Submitted:
20 October 2026
Posted:
21 October 2026
You are already at the latest version
Abstract
When the transformer is slower than the design of the substation to which it provides service, then the schedule slip sneaks in as a cost overrun. This paper defines the causes of cost overrun in bulk electric system transmission and substation projects, and distinguishes between costs caused by failure to plan and unavoidable costs caused by externalities like volatile material prices. A Monte Carlo schedule risk model for a 500 kV substation program, where long-lead equipment procurement is the link between planning error and cost growth is coupled with historical evidence from large reference classes, including 401 electricity projects, 258 transport projects and 245 dams. The ranges for transformer manufacture are based on published lead times of 5-16 months before the recent shortage and 80-210 weeks in 2024; the other inputs are explicit author assumptions. The plan is only 3% likely to be achieved under the stale pre-shortage assumptions and will take between 124 and 212 weeks to achieve under current market inputs. The transformer manufacture shows 0.95 of rank correlation with total duration. The combined effect of early slot reservation and dual sourcing and spare reallocation reduces the P80 duration by about 37 weeks. There are many exposures that are influenced by decisions that are within the control of the planning owner and many that are influenced by external factors that set the size of the penalty. A framework for governance based on leading indicators for utilities and regulators is suggested.
Keywords:
cost overrun
; long-lead equipment
; power transformers
; substations
; Monte Carlo simulation
; reference class forecasting
; transmission projects
1. Introduction
1.1. Background and Motivation
Electric transmission is being asked to carry more power, over longer distances, from more varied sources than at any time since the original interconnection of regional grids. Wind and solar resources are frequently remote from load (Battaglini et al., 2009), and the connection of those resources depends on high-voltage corridors, converter stations and substations that must be delivered within regulatory and market windows (Cain & Nelson, 2013).
The biggest restriction to such programs is no longer the availability of finance or even rights-of-way, it is the amount of time factories require to manufacture the biggest component of the plant (Gosling & Naim, 2009). Because the large power transformer is designed to fit a specific site, wound with special materials, tested individually and transported on specially designed platforms, the delivery date is likely to be the most critical component of the overall project critical path (U.S. Department of Energy, 2012). The time to put in place the lead time has increased from 5 to 16 months in the early 2010s to 80 to 210 weeks in 2024, as reported by the advisory council (National Infrastructure Advisory Council, 2024) – which is of no comparison to the time to build the transformer itself (U.S. Department of Energy, 2012).
The connection between delay and cost escalation is that the delay component of the capital project is a cost driver (Flyvbjerg et al., 2004). Owners finance, pay for extended engineering and supervision, pay for outage coordination, and pay for escalation of each component they buy late (Cantarelli et al., 2010). When key equipment is delivered a year late, the consequences are rarely limited to a year of delay. The owner bears a year of extra financing, engineering and supervision cost (Ansar et al., 2014), a year of delay against regulatory commitments, and a year in which the reliability benefit the project was meant to deliver is lost.
Pinpointing why costs increase is more useful to owners than simply noting that they increase. Shane et al. (2009) have reviewed the reasons why construction costs escalate, while Creedy et al. (2010) have tested the risk factors that contribute to cost overrun on highway delivery projects; in both cases equipment is only a small proportion of delivery cost. The opposite holds in substations and converter stations (Gosling & Naim, 2009): a few engineered items may account for a high proportion of cost and virtually all of the schedule risk (Meah & Ula, 2007), so the drivers that matter most are those that operate through procurement.
1.1.1. The Scale of the Overrun Problem
There is now a body of systematic evidence about overruns (Flyvbjerg, 2005). Flyvbjerg and colleagues came up with 258 transport infrastructure projects and found that the average difference was 28 percent between actual cost and estimated cost and that 90 percent of projects underestimated the cost (Flyvbjerg et al., 2002). In a subsequent study, Sovacool and colleagues analyzed 401 electricity projects built between 1936 and 2014 in 57 countries (Sovacool et al., 2014a) and found that these projects combined had hundreds of billions of dollars of overruns (Sovacool et al., 2014b).
Continental supergrid concepts, such as the pan-European network proposed by Battaglini et al. (2009), illustrate the scale of the issue: wind, solar and hydropower sites would be connected through a continental network (Van Hertem & Ghandhari, 2010). Such concepts show how the macro-level supply risks identified by Ho, Zheng, Yildiz and Talluri (2015) interact across jurisdictions, because procurement decisions in one country affect equipment availability in another. Further, because such networks are developed over many years (Lyneis & Ford, 2007), small differences in equipment delivery at any one point accumulate over the entire program, and a delay in one order can affect the timing of all subsequent orders that use the same corridor or the same factory slot (Williams, 1995).
Such a concept is a vision rather than a forecast, but many of its links would need converter stations, transformers and substations, so it also represents aggregated demand for long-lead equipment drawing on the same factories (Battaglini et al., 2009; Van Hertem & Ghandhari, 2010).
Transmission lines performed better than most technologies in those datasets (Eash-Gates et al., 2020), with a mean escalation far below that of nuclear reactors or hydroelectric dams, yet the favorable average conceals a wide spread and says little about the equipment-intensive substations and converter stations that accompany the lines (Sovacool et al., 2014c). A low mean also does not mean a low schedule exposure, because a project can meet its budget while missing the in-service date on which its benefits depend.
1.1.2. Why Long-Lead Equipment Deserves Separate Attention
Engineer-to-order products are different from catalog products in that the design (Gosling & Naim, 2009), procurement and production are interleaved and the customer is involved in their specification, and hence the lead time is long and uncertain (Ho et al., 2015). The attributes that make a transformer a good engineered solution (Hendricks & Singhal, 2005) are simply the attributes that keep it from being stocked, substituted or quickly re-sourced (U.S. Department of Energy, 2012).
Another risk of procurement is that it centralizes risk with a few suppliers and a few biggest items (Hendricks & Singhal, 2005). The impact of disruption increases dramatically when the supplier network is dense and some nodes are very crucial, as has been shown by the literature on supply chain disruption (Blackhurst et al., 2011). However, when a transformer order is considered one line in a bill of materials, the transmission owner is misunderstanding the nature of its exposure.
The rapid pace of change comes with a sense of urgency. The number of HVDC installations has increased and the market trends driving this growth were documented by Alassi, Bañales, Ellabban, Adam and MacIver 2019, while converter projects focus demand on a few suppliers (Flourentzou et al., 2009). If this growth is matched by the replacement requirements of an aging alternating current fleet, the average age of which is estimated at approximately forty years (U.S. Department of Energy, 2012), then the owners vie for the same factory space and all of them face each other when it comes time to replace the units.
1.2. Problem Statement
Deterministic planning schedules, based on modal or vendor quoted durations with one contingency allowance at the end, are still common in many utilities (Herroelen & Leus, 2005). In deterministic networks, the duration of network nodes is underestimated when alternative paths converge, since the later of several random durations is, on average, later than the later of their ranges of probable values (Van Slyke, 1963). The error is compounded by lead times quoted prior to the market turn, as the quotation includes assumptions that can’t be met by any supplier.
Technical explanations are supported by behavioral explanations (Lovallo & Kahneman, 2003). Planners with an ‘inside’ view of a project (Buehler et al., 1994) that see the specifics of the project tend to systematically underestimate completion time, a pattern that was initially described as the planning fallacy (Kahneman & Tversky, 1979; and later found experimentally and in practice). Its effect is that procurement risk is recognized in theory, but not in reality, and costs nothing.
The evidence of delay in construction likewise points the same way. Assaf and Al-Hejji (2006) and Sambasivan and Soon (2007) reported that planning, communication and resource deficiencies are among the top causes of delay in large scale projects and the factors of delay in large projects were ranked on the basis of relative importance by Gündüz, Nielsen and Özdemir (2013). The cost overruns that follow delay are also, to a large extent, management outcomes, just like the delay itself (Buehler et al., 1994).
1.3. Research Aim and Questions
The aim of this paper is to quantify how long-lead equipment procurement contributes to schedule and cost escalation in bulk electric system projects and to identify which part of that contribution is preventable. Three questions guide the work.
- First, what do historical data from large reference classes reveal about the frequency, magnitude and sources of escalation in electricity infrastructure?
- Second, how sensitive is the completion date of a representative substation program to the lead times of its long-lead items?
- Third, which procurement strategies reduce schedule exposure most effectively under current market conditions?
The work deliberately follows the logic of reference class thinking (Flyvbjerg, 2008), in which a forecast is anchored in the observed outcomes of comparable projects rather than in the specifics of the project at hand (Kahneman & Tversky, 1979). Simulation is then used to translate those outcomes into a project-level distribution (Goldratt, 1997), as recommended in the schedule risk literature (Malcolm et al., 1959).
The scope is bounded in three ways (Odeck, 2004). The analysis concerns high-voltage assets, represented by a 500 kV substation expansion, and the drivers considered are those that act through time and procurement, so that design-stage and political drivers enter only through their effect on lead times and scope. The evidence is drawn from published reference classes, because equipment-level delivery data are held privately, which is a limitation that Flyvbjerg, Bruzelius, and Rothengatter (2003) identified for megaproject research more generally (Flyvbjerg, 2005). Finally, the model is an illustration of structure and not a forecast for any owner.
1.4. Contribution and Structure of the Paper
This paper offers three major contributions. The first is a synthesis of the empirical record that places electricity transmission within the wider evidence on megaproject performance and sorts escalation sources into preventable and external classes. The second is a transparent Monte Carlo model whose inputs are tied to published lead-time ranges where such ranges exist and are flagged as assumptions where they do not. The third is a governance framework of leading indicators that an owner or regulator can apply before contracts are signed (Project Management Institute, 2017).
