; Pyke, D. F.; Thomas, D. J. Inventory and production management in supply chains, 4th ed.; CRC Press, 2017. [Google Scholar] [CrossRef]
  42. Snyder, L. V.; Atan, Z.; Peng, P.; Rong, Y.; Schmitt, A. J.; Sinsoysal, B. OR/MS models for supply chain disruptions: A review. IIE Trans. 2016, 48(2), 89–109. [Google Scholar] [CrossRef]
  43. Sodhi, M. S.; Tang, C. S. Managing supply chain risk; Springer, 2012. [Google Scholar] [CrossRef]
  44. Sodhi, M. S.; Son, B.-G.; Tang, C. S. Researchers' perspectives on supply chain risk management. Prod. Oper. Manag. 2012, 21(1), 1–13. [Google Scholar] [CrossRef]
  45. Sovacool, B. K.; Gilbert, A.; Nugent, D. An international comparative assessment of construction cost overruns for electricity infrastructure. Energy Res. Soc. Sci. 3 2014, 152–160. [Google Scholar] [CrossRef]
  46. Tang, C. S. Perspectives in supply chain risk management. Int. J. Prod. Econ. 2006, 103(2), 451–488. [Google Scholar] [CrossRef]
  47. Tang, C.; Tomlin, B. The power of flexibility for mitigating supply chain risks. Int. J. Prod. Econ. 2008, 116(1), 12–27. [Google Scholar] [CrossRef]
  48. Taroun, A. Towards a better modelling and assessment of construction risk: Insights from a literature review. Int. J. Proj. Manag. 2014, 32(1), 101–115. [Google Scholar] [CrossRef]
  49. Tomlin, B. On the value of mitigation and contingency strategies for managing supply chain disruption risks. Manag. Sci. 2006, 52(5), 639–657. [Google Scholar] [CrossRef]
  50. Tranfield, D.; Denyer, D.; Smart, P. Towards a methodology for developing evidence-informed management knowledge by means of systematic review. Br. J. Manag. 2003, 14(3), 207–222. [Google Scholar] [CrossRef]
  51. U.S. Department of Energy. Electric grid supply chain review: Large power transformers and high voltage direct current systems (Supply Chain Deep Dive Assessment). U.S. Department of Energy. 2022. Available online: https://www.energy.gov/sites/default/files/2022-02/Electric%20Grid%20Supply%20Chain%20Report%20-%20Final.pdf.
  52. Van Slyke, R. M. Monte Carlo methods and the PERT problem. Oper. Res. 1963, 11(5), 839–860. [Google Scholar] [CrossRef]
  53. Vanhoucke, M. Measuring time: Improving project performance using earned value management; Springer, 2010. [Google Scholar] [CrossRef]
  54. Wagner, S. M.; Bode, C. An empirical examination of supply chain performance along several dimensions of risk. J. Bus. Logist. 2008, 29(1), 307–325. [Google Scholar] [CrossRef]
  55. Ward, S.; Chapman, C. Transforming project risk management into project uncertainty management. Int. J. Proj. Manag. 2003, 21(2), 97–105. [Google Scholar] [CrossRef]
  56. Williams, T. The contribution of mathematical modelling to the practice of project management. IMA J. Manag. Math. 2003, 14(1), 3–30. [Google Scholar] [CrossRef]
  57. Williams, T. M. Criticality in stochastic networks. J. Oper. Res. Soc. 1992, 43(4), 353–357. [Google Scholar] [CrossRef]
  58. Zwikael, O.; Ahn, M. The effectiveness of risk management: An analysis of project risk planning across industries and countries. Risk Anal. 2011, 31(1), 25–37. [Google Scholar] [CrossRef]
Figure 1. Schematic of power flow from generation through transmission and distribution substations to end users (prepared by the author).
Figure 1. Schematic of power flow from generation through transmission and distribution substations to end users (prepared by the author).
Preprints 239369 g001
Figure 2. Five-phase cycle of supply chain risk management used to organize the review (prepared by the author, based on AACE International, 2009, and Hallikas et al., 2004).