The remainder of the paper is organized as follows: Section 2 reviews the literature on overruns, behavioral explanations, schedule risk methods and supply chain risk. Section 3 describes the technical and economic context of long-lead transmission equipment. Section 4 sets out the methodology. Section 5 presents historical and simulated results. Section 6 discusses the findings, proposes the governance framework and states the limitations, and Section 7 concludes, following the structure usual in applied project-risk studies (Williams, 1995).
2. Literature Review
2.1. Cost and Schedule Overruns in Large Infrastructure
2.1.1. Empirical Evidence from Megaprojects
The modern empirical literature on overruns begins with the observation that errors in cost forecasts are not random (Flyvbjerg et al., 2003). If they were, underestimates and overestimates would offset one another across a sample, but in sample after sample the mean error is positive and large (Flyvbjerg et al., 2002). Flyvbjerg and colleagues documented this for transport projects and later showed that escalation depended strongly on the length of the implementation phase (Flyvbjerg et al., 2004), so that every additional year of delivery time increased exposure (Flyvbjerg, 2005). Table 1 summarizes the principal datasets that inform the present study.
Table 1 is the evidence base of the paper: every row reports a study, with its sample size and time period, and the result pertinent to this paper. Percentages are not interchangeable because the samples vary in sector, country and time. The 28 percent mean overrun for transport (Flyvbjerg et al., 2002), and the 96 percent for dams (Ansar et al., 2014), refer to different project types, and the mean overrun of about 8 percent for Norwegian roads (Odeck, 2004), illustrates the extent to which the institutional context can shift the result. The electricity infrastructure rows are the most relevant to substations, as they are used to provide the reference class in Section 5.1.
Later studies expanded the evidence to other sectors and included explanatory variables. Between 1934 and 2007, the authors of the 2014 study (Ansar, et al.) found that the typical cost overrun percentage was 96 percent for 245 large dams that were built, and that most dams also experienced schedule overruns (Flyvbjerg, 2014). Odeck (2004) investigated road projects in Norway and discovered a much more moderate estimate-actual spread, with the difference between estimates and actuals being, on average, just over half of the projects, and around 8 percent.
These results have been summarized in the iron law of megaprojects, which asserts that projects tend to be over budget and over time repeatedly (Flyvbjerg et al., 2003). The statement must refer to central tendency in a given population class and not be predictive of the entire population. The reference classes vary and the placement of transmission projects in them is discussed in the following subsection.
2.1.2. Evidence from Electricity Infrastructure
Sovacool and colleagues tested six hypotheses on a dataset of 401 electricity projects that together represented roughly 820 billion dollars of investment (Sovacool et al., 2014a), more than 325,000 MW of capacity and 8,495 km of transmission lines (Sovacool et al., 2014b). They found that nuclear reactors carried the highest mean escalation in percentage terms, that hydroelectric dams led in absolute dollars, and that financing, partnerships, modularity and accountability appeared to matter more than technology as such. Three of every four projects in their sample were underestimated, and only 39 projects experienced no overrun (Sovacool et al., 2014a; Sovacool et al., 2014c).
Detailed engineering studies of nuclear construction show how escalation can arise from soft costs (Eash-Gates et al., 2020), namely engineering, procurement, planning, scheduling and estimating, rather than from hardware prices (Sovacool et al., 2014a). The result is relevant to transmission because the same categories of cost dominate substation delivery, where equipment is purchased from catalogs of engineered products and installation is closely tied to outage windows. Modular, factory-built designs were associated with lower exposure in the electricity dataset (Eash-Gates et al., 2020), and a plausible mechanism is that they shift work from uncertain site conditions to controlled production (Sovacool et al., 2014b).
2.1.3. Preventable Planning Failures and Unavoidable External Factors
The distinction between preventable and unavoidable sources of escalation is central to this paper and is harder to draw than it appears (Creedy et al., 2010). The literature on construction cost escalation groups causes into categories such as scope change, design deficiency, market conditions and contractual problems, and different studies place the boundary between controllable and uncontrollable factors in different places (Odeck, 2004). Cantarelli and colleagues argued that explanations of overruns can be technical (Cantarelli et al., 2010), psychological, economic or political, and that each type implies a different remedy (Cantarelli et al., 2012).
Table 2 classifies each escalation source into those in the owner’s control and those out of control, as well as indicating the amount of exposure that is under the owner’s control. The third column is the most informative: Owner controllable exposure is full or high, but even external sources have partial control (via timing, contract form and reservation), that is why an owner’s exposure to an external event is considered to be potentially preventable (Shane et al., 2009). The final column matches the mitigation to the source, thus allowing the use of this table as a checklist for the governance structure of Section 6.3 (Cantarelli et al., 2010).
Volatility of material prices is a good illustration of the challenge. The exposure to an increase in the cost of electrical steel or copper is a part of the owner’s choice, as the owner chooses to fix a price via contract, which to buy first, and which to include escalation clauses (Cantarelli et al., 2010). The classification used in Table 2, then, differentiates between the event and the exposure, which is mostly preventable.
There have been some criticism that such a psychological or political interpretation is to be avoided. Ahiaga-Dagbui and Love (2018) argued that it was a false dichotomy to consider underestimation as either an error or a lie, and that in reality, the process of procurement of large assets leads to cost growth due to scope evolution and information surfacing as design progresses (Ahiaga-Dagbui and Smith, 2014). In this framework, the following caution is accepted: the causes of a project’s failures may be preventable or external, and they can both be present.
2.1.4. Price Volatility, Escalation Clauses and Contract Form
Price escalation is a factor that should be addressed on its own as it is most often referenced as an external factor and the most often cited external factor used to justify overruns (Creedy et al., 2010). Research on cost escalation has consistently identified materials and labor cost escalation as factors affecting the price, but has also identified design change, scope growth and contractual disputes as project management issues and not material and labor cost escalation (Shane et al., 2009). The relative weight of the two groups depends on sector and time period and no study of which the author knows has separated out the proportion of electricity-sector escalation due to commodity price changes.
The party exposed to price risk in the contract depends on the contract form (Pich et al., 2002). It can be transferred to the supplier under a fixed-price contract; it can be retained by the owner under a cost-reimbursable contract; or it can be shared between owner and supplier under an indexed contract. Each has a role, and each has an impact on the incentive to deliver on time, with a supplier with an indexed payment having less motivation to put off the decisions to produce when the price of inputs drops (Assaf & Al-Hejji, 2006). Just as in the United States, the empirical evidence on road development projects in Norway indicates that there are cost differences between the various forms of contract and that the pattern is not consistent (Ahiaga-Dagbui & Smith, 2014), further supporting the argument that contract form is a choice that has consequences.
The relationship between price and schedule is especially strong in the case of long-lead equipment (Flyvbjerg et al., 2004). A transformer ordered today will cost today’s materials cost, but be delivered years later, and the supplier will either have the exposure and price it now, or pass it on via indexation. Buyers who wait to buy because they are hoping the price will drop face a possibility of double punishment, since the longer they wait, the longer the delivery schedule will be delayed, and the market may even go up during this time (National Infrastructure Advisory Council, 2024).
2.2. Behavioral and Institutional Explanations
2.2.1. Optimism Bias and the Planning Fallacy
Kahneman and Tversky (1979) distinguished between an inside view, which builds a forecast from the specifics of the case, and an outside view, which places the case in a class of similar cases and uses the distribution of their outcomes (Lovallo & Kahneman, 2003). Experimental evidence shows that people predict completion times that are shorter than their own past experience justifies (Buehler et al., 1994), even when they are aware of that experience, and the effect persists for tasks of every size (Flyvbjerg, 2008).
Lovallo and Kahneman (2003) described the managerial version of the same bias as delusions of success, in which executives overweight plans and capabilities and underweight the distribution of outcomes for comparable ventures (Kahneman & Tversky, 1979). For procurement, the practical form is the acceptance of a vendor’s quoted lead time as a commitment rather than as a point on a distribution.
2.2.2. Strategic Misrepresentation and Lock-In
The second family of explanations focuses on incentives. In cases where the approvals and finances are limited, there is a reward for providing low costs, short schedules – and Flyvbjerg and colleagues contended that this strategy misrepresentation, combined with optimism, was the reason for the systematic pattern in their data (2002). While the argument has been challenged, the incentive structure it outlines is familiar in regulated utilities, where a set budget is used to measure the changes that follow (Cain & Nelson, 2013) and an approved budget is a yardstick for subsequent modifications (Love & Ahiaga-Dagbui, 2018).
Lock-in refers to when early choices eliminate later options (Cantarelli et al., 2010). For infrastructure projects, Cantarelli and colleagues demonstrated in the case of the Netherlands that projects with high lock-in effects were more likely to have cost overruns because by the time they had more information on costs, abandoning or redesigning the project was politically costly (Cantarelli et al., 2012). Lock-in” in a procurement sense is a situation where the transformer slot is locked up with one supplier, and the design is frozen around it, making it difficult to change suppliers if they deliver late.
2.3. Schedule Risk Analysis Methods
2.3.1. Critical Path and PERT Approaches
The critical path method, developed in the late 1950s, represents a project as a network of activities with durations and logical dependencies and identifies the longest path as the one that governs completion. The program evaluation and review technique added probabilistic durations through a three-point estimate (Malcolm et al., 1959) and assumed that the critical path would remain the same under uncertainty (Project Management Institute, 2017). Van Slyke (1963) showed with Monte Carlo experiments that this assumption leads to systematic underestimation, because several near-critical paths can each finish late, and the bias grows as the number of merging paths grows (Herroelen & Leus, 2005).
2.3.2. Monte Carlo Schedule Risk Analysis
The merge problem is addressed using a technique called Monte Carlo Analysis which involves making many trials of the activity durations drawn from a probability distribution, recomputing the network for each trial, and summarizing the distribution of activity finish dates (Lyneis & Ford, 2007). The approach provides a probability of reaching a target date as well as a ranking of the activities that have the greatest uncertainty that affect the outcome, which is more informative than a single critical path (Goldratt, 1997). The PMi has made the technique a recognized quantitative technique for evaluating schedule and cost risk while the technique is supported by commercial software products (Project Management Institute, 2017).