Figure 2. Five-phase cycle of supply chain risk management used to organize the review (prepared by the author, based on AACE International, 2009, and Hallikas et al., 2004).
Preprints 239369 g002
Figure 3. Baseline energization-date distribution from the author's Monte Carlo model (20,000 trials): histogram, cumulative curve, P50 and P80 markers, and the deterministic critical-path date of 36.5 months. 
Figure 3. Baseline energization-date distribution from the author's Monte Carlo model (20,000 trials): histogram, cumulative curve, P50 and P80 markers, and the deterministic critical-path date of 36.5 months. 
Preprints 239369 g003
Figure 4. PRISMA-style workflow for identification, screening and inclusion of evidence (redrawn for this study; only the final count of sources is reported).
Figure 4. PRISMA-style workflow for identification, screening and inclusion of evidence (redrawn for this study; only the final count of sources is reported).
Preprints 239369 g004
Figure 5. Cumulative distribution of the energization date under the baseline and four mitigation scenarios (Excel-based chart from the simulation workbook).
Figure 5. Cumulative distribution of the energization date under the baseline and four mitigation scenarios (Excel-based chart from the simulation workbook).
Preprints 239369 g005
Figure 6. Criticality index of network activities in the baseline simulation (Excel-based chart from the simulation workbook).
Figure 6. Criticality index of network activities in the baseline simulation (Excel-based chart from the simulation workbook).
Preprints 239369 g006
Figure 7. Expected delay-cost saving, mitigation cost and net benefit by scenario (Excel-based chart from the simulation workbook).
Figure 7. Expected delay-cost saving, mitigation cost and net benefit by scenario (Excel-based chart from the simulation workbook).
Preprints 239369 g007
Table 1. Comparison of schedule risk analysis methods and their suitability for long-lead procurement.
Table 1. Comparison of schedule risk analysis methods and their suitability for long-lead procurement.
Method Key sources Treatment of uncertainty Strengths Limitations Suitability for long-lead procurement
Critical path method (Kelley & Walker, 1959; Project Management Institute, 2017) None; single-point durations Transparent; identifies float and driving path No probability of achieving the date; ignores event risk Low as a stand-alone tool
PERT three-point method (Malcolm et al., 1959; Van Slyke, 1963) Beta-type durations; expected values summed on longest path Simple; needs only three estimates Biased low where several paths are near-critical Moderate for screening
Monte Carlo schedule simulation (Hulett, 1996, 2009; Kwak & Ingall, 2007) Sampled durations and risk events; shared drivers possible Produces confidence-based dates; supports scenario testing Depends on credible inputs; may understate tails High
Criticality and sensitivity analysis (Elmaghraby, 2000; Saltelli et al., 2008; Williams, 1992) Post-processing of simulated trials Ranks activities and drivers; guides mitigation Rank measures differ and can mislead if used alone High as complement to simulation
Critical chain buffer management (Goldratt, 1997; Herroelen & Leus, 2005) Aggregated project and feeding buffers Addresses behavior such as padding and multitasking Buffer sizing is heuristic; limited event modeling Moderate
Integrated cost–schedule risk analysis (AACE International, 2009; Hulett, 2009) Joint simulation of cost and time Reveals joint confidence and correlation Needs cost-loaded schedule and burn-rate data High where cost data exist
Earned value with schedule-risk forecasting (Vanhoucke, 2010) Updates forecasts as progress is observed Supports monitoring and early warning Less informative before award High during execution
Table 2. Synthesis of literature streams and the gaps addressed in this study.
Table 2. Synthesis of literature streams and the gaps addressed in this study.