The sophistication of the software has less impact on the quality of the result than the discipline of the inputs, specifically how the correlation between the activities is treated and whether the risk events are modeled as discrete events, instead of continuous duration uncertainty as proposed by Williams (1995) (Hulett, 2009). The present model does just that, combining inputs with ranges that have been documented, and testing scenarios instead of a single set of numbers.
2.3.3. Critical Chain and Buffer Management
Goldratt (1997) proposed that safety time hidden in individual activity estimates is wasted through student syndrome and Parkinson’s law, and that it should instead be removed from activities and concentrated in project and feeding buffers that are managed explicitly (Herroelen & Leus, 2005). Buffer logic is attractive for procurement because feeding buffers can be placed before the point at which a long-lead item joins the main path. Its limitation is that buffers address variation, whereas the present problem includes a structural shift in the mean lead time.
2.3.4. System Dynamics and Design Structure Approaches
Rework, feedback and interdependence cause schedule growth that network models cannot represent. System dynamics models of project management capture the cycles by which undiscovered errors generate rework and by which schedule pressure reduces quality, and Lyneis and Ford (2007) surveyed the evidence for their usefulness (Williams, 1995). Browning and Eppinger (2002) modeled the architecture of development processes and showed that the pattern of iteration between tasks can change both expected cost and schedule risk (Pich et al., 2002). Table 3 compares these approaches against the needs of long-lead procurement analysis.
Table 3 contrasts the seven approaches to long-lead procurement with what long-lead procurement needs: a probability of meeting a date, a ranking of drivers and a means to test mitigation. Across the row, reading, reveals the advantages and disadvantages of each approach. Deterministic critical path analysis is easy but does not account for the merge effect of Equation 5 (Section 2.5.2), while Monte Carlo analysis provides percentiles and driver rankings, at the cost of providing credible inputs; Hulett (2009), Kwak & Ingall (2007). The reference-class entry complements the others, does not compete with them, disciplines the inputs that a simulation needs (Flyvbjerg, 2008). This is why the paper is made up of Monte Carlo analysis and reference-class evidence.
Herroelen and Leus (2005) carried out a survey of approaches to scheduling under uncertainty, such as reactive, stochastic, and fuzzy approaches, and also identified a lack of a connection between the research literature and industrial practice (Hazır, 2015). This survey also provides justification for the selection of the simple, transparent Monte Carlo model whose mechanics are explained to non-experts and can be audited by regulators in this choice.
2.4. Supply Chain Risk and Engineer-to-Order Procurement
2.4.1. Characteristics of Engineer-to-Order Supply Chains
Gosling and Naim (2009) reviewed the literature on engineer-to-order supply chain management and identified features that distinguish it from make-to-stock operations, including customer-specific design, low volumes, long lead times and strong interaction between engineering and procurement (Ho et al., 2015). Large transformers, shunt reactors and HVDC converter transformers all share those features.
2.4.1.1. Purchasing Portfolio Logic
Kraljic’s portfolio model classifies purchases by profit impact and supply risk into non-critical (Hendricks & Singhal, 2005), leverage, bottleneck and strategic items, and prescribes different strategies for each (Kraljic, 1983). Large power transformers belong in the strategic or bottleneck categories under current market conditions, because their impact on project success is high and the number of qualified suppliers is limited. Treating them with the tools suited to leverage items, such as competitive reverse auctions on price alone, therefore invites schedule risk.
2.4.1.2. Uncertainty Type and Management Response
Pich, Loch, and De Meyer (2002) argued that the appropriate response to uncertainty depends on its nature, and that complexity and ambiguity call for different approaches than simple variation (Browning & Eppinger, 2002). A lead time that varies around a stable mean can be managed with buffers, whereas a market-wide shift in capacity requires structural responses such as capacity reservation and supplier development.
2.4.2. Disruption Severity, Resilience and Risk Mitigation
Tang (2006) summarized methods of supply chain risk management into the following categories: supply management, demand management, product management and information management. Chopra and Sodhi (2004) suggested that the type of risk should match the type of mitigation since some risk reductions, such as inventory against delay, may lead to an increase in other risk, such as cost (Chopra & Sodhi, 2004). Collaboration, agility and visibility were cited as the building blocks of resilience by Christopher and Peck (2004) and were also highlighted by Blackhurst et al. (2011).
The empirical record shows that the consequences are material. When supply-chain events disrupt the chain, Hendricks and Singhal (2005) showed that there is a significant loss in shareholder value and an increase in equity risk, suggesting that markets have a high cost of such events. The disruption severity has been found to be associated with properties of the supply chain design (density, complexity, and node criticality) and with mitigation capabilities (warning and recovery) (Craighead et al., 2007; Ho et al., 2015). Blackhurst et al. (2011); Tang (2006) created an empirically derived framework for resilience that consisted of three elements: flexibility, redundancy, and visibility. The field was reviewed and the authors observed increasing interest in macro risks like natural disasters (Chopra & Sodhi, 2004) and micro risks like supplier failure (Ho et al., 2015).
2.4.3. Market and Policy Evidence on Grid Equipment
The type of institution where equipment is purchased determines the risk that owners face. Investment in transmission is constrained by the fragmented authority over siting and cost allocation, with the benefits of a line often falling to additional parties other than the party needing to obtain its approval, Joskow (2012) noted. The same type of fragmentation is seen with equipment, as utilities purchase in smaller quantities and at different times, and manufacturers have no way of knowing how much capacity is available in an invisible pipeline, and at what time.
The Federal assessments are routinely warning of the concentration and import reliance of the supply base for large transformers. The U.S. Department of Energy (2012) report detailed the physical and procurement specifications for the class and the National Infrastructure Advisory Council (2024) reported lead times of up to 210 weeks, well outside of the range reported a decade earlier. Exposure is likely structural rather than due to a passing disturbance, given the related demand from renewable connection targets (Battaglini et al., 2009).
2.5. Measuring Overruns and the Probabilistic Foundations
2.5.1. Definitions and Aggregate Metrics
Comparisons across studies are meaningful only when overruns are measured in the same way, and the literature has converged on a simple convention. Flyvbjerg, Holm, and Buhl (2002) defined cost overrun as actual out-turn cost minus estimated cost, expressed as a percentage of estimated cost, and Flyvbjerg (2005) noted that such figures are conservative when measured in constant prices. Equation 1 states the definition for project i, in which Ca is the actual cost and Ce the estimated cost at the decision to build.
Equation 1 expresses the overrun as a percentage of the original estimate. The numerator is the extra money spent in absolute terms, and dividing by the estimate Ce puts projects of very different size on a common scale, which is what allows a small substation and a multi-billion-dollar corridor to be compared on the same footing (Flyvbjerg et al., 2002). A positive value indicates an overrun, zero indicates delivery on budget and a negative value indicates an underrun. As a purely illustrative example, a substation estimated at 80 million dollars at the decision to build and completed for 92 million dollars has an overrun of (92 − 80) / 80 × 100 = 15 percent.
The equality of the reference point is as important as the equality of the formula. As the estimate is made at the time of building, when it is the most difficult to withdraw the owner’s commitment (Flyvbjerg et al. 2002), an estimate made later (e.g. when the contract is signed) will reveal a smaller overrun for the same project. There is also a hidden scale effect in percentages: nuclear projects have the highest percentage and hydroelectric projects have the highest absolute dollar value (Sovacool et al., 2014a). This equation should then be interpreted in concert with the size of the project and with the price basis which is described in the next section (Cantarelli et al., 2012).
Selection of base year and of price basis is significant. As demonstrated by Cantarelli, van Wee, Molin and Flyvbjerg (2012), the difference in the overrun figures found in different National studies partly reflects the difference in the price levels used (real prices in some countries and nominal prices in others), which can lead to apparently different performance being reported.
Averages across heterogeneous classes require weights, and Equation 2 gives the sample-weighted mean escalation, in which nk is the number of projects in class k and Ek is the mean escalation of that class (Flyvbjerg et al., 2004). Section 5.1.4 applies it to the technology data summarized in Table 8.
Equation 2 is a weighted average. The mean escalation Ek of each class is multiplied by the number of projects nk in that class, the products are summed over all K classes, and the sum is divided by the total number of projects. The weights make every project count once, so a class of 180 projects influences the result far more than a class of 36. A simple average of class means would ignore this: for the six electricity classes in Table 8 the unweighted average of the class means is about 36 percent, whereas the weighted mean is 66.3 percent, because the large nuclear class carries so many projects (Flyvbjerg et al., 2004).
The weighted mean describes the pooled sample and is not a forecast for any single project. It is pulled upward by a small number of very large overruns and can therefore differ greatly from the typical case, which is why Love and Ahiaga-Dagbui (2018) urge care in interpreting averages. For that reason the paper reports the median and the tail shares beside the mean in Section 5.1.5, and it treats pooled figures as a starting point for choosing a reference class and not as a contingency allowance (Flyvbjerg, 2008).
2.5.2. Moments and Combination of Uncertain Durations
For schedule risk models, it is important to have a short description of the duration of each uncertainty. When only 3-point estimates are available, the triangular distribution with minimum a, mode m and maximum b has a mean and variance as detailed in Equations 3 and 4 which is used in the Monte Carlo practice detailed by Kwak and Ingall (2007) and by Hulett (2009). As the expression for the mean demonstrates, a range that is right-skewed results in a longer duration than the mode and thus makes the plans based on the mode more optimistic prior to network combination.
The duration of an activity, described by a minimum a, a most likely value m and a maximum b is expected to follow this equation: 3 It is an average (mean) of the three points and each point is given equal weight. If there is a greater distance between the maximum value and the mode than the minimum value and the mode, the distribution is right-skewed, and the mode is less than the mean. Specifications, Table 7, range 12, 16, 30: mode is 16, but the mean is (12 + 16 + 30) / 3 = 19.3; so, a plan based on the mode is already three weeks short for this one activity.
The triangular form is attractive because it needs only three numbers that an engineer can defend, which is why it is common when data are scarce (Kwak & Ingall, 2007; Hulett, 2009). Its mean differs from the one used in classical PERT, which weights the mode four times and divides by six (Malcolm et al., 1959). For the current transformer range of 80, 120 and 210 weeks the PERT mean would be (80 + 4 × 120 + 210) / 6 = 128.3 weeks, about eight weeks lower than the triangular value of 136.7 weeks. The choice of distribution therefore moves the level of the results, as the robustness checks in Section 5.5 confirm, and it should be stated openly.
Equation 4 gives the variance of the same distribution, which measures how widely the duration is likely to scatter around its mean. Its square root, the standard deviation, is expressed in weeks and is easier to interpret. The variance is zero only when a, m and b are equal, that is when the activity is certain, and it grows as the range widens or as the mode moves away from the center of the range. For specification and approvals (12, 16 and 30 weeks) the numerator is 268, the variance is 268 / 18 = 14.9 weeks squared and the standard deviation is about 3.9 weeks.
Spread matters as much as the average because uncertain durations do not simply add up or cancel out when the network merges. A wide distribution on one path raises the chance that this path, and not the modal critical path, decides the finish date, which is the merge effect described by Van Slyke (1963). For this reason, Hulett (2009) and Kwak and Ingall (2007) present schedule risk results as ranges and percentiles and not as a single date. The market shift documented in Section 5.3.4 is exactly such a change, since it raises the standard deviation of transformer manufacture by a factor of about 2.8.
Combination of parallel paths is the second source of bias. If the finishing times of independent paths have distribution functions Fi, the probability that all of them finish by time t is their product, as in Equation 5, and the expected maximum of random variables is never smaller than the largest of their expectations (Van Slyke, 1963). Malcolm, Roseboom, Clark, and Fazar (1959) introduced the three-point estimate that made network evaluation practical, but the merge effect was identified only later and explains why the baseline simulation in this paper places the median 17.4 weeks beyond the modal plan.
Equation 5 states the rule for a stage that cannot start until several parallel paths have all finished. Each Fi(t) is the probability that path i has finished by time t, and if the paths are independent the probability that every one of them is done by t is the product of those probabilities. Each factor is less than or equal to one, so the product will be less than or equal to the factor that is smallest. What is the probability that all three paths complete by a given week? If each path has an 80% chance of being completed by a given week, the probability that all three are completed is 0.8 × 0.8 × 0.8 = 0.51, or approximately 50%.
This is why a schedule can be a safe path by path but have little chance of holding overall. Transformer manufacture, switchgear, reactors, protection and control supply and civil works are all initiated concurrently in the substation network and installation does not start until the slowest one of these has finished. (Van Slyke, 1963) This maximum would have a minimum expected value of the maximum of the individual expectations, and this covers the difference between the modal plan and the baseline median and the low probability of achieving the plan. As the robustness checks in Section 5.5 reveal, the independence assumption is a simplifying one: if a common cause, like capacity shortage, impacts the results of several items simultaneously, then the upper tail of the distribution is fatter.
Lastly, the importance of the driver is usually represented by the rank correlation between each input and the output. In a review of the project risk literature, Williams (1995) highlighted the importance of determining the sources of variability that are most relevant. The measure used in Section 5.3.2 is the Spearman coefficient in Equation 6 where d is the difference of the ranks of a pair of observations and N is the number of trials, and is reported by most commercial tools (Hazır, 2015).
Equation 6 is the Spearman rank correlation. Instead of using the raw durations, the trials are first converted to ranks, one set for the activity and one for total duration, and dj is the gap between the two ranks in trial j. If the two rankings agree in every trial the gaps vanish and ρs equals 1; if the rankings are exactly reversed ρs equals −1; and values near zero indicate no consistent relationship. A small example makes this concrete: if five trials give the activity ranks 1 to 5 and the total duration ranks 1, 3, 2, 4 and 5, the squared gaps sum to 2 and ρs = 1 − (6 × 2) / (5 × 24) = 0.90.
Ranks are preferred to raw values because the link between one activity and total duration is monotone but not linear. A longer activity pushes the finish date later only when it lies on the critical path, and the input distributions are skewed. A rank-based measure is unaffected by both features (Hulett, 2009; Kwak & Ingall, 2007) and is reported by most commercial tools (Hazır, 2015). It shows how strongly an activity moves with the finish date and not how many weeks it adds, so it should be read as a ranking of drivers (Williams, 1995). In Table 10 a value of 0.951 means that the ranking of transformer manufacture follows that of total duration almost trial by trial, while values near zero-mark activities with little bearing on the end date.
2.6. Delay Evidence from Construction and the Research Gap
Research on construction delay provides a list of delay factors that can be added to the literature on megaproject construction. Assaf and Al-Hejji (2006) conducted a study on the large projects in Saudi Arabia and found that delays were an issue in most projects, where owner and contractor related causes were significant. Sambasivan and Soon (2007) came up with comparable findings for Malaysia, and identified poor contractor planning, site management, material shortages and equipment problems as the major causes (Sambasivan & Soon, 2007). A relative importance index was used to quantify the delay factors in Turkey by Gündüz et al. (2013) and the evidence was synthesized by Zidane and Andersen (2018) into a set of universal delay factors that are common across countries (Gündüz et al., 2013).
The similarity is that even though all these delay factors are present, they group around planning (Assaf & Al-Hejji, 2006), and management decisions as communication and resource availability are present and dominate, the weather and the regulation are present but rare (Zidane & Andersen, 2018). But much of the literature is not of relevance to the electricity sector where the supply side is concentrated and the demand side is policy-driven. While there has been research on siting and permitting transmission lines and their public acceptance (Cain & Nelson, 2013), there is limited research to date on how delays incurred during the siting and permitting process interact with delays in equipment procurement (Vajjhala & Fischbeck, 2007). The paper aims to address this gap by quantifying procurement-driven schedule exposure in transmission and substation projects, and to test mitigation options against that exposure.
3. Technical and Economic Context of Long-Lead Transmission Equipment
3.1. Equipment Classes and Lead-Time Structure
Bulk electric system projects combine linear assets, such as overhead lines and cables, with nodal assets, such as substations and converter stations, and the two have very different schedule behavior (Vajjhala & Fischbeck, 2007). Lines are dominated by right-of-way, permitting and construction productivity, whereas substations are dominated by the delivery and commissioning of a small number of engineered items (Joskow, 2012). Table 4 lists the principal long-lead equipment classes and the features that make each of them a candidate for the critical path.
Table 4 ranks equipment by how it threatens the schedule and not by cost. The second column names what makes each item slow, the third describes what that means for the critical path and the fourth states what an owner can do about it. Large power transformers head the table because design, core steel supply, winding, testing and transport follow one another and are specific to each site (U.S. Department of Energy, 2012), whereas structures, conductors and hardware are catalog purchases that stay off the critical path unless scope changes (Gosling & Naim, 2009). The pattern explains why the simulation in Section 5.3 concentrates on transformer manufacture.
The classification in Table 4 is not exhaustive, but it covers the items that most frequently appear in utility experience as schedule drivers. Owners who maintain a register of such items (Kraljic, 1983), with current quoted lead times and the date each quote was last confirmed, hold information that most project schedules lack (Project Management Institute, 2017).
3.1.1. Large Power Transformers
The federal assessment of large power transformers is a broad definition for a transformer of 100 MVA or greater (Gosling & Naim, 2009) and it describes a procurement and manufacturing process that consists of different phases, including design, procurement of electrical steel, winding, core assembly, tanking, testing and transport. (U.S. Department of Energy, 2012) According to the same assessment report, lead times for the previous shortage were approximately 5 to 16 months (U.S. Department of Energy, 2012) and hundreds of tons of units are shipped by specialized rail or road transport, which increases the time (U.S. Department of Energy, 2012).
A later in-depth study by the National Infrastructure Advisory Council referenced market analysis that average power transformer lead times were averaging around 120 weeks for 2024, and up to 210 weeks for large substation and generator step up units. One utility was reported to have disclosed a wait of five years for new orders (National Infrastructure Advisory Council, 2024; U.S. Department of Energy, 2012). Lack of domestically manufactured equipment and critical components was identified as a contributor to this (Craighead et al., 2007) and this is considered a threat to grid reliability and to the rate of connection of new generation (National Infrastructure Advisory Council, 2024).
The scope of change should be emphasized (Hendricks & Singhal, 2005). A 10-fold increase in lead time is a significant increase which a traditional contingency cannot absorb and would invalidate any schedule that is derived from historical durations. In this paper the market shift, as defined by the two published ranges, is treated as an input to the scenarios, excluding the impact of the market shift from all other scenario input values (Goldratt, 1997).
3.1.2. Gas-Insulated Switchgear, Circuit Breakers and Reactors
Gas-insulated switchgear and high-voltage circuit breakers are produced in series but are configured per project, which gives them shorter and more predictable lead times than transformers in normal markets (Chopra & Sodhi, 2004). Under conditions of high demand, however, factory slots are rationed and the same configuration step that allows customization becomes a source of delay (Gosling & Naim, 2009). Shunt reactors share the manufacturing base and many of the materials of transformers (Tang, 2006), and the competition for capacity means that a rise in transformer lead times is typically accompanied by a rise in reactor lead times (U.S. Department of Energy, 2012).
3.1.3. Protection, Control and Communication Systems
Protection, control and communication equipment has short manufacturing times but long engineering, factory acceptance and integration times, and its schedule risk is therefore concentrated in specification and testing instead of in production. The power system can be viewed in layers, from generation through transmission, substations and distribution to customers, with information and communication domains that monitor and control each layer, and the control system must support interfaces across all of them (Browning & Eppinger, 2002; Joskow, 2012).