Literature stream Representative sources Principal contribution Gap relevant to this study
Network scheduling under uncertainty (Elmaghraby, 2000; Herroelen & Leus, 2005; Kelley & Walker, 1959; Malcolm et al., 1959; Van Slyke, 1963; Williams, 1992) Formal treatment of stochastic durations, merge bias and criticality Supply-side events rarely modeled explicitly
Practical schedule risk analysis (AACE International, 2009; Hulett, 1996, 2009; Kwak & Ingall, 2007) Procedures for Monte Carlo analysis and interpretation Few applications to long-lead electrical equipment
Disruption and mitigation models (Babich et al., 2007; Kleindorfer & Saad, 2005; Tang, 2006; Tang & Tomlin, 2008; Tomlin, 2006) Value of inventory, sourcing and flexibility Effects on project completion dates seldom quantified
Resilience and visibility (Christopher & Peck, 2004; Craighead et al., 2007; Ivanov & Dolgui, 2020; Pettit et al., 2019; Sheffi & Rice, 2005) Network design, agility and recovery capabilities Limited link to capital project schedules
Reviews and analytics (Baryannis et al., 2019; Fahimnia et al., 2015; Ghadge et al., 2012; Ho et al., 2015; Snyder et al., 2016; Sodhi et al., 2012) Mapping of research clusters and trends Practice lags theory; few integrated cases
Infrastructure performance (Ansar et al., 2014; Flyvbjerg et al., 2002, 2003; Flyvbjerg, 2006; Sovacool et al., 2014) Evidence of systematic overruns and optimism bias Mitigation not linked to equipment procurement
Grid equipment supply chains (CIGRE Working Group A2.37, 2015; International Energy Agency, 2023; U.S. Department of Energy, 2022) Evidence on concentration, imports and reliability Qualitative; no schedule distribution
Project risk management practice (Atkinson et al., 2006; Hillson, 2002; Hubbard, 2020; Project Management Institute, 2017; Taroun, 2014; Ward & Chapman, 2003; Zwikael & Ahn, 2011) Standards, effectiveness evidence and critiques of scoring Qualitative registers seldom converted to dates
Table 3. Equipment classes and planning ranges adopted in the case model (minimum–mode–maximum, months).
Table 3. Equipment classes and planning ranges adopted in the case model (minimum–mode–maximum, months).
Equipment class Scope in the case project Design approval Manufacture and factory tests Shipping and customs Principal constraint
Power transformers Autotransformer package for the bulk-supply substation 2–3–5 10–13–20 2–3–6 Factory slots; electrical steel; heavy haulage
Gas-insulated switchgear and breakers High-voltage bays with circuit breakers 2–3–4 9–11–16 2–3–5 Modular design; several qualified suppliers
Shunt reactors Reactive compensation units 2–3–5 10–12–18 2–3–5 Site-specific rating; test capacity
Protection, control and SCADA Secondary systems and communications Included in supply 6–8–12 Included in supply Integration and testing after primary equipment
Civil works Survey, foundations, control building 3–4–6 (survey and design) 6–8–12 (foundations) and 4–5–8 (building) Not applicable Ground conditions; weather; access
Line materials and construction Tie-line stringing and terminal tie-in Not applicable 14–18–26 (from award) Not applicable Right-of-way; volume and logistics
Note: ranges are assumed planning values, to be replaced by supplier quotations and project histories. 
Table 4. Activity network with three-point duration estimates (months).
Table 4. Activity network with three-point duration estimates (months).