Protection and control equipment sits at the interfaces between these layers. That is why its schedule risk lies not in manufacturing time but in integration, interfaces and testing (Browning & Eppinger, 2002; Joskow, 2012).
The system dynamics literature can be applied to the rework cycle, and often protection philosophy, communication protocol or interface requirements are changed late in the game (Lyneis & Ford, 2007) which always leads to rework in software and in wiring. These changes are examples of preventable planning failures (Ahiaga-Dagbui & Smith, 2014) as they could have been prevented if the decision to freeze scope had not been made by the owner (Shane et al., 2009).
3.2. Technology Choice and the Structure of Transmission Cost
The choice between alternating-current and direct-current transmission determines which long-lead items a project needs, and therefore which schedule risks it carries (Flourentzou et al., 2009). High-voltage alternating-current systems rely on lines, transformers, reactors and series compensation, whereas line-commutated and voltage-source HVDC systems rely on converter stations, converter transformers and valves, which are produced by a smaller number of suppliers (Bahrman & Johnson, 2007).
Technology choice therefore changes more than cost. Different conductor and tower arrangements imply different construction and right-of-way requirements, and different terminal equipment implies a different set of suppliers, so the choice also changes which long-lead items a project needs (Bahrman & Johnson, 2007; Meah & Ula, 2007).
3.2.1. HVAC Cost Structure
Published cost breakdowns for overhead HVAC lines at 500 kV show that, for a 2,000 MW single-circuit line over 600 km, the line itself accounts for about 83 percent of cost, the HVAC substation for about 10 percent and the series capacitor station for about 7 percent (Alassi et al., 2019; Meah & Ula, 2007).
The large line share shows that most of the money, and most of the construction program, is in right-of-way and line works. The substation and series capacitor station are small in cost terms but contain the transformers and compensation equipment whose lead times can still govern the finish date (Alassi et al., 2019; U.S. Department of Energy, 2012).
Doubling the capacity to 4,000 MW with a double-circuit line changes the proportions only slightly: the substation share rises to about 11 percent and the series capacitor share to about 8 percent (Bahrman & Johnson, 2007), with the overhead line making up roughly four-fifths of the total (Meah & Ula, 2007).
Because these shares change little with scale, doubling capacity roughly doubles the number of transformers and compensation units without changing the ratio of line cost to equipment cost (Bahrman & Johnson, 2007). More transformers and compensation units therefore compete for factory capacity, even though the cost ratios appear reassuringly similar.
When the cost structure for an HVAC project is primarily line cost, the schedule risk for a project is primarily a construction risk and permitting risk and the equipment risk is only for a relatively small number of substation items. The small substation share is a misleading figure for scheduling purposes (U.S. Department of Energy, 2012), however, when the lead time for the substation is the longest on the network (Vajjhala & Fischbeck, 2007) a small amount of cost may be controlling the finish date.
3.2.2. HVDC Cost Structure
For a 3,000 MW, ±500 kV line-commutated HVDC overhead line over 600 km, the overhead line represents about 57 percent of the total, converter stations account for most of the remainder, and the ground electrode and electrode line take a very small share (Flourentzou et al., 2009).
Compared with the HVAC case, the line share drops from about 83 to about 57 percent, leaving a much greater share of cost at the converter stations. This shows the trade-off in moving to direct current: a long construction program is exchanged for dependence on a relatively small number of converter transformers and valves made by a limited number of companies (Bahrman & Johnson, 2007; Flourentzou et al., 2009).
Terminal costs are therefore much more significant in HVDC than in HVAC systems, and the principal equipment risk in direct-current projects lies in the converter stations. Converter transformers and valves are specialized devices that few suppliers can provide, so an HVDC project has inherently higher schedule volatility than an equivalent HVAC project (Van Hertem & Ghandhari, 2010; Bahrman & Johnson, 2007).
3.2.3. Distance, Break-Even and Cost Per Unit of Energy
Direct-current systems have higher terminal costs but lower line costs (Bahrman & Johnson, 2007), so beyond a break-even distance the direct-current option becomes cheaper. That distance is reported at roughly 600 to 800 km for overhead lines, about 48 to 96 km for underground cable and about 50 km for submarine cable (Meah & Ula, 2007).
Both technologies become more expensive with distance, but direct current starts higher because of its terminals and rises more slowly. The distance at which the two cost curves cross is the break-even distance, to the left of which alternating current is cheaper and to the right of which direct current is cheaper. Because the crossing depends on the cost inputs, it is better treated as a range than as a threshold (Bahrman & Johnson, 2007; Meah & Ula, 2007).
Price comparisons over distances of 300 to 1,500 km place the crossing in the neighborhood of 600 to 700 km, with the alternating-current cost rising more steeply. Because terminal equipment is the slow item (Alassi et al., 2019), a shift to direct current on long routes relocates schedule risk from the line to the terminals (Flourentzou et al., 2009).
Beyond the crossing point the gap widens, so the economic case for direct current strengthens with distance, but so does the dependence on terminal equipment that only a few suppliers can deliver (Flourentzou et al., 2009).
Decomposing total cost into line cost, terminal cost and losses makes plain why direct current is attractive at long distances, since its losses and line cost grow more slowly with distance (Bahrman & Johnson, 2007), and why it requires early commitment to scarce converter capacity (Van Hertem & Ghandhari, 2010).
For a remote source, the cost per kilowatt-hour of a voltage-source converter connection with cable can be compared with local diesel generation and with an alternating-current overhead connection; at long distances, the voltage-source option is reported as the lowest-cost choice (Alassi et al., 2019; Flourentzou et al., 2009).
These published cost structures and distance relationships are consolidated in Table 5, so that the equipment exposure of each technology can be compared with its cost structure. The comparison indicates that the technology with the higher share of terminal cost also has the narrower supplier base (Alassi et al., 2019), and that this combination is the most likely to create a schedule shock (Bahrman & Johnson, 2007).
Table 5 places cost structure and schedule exposure side by side. Reading down the second and third columns shows how the weight shifts from the line to the terminals: the overhead line accounts for 83 percent of the 2,000 MW HVAC case but 57 percent of the HVDC case, in which converter stations make up most of the remainder (Alassi et al., 2019; Meah & Ula, 2007). The last column translates that cost shape into delivery risk. Where terminals dominate, the supplier base is narrow, so risk moves from construction and permitting to converter transformers and valves (Bahrman & Johnson, 2007). Because the values were read from charts they are approximate and are best taken as orders of magnitude.
3.3. Network-Level Demand and the Competition for Capacity
Continental concepts such as the pan-European supergrid (Battaglini et al., 2009), together with the layered structure of the power system, point to a feature of procurement that is easily overlooked, namely that the demand for long-lead equipment is correlated across owners. Policy targets for renewable connection are set on similar timetables in many jurisdictions (Battaglini et al., 2009), so that the same few factories receive orders at the same time (Van Hertem & Ghandhari, 2010). Supergrid proposals envisage multi-terminal direct-current networks that would multiply the number of converter stations required (Alassi et al., 2019), and the obstacles identified for them include equipment standardization and supplier capacity (Van Hertem & Ghandhari, 2010).
Correlated demand has two consequences for schedule risk (Tang, 2006). First, lead-time distributions are not independent across projects, so that a portfolio of projects cannot diversify away the exposure. Second, early commitment by one owner raises the lead time faced by others, which creates a strategic element that deterministic schedules ignore (Chopra & Sodhi, 2004).
3.4. Permitting, Siting and Interface Delay
Equipment lead time is not the sole outside factor impacting on transmission project schedule risk, and it is important to recognize the competing impacts of permitting and public acceptance. Vajjhala and Fischbeck (2007) created an index of the difficulty of construction projects for siting U.S. transmission lines, and demonstrated that the difficulty of a project is highly variable and can be correlated with measurable aspects of the siting route (Joskow, 2012). Cain and Nelson (2013) studied the factors that underlie opposition to high-voltage lines and found that property value concerns, aesthetic concerns and perceived concerns for health all contribute, suggesting that there is no single reason for opposition.
There are obvious ways in which permits and equipment interact that can be overlooked (Pich et al., 2002). To protect against stranded cost if a route is denied or modified, an owner should order equipment prior to receiving a permit; to protect against the full manufacturing lead time if the permit isn’t issued, the owner should wait for the permit before ordering equipment. The timing of the commitment is then a decision under uncertainty, and the rationale is that of a real option, with the reservation fee being the option premium (Joskow, 2012).
There is additional risk in interfaces between the line and the substation (Herroelen & Leus, 2005). The line that is finished before the arrival of the terminal equipment will be useless, and the equipment will be delivered before the line will be finished will increase storage, warranty and insurance costs. To match the two, critical chain methods and feeding buffers are needed, and an honest estimate of the probability distribution of each completion date must be provided (Goldratt, 1997).
The overall message is that the risk from equipment and permitting can be modeled together. In this paper, the permitting process is not distinguished from the specification and approvals process, and the addition of explicitly representing the permit outcomes is a logical next step (Goldratt, 1997) (Vajjhala & Fischbeck, 2007).
4. Methodology
4.1. Research Design
The study uses a convergent design that combines a synthesis of historical reference-class evidence with a stochastic schedule model (Creswell & Plano Clark, 2018). The historical component answers the question of how often and by how much projects escalate, and which sources of escalation are preventable. The simulation component answers the question of how much of the schedule exposure of a representative substation program is attributable to long-lead items and which strategies reduce it (Hulett, 2009).
Using the two components together reflects the recommendation that forecasts should combine an outside view (Flyvbjerg, 2008), which fixes the distribution of outcomes, with an inside view, which captures project specifics (Kahneman & Tversky, 1979). The reference-class evidence disciplines the simulation inputs, while the simulation turns the reference-class evidence into a project-level probability.