ID Activity Predecessors Min Mode Max PERT mean Group
A1 Technical specification and bid package – 3 4 6 4.17 Procurement
A2 Tender issue, bid evaluation and clarification A1 3 4 7 4.33 Procurement
A3 Contract negotiation and award A2 1 2 4 2.17 Procurement
A4 Transformer design and drawing approval A3 2 3 5 3.17 Transformer
A5 Transformer manufacture and factory tests A4 10 13 20 13.67 Transformer
A6 Transformer shipping, customs and haulage A5 2 3 6 3.33 Transformer
A7 GIS and breaker design approval A3 2 3 4 3.00 GIS
A8 GIS and breaker manufacture and factory tests A7 9 11 16 11.50 GIS
A9 GIS and breaker shipping and customs A8 2 3 5 3.17 GIS
A10 Shunt reactor design approval A3 2 3 5 3.17 Reactor
A11 Shunt reactor manufacture and factory tests A10 10 12 18 12.67 Reactor
A12 Shunt reactor shipping and customs A11 2 3 5 3.17 Reactor
A13 Protection, control and SCADA supply A3 6 8 12 8.33 Secondary
A14 Site survey, geotechnical work and detailed design A3 3 4 6 4.17 Site
A15 Foundations and civil works A14 6 8 12 8.33 Site
A16 Control building and cable trenches A15 4 5 8 5.33 Site
A17 Transformer installation and oil processing A6, A16 2 3 5 3.17 Installation
A18 GIS installation and assembly A9, A16 3 4 6 4.17 Installation
A19 Reactor installation A12, A16 1.5 2 3.5 2.17 Installation
A20 Secondary systems installation and wiring A13, A16 3 4 6 4.17 Installation
A21 Line stringing and terminal tie-in A3 14 18 26 18.67 Line
A22 Pre-commissioning tests A17, A18, A19, A20 2 3 4 3.00 Commissioning
A23 Energization and commissioning A22, A21 1 1.5 3 1.67 Commissioning
Note: durations are planning assumptions of the illustrative case; PERT mean = (min + 4 × mode + max)/6. 
Table 5. Risk register with probabilities and impact parameters (baseline scenario).
Table 5. Risk register with probabilities and impact parameters (baseline scenario).
ID Risk Affected activities Probability Simulated frequency Impact form Impact (min–mode–max)
R1 Factory slot and backlog congestion A5, A8, A11 0.40 0.40 Multiplier on duration 1.05–1.15–1.40
R2 Electrical steel and raw-material shortage A5, A11 0.25 0.25 Multiplier on duration 1.05–1.12–1.30
R3 Design approval iteration A4, A7, A10 0.50 0.50 Multiplier on duration 1.10–1.30–1.80
R4 Factory acceptance test failure and retest A5 (0.12), A8 (0.08), A11 (0.10) see activities 0.12 / 0.08 / 0.10 Additive delay (months) 1–2–4
R5 Shipping, port and customs delay A6, A9, A12 0.35 0.35 Multiplier on duration 1.20–1.60–2.50
R6 Site readiness and civil works delay A15, A16 0.45 0.45 Multiplier on duration 1.05–1.20–1.50
R7 Right-of-way and line construction delay A21 0.35 0.35 Multiplier on duration 1.10–1.30–1.70
R8 Tender evaluation and award delay A2, A3 0.40 0.40 Multiplier on duration 1.10–1.35–1.80
R9 Supplier failure A5 0.03 0.03 Additive delay (months) 6–9–12
R10 Price escalation and renegotiation A3 0.20 0.20 Additive delay (months) 1–2–3
Note: probabilities are planning assumptions. Simulated frequency is the share of 20,000 baseline trials in which the event occurred. 
Table 6. Definition of baseline and mitigation scenarios.
Table 6. Definition of baseline and mitigation scenarios.
Scenario Strategy Changes applied to the model Assumed mitigation cost (USD million)
S0 Baseline Sequential tender and award; all risks at Table 5 probabilities 0.0
S1 Early award of the long-lead package Design approvals for transformers, switchgear and reactors start after specification plus an advance award of 2–3–5 months (subject to R8); slot reservation lowers R1 from 0.40 to 0.20, R2 from 0.25 to 0.15 and R10 from 0.20 to 0.10 0.9
S2 Pooled strategic spare In 50 percent of trials a compatible spare transformer is released and delivered 3–4–7 months after contract award, replacing design approval and manufacture of the transformer; shipping and installation still apply 2.4
S3 Dual sourcing Second qualified supplier lowers R1 to 0.15, R9 from 0.03 to 0.01 and the transformer and switchgear test-failure probabilities by 30 percent; design approval durations increase by 8 percent for interface work 1.1
S4 Combined strategy S1, S2 and S3 together, with R1 further reduced to 0.10 3.9
Table 8. Criticality index of network activities in the baseline simulation (activities with index of at least 0.10).