4.1.1. Data Sources and the Reference Classes
The principal sources of historical evidence are the published datasets of Flyvbjerg and colleagues on transport projects, of Ansar, Flyvbjerg, Budzier, and Lunn (2014) on dams, and of Sovacool and colleagues on electricity infrastructure, together with the engineering analysis of nuclear construction by Eash-Gates et al. (2020) (Flyvbjerg et al., 2002; Sovacool et al., 2014a). The published charts of the electricity dataset by technology class in Sovacool et al. (2014b) supplement those sources, and the values used in Section 5 are read from those charts or from the published text, with the limits of readability noted where they apply (Sovacool et al., 2014b).
Equipment lead-time evidence is drawn from the federal assessment of large power transformers (U.S. Department of Energy, 2012) and the advisory council’s report on the shortage (National Infrastructure Advisory Council, 2024). No proprietary utility project data were used, and the simulation is therefore described throughout as illustrative.
4.1.2. Procurement Milestones as Risk Checkpoints
Procurement for a long-lead item proceeds through a sequence of milestones, and a schedule risk review is most effective when it is attached to those milestones. Table 6 lists the milestones used in the model and the checkpoint question that each one raises (Gosling & Naim, 2009), in line with the practice of tying risk review to project stages (Project Management Institute, 2017).
Table 6 turns the procurement process into a sequence of review points. Each row links a milestone to the activity that represents it in the simulation, so that a reviewer can move from the actual status of a project to the matching model input. The checkpoint question is the test to apply at that stage, and the evidence column states what the reviewer should see before accepting that the answer is yes, for example a dated quote register with confidence levels at market sounding. Reading the table from top to bottom follows an equipment order from specification to energization, with risk review tied to project stages (Gosling & Naim, 2009; Project Management Institute, 2017).
4.2. Classifying Sources of Escalation
The literature reviewed identified nine sources of escalation (Cantarelli et al., 2010) and they were assigned to two classes. When a source is considered preventable, it is the decision of the owner that the source could have been avoided or significantly reduced when decisions were made prior to the awarding of the contract, for example, scope freeze, early engagement, contract structure or market intelligence. If the occurrence is not under the owner’s control, for example, a commodity price shock or a change in law, it is included in the category of external if the owner could have avoided being exposed to the shock or change, or if he could have responded in some way to the shock or change so as not to be affected by it, the shock or change is not included in the category of external (Shane et al., 2009).
The two-class scheme is simplified and borderline cases are indicated in Section 5.2. It is nevertheless helpful in directing attention to the actions that owners and regulators can take (Cantarelli et al., 2012), and because it fits in with the explanatory categories of technical, psychological, economic and political causes (Zidane & Andersen, 2018).
4.3. The Monte Carlo Schedule Model
4.3.1. Network Structure
The model represents the procurement and delivery of a 500 kV substation expansion as a network of ten activities. Specification and approvals and bid evaluation and award are serial, and both precede manufacture of the long-lead items. Transformer manufacture and transport, gas-insulated switchgear and breakers, shunt reactors, and protection and control supply then proceed in parallel, together with civil works and foundations. Installation and testing and commissioning follow the latest of those paths (Goldratt, 1997; Lyneis & Ford, 2007).
The planned duration is the sum of the modal durations along the critical path under pre-shortage inputs, which is 107 weeks, and it represents the plan that an owner would have produced from historical experience. The simulation measures how far outcomes diverge from that plan when durations are random (Malcolm et al., 1959) and when the market has shifted (Van Slyke, 1963).
4.3.2. Input Distributions
Each activity duration follows a triangular distribution defined by minimum, most likely and maximum values in weeks (Hazır, 2015). The triangular form is chosen for transparency and is common in practice when data are scarce, although it understates the probability of extreme outcomes relative to heavier-tailed alternatives (Kwak & Ingall, 2007). Table 7 lists the inputs for the baseline and current-market scenarios.
Table 7.
Simulation inputs: triangular distributions (weeks) for baseline and current-market scenarios.
Table 7.
Simulation inputs: triangular distributions (weeks) for baseline and current-market scenarios.
| Activity | Baseline (min / mode / max) | Current (min / mode / max) | Basis of input |
|---|---|---|---|
| Specification & approvals | 12 / 16 / 30 | 12 / 16 / 30 | Author assumption |
| Bid evaluation & award | 10 / 14 / 28 | 10 / 14 / 28 | Author assumption |
| Transformer manufacture | 22 / 45 / 69 | 80 / 120 / 210 | Published ranges (DOE; NIAC) |
| Transformer transport & delivery | 4 / 8 / 20 | 6 / 12 / 30 | Author assumption, raised for heavier transport |
| GIS / breaker manufacture | 30 / 40 / 60 | 50 / 70 / 110 | Author assumption, raised for current demand |
| Shunt reactor manufacture | 40 / 55 / 80 | 60 / 90 / 140 | Author assumption, raised for current demand |
| Protection & control supply | 24 / 32 / 52 | 30 / 44 / 70 | Author assumption, raised for current demand |
| Civil works & foundations | 30 / 40 / 60 | 30 / 40 / 60 | Author assumption |
| Installation | 10 / 14 / 24 | 10 / 14 / 24 | Author assumption |
| Testing & commissioning | 6 / 8 / 14 | 6 / 8 / 14 | Author assumption |
All inputs to the simulation are listed in Table 7. Each activity is described by three numbers, the minimum, most likely and maximum duration in weeks, and the two scenarios differ only where the baseline and current columns differ. The only other transformers anchored in published ranges are 22, 45 and 69 weeks before the shortage, and 80, 120 and 210 weeks in 2024 (National Infrastructure Advisory Council, 2024; U.S. Department of Energy, 2012). The other rows are assumptions made by the author in the current instance for items competing for the same factory capacity. The first column of the table illustrates the equipment on the basis of which the market was considered, thereby separating out the market effect from the other inputs in the market, while the last column shows the basis of each of the inputs in accordance with the transparency recommendations made by Hulett (2009).
The only input that is explicitly tied to published ranges is transformer manufacture. The baseline range of 22 to 69 weeks is consistent with the 5 to 16 months reported prior to the shortage (National Infrastructure Advisory Council, 2024), while the current range of 80 to 210 weeks is consistent with the range reported in 2024, and the mode is 120 weeks consistent with the reported average (U.S. Department of Energy, 2012). All other ranges are assumed by the author and are representative of plausible relativities and the model is to be run again with owner data.
4.3.3. Scenarios and Mitigation Strategies
Six scenarios are simulated. The first two compare baseline and current-market inputs (Christopher & Peck, 2004). The remaining four apply mitigation strategies to the current-market case. Early slot reservation begins the transformer clock after specification and approvals rather than after contract award, which represents payment of a reservation fee before award. Dual sourcing splits the order between two independent suppliers, adds ten percent to each duration to represent smaller lot sizes and takes the earlier delivery. Spare reallocation represents the probability, set at 0.4, that an owner-held spare or fleet unit can be redeployed, replacing manufacture with a short transport and reinstallation period. The combined case applies all three (Chopra & Sodhi, 2004).
4.3.4. Outputs and Sensitivity Analysis
For each scenario, 10,000 trials are run with a fixed random seed. Outputs are the mean and the 10th, 50th, 80th and 90th percentiles of total duration, together with the probability of finishing within the 107-week plan. Sensitivity is measured by the Spearman rank correlation between each activity duration and the total duration (Hazır, 2015), which is robust to nonlinearity and is the measure reported by most commercial tools (Hulett, 2009). The workbook supplied with this paper contains the inputs, results and the three charts reproduced as Figures 2 to 4.
4.4. Validity and Limitations of the Approach
There are three main drawbacks to the approach. First, the simulation assumes inputs for all activities, except for the transformer manufacturing activities, which are not observed but rather assumed, meaning that the quantitative results are illustrative, and not intended to be a forecast for any particular owner. Second, the activities are sampled independently, which underestimates the joint risk when multiple items are jointly affected by a common cause, e.g., manufacturing capacity deficit (Hulett, 2009). Third, the triangular distributions do not include discrete catastrophic events, like a factory failure or a transport accident (Craighead et al., 2007), nor do they bound the outcomes (Blackhurst et al., 2011).
Despite these limitations, the model is good enough for the purposes of this paper, which are to illustrate the structure of the exposure, to rank drivers, and to compare the relative effect of the mitigation strategies. Relative comparisons are less sensitive to input error than are absolute forecasts (Herroelen & Leus, 2005), and the logic of the model can be audited line by line (Pich et al., 2002).
4.5. Reproducibility and Transparency
All inputs, results and the random seed are recorded in the workbook that accompanies the paper, together with the 10,000 trial outcomes for the baseline, current-market and combined-mitigation scenarios. Any reader can therefore reproduce the figures (Hulett, 2009), replace the assumed inputs with data of their own and observe the effect on the results (Kwak & Ingall, 2007). Transparent modeling is also an ethical requirement in a field in which numbers have been used to win approval for projects (Flyvbjerg et al., 2002), and a model whose assumptions are visible is less open to manipulation than one whose assumptions are buried (Love & Ahiaga-Dagbui, 2018).
5. Results
5.1. Historical Evidence on Frequency and Magnitude of Escalation
5.1.1. Distribution of Cost Escalation in Electricity Projects
Figure 1 shows the frequency distribution of cost escalation for the 401 projects in the electricity dataset. The most common outcome is a modest overrun (Sovacool et al., 2014a), since the tallest bar, with 106 projects, lies in the band from zero to 20 percent, but the distribution has a long right tail and the open-ended class of 200 percent or more contains 43 projects (Sovacool et al., 2014c).
Figure 1 is a histogram – the height of each bar represents the number of projects, not the percentage of projects, that are overrun in a range. The message is embodied in the shape. The tall bar at the bottom represents 106 projects ranging from zero to 20 percent, followed by a long tail of an open class of 200 percent or more that includes 43 projects. The bars would be approximately symmetrically distributed around the zero value if they were unbiased, but the strong right skew indicates that they are not (Flyvbjerg et al., 2002; Sovacool et al., 2014c).
The class counts show that 61 projects were completed under budget, 39 on budget and 301 over budget, which is consistent with the finding that roughly three out of four projects were underestimated. The asymmetry is important for schedule risk analysis (Kahneman & Tversky, 1979) because it suggests that a symmetric distribution with a mean equal to the estimate is not a good approximation of the outcomes (Sovacool et al., 2014c).
One common feature of reference-class data is its heavy right tail. Flyvbjerg and others reported that the standard deviation of overruns was large compared to the mean in all transport classes (Flyvbjerg et al., 2004) and the electricity data are similarly characterized by a large standard deviation compared to the mean so that the mean underestimates the exposure that an owner faces given that he or she cannot diversify across many projects (Flyvbjerg, 2005).
Table 8.
Mean cost escalation by technology in the published summary table (Sovacool et al., 2014b).
Table 8.
Mean cost escalation by technology in the published summary table (Sovacool et al., 2014b).
| Technology | Mean cost escalation (%) | Sample size (n) | Position among classes |
|---|---|---|---|
| Nuclear reactors | 117 | 180 | Highest |
| Hydroelectric dams | 71 | 61 | Second |
| Railway networks | 45 | 58 | Third |
| Bridges and tunnels | 34 | 33 | Fourth |
| Roads | 20 | 167 | Fifth |
| Mining projects | 14 | 63 | Sixth |
| Thermal power plants | 13 | 36 | Seventh |
| Wind farms | 8 | 35 | Joint eighth |
| Transmission projects | 8 | 50 | Joint eighth |
| Solar farms | 1 | 39 | Lowest |
Table 8 lists ten technology classes by mean cost escalation, and the sample-size column indicates how much confidence each mean deserves. Nuclear reactors (117 percent across 180 projects) and hydroelectric dams (71 percent across 61 projects) are far above the other classes, while transmission projects (8 percent across 50 projects) and solar farms (1 percent across 39 projects) are at the bottom. As Figure 1 demonstrates, the ranking reflects exposure to large overruns rather than the typical project (Flyvbjerg et al., 2004; Sovacool et al., 2014a). The table is also used as the input to Equation 2 in Section 5.1.4.
Among the six electricity classes, transmission projects perform best after solar farms: their mean escalation of 8 percent across 50 projects places them joint eighth of the ten classes, level with wind farms and far below nuclear reactors and hydroelectric dams (Sovacool et al., 2014b). Even so, the transmission mean is an average across many project types and says little about the equipment-intensive substations that accompany the lines (Odeck, 2004; Sovacool et al., 2014c).
5.1.2. Construction Time and Time Overrun by Technology Class
Sovacool et al. (2014b) also report mean construction time and mean cost overrun by technology class. Hydroelectric and nuclear projects have the longest construction durations, roughly 118 and 91 months respectively, and the largest cost overruns (Ansar et al., 2014), while wind, solar and transmission and distribution projects have the shortest durations and overruns close to zero (Sovacool et al., 2014b). The ordering supports the proposition that cost escalation is strongly related to the length of the delivery period (Flyvbjerg et al., 2004; Sovacool et al., 2014a).
The construction-time values are approximate and are used only to establish ordering. The construction-time data also come from a smaller sample than the cost data (Eash-Gates et al., 2020; Sovacool et al., 2014b).
Sovacool et al. (2014b) also report the mean time overrun and the share of projects with an overrun. Hydroelectric and nuclear projects each show a mean time overrun near 64 percent, thermal and wind projects near 10 percent, and transmission and distribution projects near 7 percent, while solar projects show essentially none. The share of projects with an overrun ranges from about 97 percent for nuclear (Ansar et al., 2014) and 75 percent for hydroelectric to about 40 percent for transmission and distribution and 41 percent for solar (Cantarelli et al., 2012; Sovacool et al., 2014a).
The two measures, the average delay (mean time overrun) and the share of projects delayed, need not move together: a class might have a low average overrun yet still overrun frequently. Transmission and distribution projects are an example, since on average they exceed schedule by only about 7 percent, yet about 40 percent of them overrun (Sovacool et al., 2014a).
There are two observations that follow. First, transmission and distribution projects suffer little from large time overruns, and about 20% of these projects are found to be over budget, suggesting that cost growth does not primarily stem from a project’s schedule slippage on the project itself (Sovacool et al., 2014c). Second, the relatively strong performance of the class is an average across a variety of project types (National Infrastructure Advisory Council, 2024), and, as evidenced by the transformer market, equipment-intensive projects might now behave differently from the historical average (U.S. Department of Energy, 2012).
5.1.3. Project Size, Unit Cost and Cost Overrun
Sovacool et al. (2014b) also report mean project size, mean cost and mean cost overrun by technology class. Hydroelectric and nuclear projects are the largest and carry the largest absolute overruns (Eash-Gates et al., 2020), wind and solar projects are small with negligible overruns, and solar projects have the highest cost per installed unit of capacity (Sovacool et al., 2014b).
Taken together, these data show that absolute dollars at risk grow with project size and not only percentages, which is why packaging work into smaller lots can reduce exposure where the supply base allows (Flyvbjerg et al., 2004; Sovacool et al., 2014a).
Size therefore appears to be associated with absolute overrun (Flyvbjerg et al., 2004), which agrees with the finding that larger bridges and tunnels have larger percentage escalations and with the argument that modularity reduces exposure (Sovacool et al., 2014a). The result has an implication for transmission owners (Odeck, 2004), who can influence project size through packaging of work, and who may reduce schedule exposure by splitting large equipment orders where the supply base allows (Sovacool et al., 2014b).
5.1.4. Weighted Aggregation of the Technology Data
The sample-weighted mean of Equation 2, which follows the aggregation used by Flyvbjerg, Holm and Buhl (2004), provides a consistency check on the entries in Table 8. The six electricity classes (180 nuclear, 61 hydroelectric, 36 thermal, 35 wind, 50 transmission and 39 solar projects, 390 in total) have a weighted mean escalation of 68.1 percent, close to the mean of 66.3 percent reported for the full dataset of 401 projects (Sovacool et al., 2014b), and all ten classes together (711 projects) have a weighted mean of 48.6 percent. The small gap between 68.1 and 66.3 percent is consistent with the 11 projects in the full dataset that fall outside the six classes listed.
The aggregate is heavily skewed toward two classes. Removing the 180 nuclear projects reduces the weighted mean of the remaining 210 electricity projects to 26.3 percent, and removing the hydroelectric projects as well leaves 149 projects with a mean of only 8.0 percent. The remaining classes, including transmission and wind, therefore fare much better than the headline figure suggests (Sovacool et al., 2014c), and the distinction between technology classes should be taken into account when building a reference class for a substation program (Flyvbjerg, 2006).
5.1.5. Median, Mean and Tail Shares from the Frequency Distribution
The class counts in Figure 1 can also be used to recover summary statistics (Sovacool et al., 2014c). There are 61 projects that cost less than their budget, 39 that were on budget and 301 that were over budget, so the proportion over budget is 301/401, or 75.1 percent. Cumulatively, 100 projects lie at or below zero escalation and 206 at or below 20 percent, so the median, the 201st observation, falls in the class from 0.1 to 20 percent, far below the reported mean of 66.3 percent (Sovacool et al., 2014b).
The difference between the median and mean is characteristic of a heavy right-tail. The number of projects in each of these classes (100 percent and above) is 8, 9, 4, 10, 10 and 43, or 84 (20.9 percent); about one project out of every five doubled or more. The skewness of this type is also responsible for the cautionary advice of Love and Ahiaga-Dagbui (2018) for the caution regarding average interpretation and Shane et al. (2009) to identify escalation factors for each project and not the mean. A planner who takes the mean as a contingency will be too generous for the average project and too tight for the unlucky project (Flyvbjerg et al., 2002).
5.1.6. Cost-to-Time Overrun Ratio by Technology Class
The time-overrun data and Table 8 can be combined to examine whether cost grows in proportion to time, a question raised by Flyvbjerg, Holm, and Buhl (2004). Define the cost-to-time ratio for class k as the mean cost escalation divided by the mean time overrun, as in Equation 7, in which Ek is read from Table 8 and τk is the mean time overrun reported by Sovacool et al. (2014b).
Equation 7 divides the mean cost escalation of a technology class by its mean time overrun, both in percent, so that rk is a pure ratio that can be compared across classes. A value of 1 means that cost grows in the same proportion as schedule, a value above 1 means that cost grows faster than time, and a value below 1 means that it grows more slowly. Because Ek comes from the cost data summarized in Table 8 and τk from the reported time-overrun data, the ratio links two datasets drawn from the same literature (Sovacool et al., 2014b). It is a descriptive device and not a model, and it does not by itself show that delay causes cost growth.
The ratio is helpful because one of the most frequently reported correlates of escalation is the length of the delivery period. Escalation would tend to increase as the implementation phase extended (Flyvbjerg et al., 2004), and Ansar et al. (2014) reported that schedule overruns, and to a great extent, cost overruns were experienced in most of the dams. A ratio close to one is then close to consistent with time being a general scale on cost; one ratio much higher than one suggests cost increases faster than delays, which Eash-Gates et al. (2020) attribute to soft costs. There are two cautions that need to be noted here: First, the time data are based on smaller sample sizes than are the cost data, and second, the average of different samples does not correlate project-by-project with the average of the cost samples, so the ratio should be viewed as indicative (Sovacool et al., 2014a).
The approximate values are 1.8 for nuclear reactors, 1.1 for hydroelectric dams, 1.3 for thermal plants, 0.9 for wind farms and 1.1 for transmission and distribution. Most of the ratios are close to one, indicating that there is a dependency of escalation on implementation time, as reported by Flyvbjerg, Holm and Buhl (2004) and Ansar, Flyvbjerg, Budzier and Lunn (2014) for other projects, outside the nuclear domain. The ratio of the nuclear projects is well above unity, and stands in line with the soft-cost explanation of Eash-Gates et al. (2020), where indirect costs exacerbate the impact of delay. The ratios are approximate as the base time data are based on a smaller sample, and should be considered indicative only (Sovacool et al., 2014a).