Table 8. Criticality index of network activities in the baseline simulation (activities with index of at least 0.10).
ID Activity Group On deterministic critical path Criticality index
A1 Technical specification and bid package Procurement Yes 1.00
A2 Tender issue, bid evaluation and clarification Procurement Yes 1.00
A3 Contract negotiation and award Procurement Yes 1.00
A23 Energization and commissioning Commissioning Yes 1.00
A22 Pre-commissioning tests Commissioning Yes 0.96
A17 Transformer installation and oil processing Installation Yes 0.56
A4 Transformer design and drawing approval Transformer Yes 0.56
A5 Transformer manufacture and factory tests Transformer Yes 0.56
A6 Transformer shipping, customs and haulage Transformer Yes 0.56
A18 GIS installation and assembly Installation No 0.18
A14 Site survey, geotechnical work and detailed design Site No 0.16
A15 Foundations and civil works Site No 0.16
A16 Control building and cable trenches Site No 0.16
A10 Shunt reactor design approval Reactor No 0.14
A11 Shunt reactor manufacture and factory tests Reactor No 0.14
A12 Shunt reactor shipping and customs Reactor No 0.14
A19 Reactor installation Installation No 0.14
A7 GIS and breaker design approval GIS No 0.10
A8 GIS and breaker manufacture and factory tests GIS No 0.10
A9 GIS and breaker shipping and customs GIS No 0.10
Table 9. Ranking of inputs and drivers by Spearman rank correlation with the energization date (baseline scenario).
Table 9. Ranking of inputs and drivers by Spearman rank correlation with the energization date (baseline scenario).
Rank Input or driver Spearman correlation Interpretation
1 Tender evaluation and award delay 0.35 Owner-side award delay propagates to every equipment chain
2 Base duration: Transformer manufacture and factory tests 0.33 Largest technical duration on the deterministic critical path
3 Factory slot and backlog congestion 0.30 Shared congestion lengthens three manufacturing activities
4 Shipping, port and customs delay 0.27 Shipping and customs delay on all three equipment chains
5 Base duration: Tender issue, bid evaluation and clarification 0.23 Front-end tender duration; critical in every trial
6 Supplier failure 0.22 Rare but severe; adds 6–12 months to transformer manufacture
7 Price escalation renegotiation 0.19 Price renegotiation delays contract award
8 Electrical steel and raw-material shortage 0.19 Steel and raw-material shortage lengthens manufacture
9 Base duration: Contract negotiation and award 0.17 Contract negotiation duration; critical in every trial
10 Base duration: Technical specification and bid package 0.14 Specification and bid package duration
11 Base duration: Transformer shipping, customs and haulage 0.14 Transformer shipping and haulage duration
12 Design approval iterations 0.13 Design approval iteration across three chains
Note: R-codes refer toTable 5and A-codes toTable 4.
Table 10. Economic evaluation of mitigation scenarios at an assumed delay cost of USD 1.2 million per month (USD million unless stated).
Table 10. Economic evaluation of mitigation scenarios at an assumed delay cost of USD 1.2 million per month (USD million unless stated).
Scenario Mitigation cost Mean delay beyond target (months) Expected delay cost Saving vs baseline Net benefit Break-even delay cost (USD M/month) P80 minus target (months)
S0 Baseline 0.0 10.67 12.80 – – – 13.99
S1 Early award 0.9 7.35 8.82 3.98 3.08 0.27 10.21
S2 Pooled spare 2.4 9.67 11.60 1.20 -1.20 2.41 12.83
S3 Dual sourcing 1.1 10.04 12.05 0.76 -0.34 1.75 13.19
S4 Combined 3.9 6.83 8.19 4.61 0.71 1.02 9.61
Note: delay cost and mitigation costs are illustrative assumptions; net benefit = saving vs baseline minus mitigation cost. 
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.