5.2. Classifying the Sources of Escalation
The historical evidence may now be read in the context of the classification of sources of escalation identified from the literature, as shown in Table 2, which divides them into preventable and external groups. Optimistic duration assumptions (Ahiaga-Dagbui & Smith, 2014), incomplete scope at award time, late design change, weak interface management, and the situation where price or schedule risk is placed with the party that cannot handle it best (Shane et al., 2009) dominate the preventable group. These are consistently seen as the most critical factors in delay in several studies conducted in different countries (Gündüz et al., 2013; Sambasivan & Soon, 2007).
Other sources are commodity price shocks, general shortage of capacity, alterations in law and permitting procedures, geopolitical disruption of trade and extreme weather (Christopher & Peck, 2004). The lack of transformers is in this category because no single utility produced them (National Infrastructure Advisory Council, 2024). The classification does not mean that external sources are not under control (Blackhurst et al., 2011); the exposure to external sources is dependent on choices made regarding timing, the form of contract and supplier relationships (Chopra & Sodhi, 2004).
There are many boundary cases. The choice to depend on a solitary foreign supplier for a crucial component is one, while the geopolitical occasion that created the disruption to that supplier is not. The percentage of the delay that is avoidable depends on whether there were alternatives available at the time of the choice (Tang, 2006). Similarly, failure to permit delay comes from outside the equipment supplier (Cain & Nelson, 2013); however, early involvement of stakeholders and regulators by the owner could help prevent this failure (Vajjhala & Fischbeck, 2007).
The literature on cost estimation identifies another source that would have been avoided, namely, poor estimation techniques (Buehler et al., 1994). Past studies have employed data mining techniques to predict overruns and found that some of the unpredictability of overruns is due to lack of use of the available information at the beginning of the project (Ahiaga-Dagbui & Smith, 2014). Similarly, the evidence from a reference class in Table 8 offers distributions that planners can utilize even if they have little or no project-specific information to work with (Flyvbjerg et al., 2002; Flyvbjerg, 2008).
5.3. Simulation Results
5.3.1. Baseline and Current-Market Scenarios
The simulation begins with the baseline scenario, in which inputs reflect pre-shortage transformer lead times. The median completion is 124.4 weeks, which is 17.4 weeks or about 16 percent later than the 107-week plan built from modal values, and the probability of finishing within plan is only 3 percent (Hulett, 2009). The shortfall is entirely a product of uncertainty and of merging paths (Malcolm et al., 1959), since no market shift is present, and it illustrates the bias that Van Slyke (1963) identified in networks that rely on most-likely durations (Van Slyke, 1963).
Under current-market inputs, the median completion is 211.6 weeks and the 80th percentile is 238.9 weeks, which is nearly double the plan, and the probability of meeting the plan is effectively zero. Table 9 reports the full set of statistics for all six scenarios. Figure 2 plots the cumulative probability of completion for the baseline (Hulett, 2009), current-market and combined-mitigation cases against the 107-week plan (Kwak & Ingall, 2007; National Infrastructure Advisory Council, 2024).
Table 9 summarizes 10,000 trials for each scenario. The mean is the average duration, P10, P50, P80 and P90 are the durations that 10, 50, 80 and 90 percent of trials finish within, and the last column is the share of trials that finish within the 107-week plan. Reading down the P50 column shows the central shift from 124.4 to 211.6 weeks between the baseline and current-market cases, and reading across a row shows the spread between P10 and P90. The P80 column is the most relevant for an owner who needs high confidence in a committed date (Hulett, 2009; Kwak & Ingall, 2007). Reporting percentiles instead of one number shows how likely a date is and not merely what the date might be.
Figure 2.
Cumulative probability of completion for a 500 kV substation program under alternative lead-time assumptions.
Figure 2.
Cumulative probability of completion for a 500 kV substation program under alternative lead-time assumptions.

For each time in the horizontal direction, the curve in Figure 2 shows the percentage of trials completed up to that time, meaning that all of the curves will start at zero and end at one. It is a “simulated” version of the probability Pr(T ≤ t) in Equation 5. A curve to the right side represents a slower scenario, a curve to the left side represents a narrower range of outcomes. The point where the curve intersects the 107-week plan indicates the probability of achieving that plan; at 0.8 the point on the curve indicates the P80 values in Table 9 (Hulett, 2009; Kwak & Ingall, 2007).
The difference between the plan and the median currently on the market is 104.6 weeks. Of that difference, 17.4 weeks are due to planning method and variability and 87.2 weeks are due to the change in the transformer market. As a share, the gap is caused by a preventable methodological weakness (about 17 percent) and an external change in the market (about 83 percent); however, Section 5.3.3 demonstrates that part of the latter is attributable to procurement strategy (Herroelen & Leus, 2005; U.S. Department of Energy, 2012).
The spread of outcomes also widens. The interval between the 10th and 90th percentiles is about 25.6 weeks in the baseline case and about 72.9 weeks in the current-market case, so that the market shift increases uncertainty as well as the mean. An owner who commits to a date on the basis of the median therefore carries a much larger probability of late completion than before (Hendricks & Singhal, 2005).
5.3.2. Sensitivity of Project Duration to Individual Activities
Table 10 ranks the activities by their Spearman rank correlation with total duration in the current-market scenario, and Figure 3 shows the same ranking graphically. Transformer manufacture dominates, with a correlation of 0.95, and no other activity exceeds 0.18 (Hulett, 2009; Kwak & Ingall, 2007).
Table 10.
Rank-correlation sensitivity of total duration to each activity, current-market scenario.
| Rank | Activity | Spearman correlation | Reading |
|---|---|---|---|
| 1 | Transformer manufacture | 0.951 | Dominant driver |
| 2 | Transformer transport & delivery | 0.171 | Minor driver |
| 3 | Specification & approvals | 0.134 | Minor driver, owner-controlled |
| 4 | Bid evaluation & award | 0.127 | Minor driver, owner-controlled |
| 5 | Installation | 0.081 | Minor driver |
| 6 | Testing & commissioning | 0.076 | Minor driver |
| 7 | Shunt reactor manufacture | 0.016 | Off critical path |
| 8 | Protection & control supply | 0.015 | Off critical path |
| 9 | Civil works & foundations | 0.010 | Off critical path |
| 10 | GIS / breaker manufacture | -0.008 | Off critical path |
Table 10 lists the activities in order of influence on the finish date, measured by the rank correlation of Equation 6. A value near 1 means that when the activity runs long the whole project tends to run long, and a value near zero means that the activity has little bearing on the end date; the near-zero and slightly negative entries at the bottom, such as gas-insulated switchgear and breaker manufacture, are off the critical path in this scenario. The gap between 0.951 and the next value of 0.171 is the main message, because it says that management attention should follow the ranking and not be spread evenly across procurement lines (Hulett, 2009; Kraljic, 1983). The ranking holds only for these inputs and should be refreshed when quotes change.
Figure 3 presents the correlations from Table 10 as bars, making it easy to see visually, that one bar is much taller than the rest. This type of chart is a typical result from schedule risk software (Hulett, 2009) and provides the benefit of highlighting where management attention will be rewarded. Bars that are short in this situation are the activities that are within the transformer path, and may experience an increase if the lead time of the transformer decreases.
Transformer transport and delivery comes in second with a correlation of 0.17 followed by specification and approval at 0.13 and bid evaluation and award at 0.13. The last two are interesting, because they are upstream from all manufacturing routes and are completely under the owner’s control (Gündüz et al., 2013), thus a measure of the cost of slow internal decisions (Shane et al., 2009).
The current-market situation (Williams, 1995) shows that the correlations of the various components are very close to 0 for gas-insulated switchgear, reactors, protection and control, and civil works. This does not imply that those items are not important in general, but it only means that their assumed durations are within the transformer path. If the transformer lead time was to get reduced, the ranking would change and the analysis should be re-run whenever the lead time quote is changed (Project Management Institute, 2017).
The focus of sensitivity in the single product is in line with the management of supply chain risk by criticality rather than by volume. One hundred of hundreds of procurement lines, with one line being big and the rest being small, is best handled by focusing more on the big line and less on the others (Kraljic, 1983; Craighead et al., 2007).
5.3.3. Effect of Mitigation Strategies
Table 11 reports the change in the median, 80th and 90th percentiles produced by each strategy relative to the current-market case, and Figure 4 compares the median and P80 durations. Early slot reservation lowers the median by 17.2 weeks and the P80 by 17.6 weeks. Dual sourcing lowers the median by only 2.9 weeks but lowers the P80 by 8.2 weeks and the P90 by 11.4 weeks (Chopra & Sodhi, 2004), so its effect is concentrated in the upper tail (Tang, 2006).
Table 11 reports weeks saved relative to the current-market case, so larger numbers are better. Comparing columns shows how each strategy behaves. Early slot reservation saves about the same at the median, P80 and P90 (17.2, 17.6 and 17.4 weeks) because it moves the start of the transformer clock forward by a roughly fixed interval. Dual sourcing saves little at the median (2.9 weeks) but more in the tail (11.4 weeks at P90), and spare reallocation saves more at the median (22.5 weeks) than at P90 (10.6 weeks). The last column states the price paid in each case, which is why the table should be read together with the break-even condition of Section 5.4 (Chopra & Sodhi, 2004; Tang, 2006).
The duration for each of the scenarios in Figure 4 is compared in terms of the median and P80 duration. The distance between the two bars for one scenario shows how much longer it will take to cover from an even chance to 80 percent chance and the shorter the distance the quicker the time taken. The use of both strategies results in the lowest bars, but the P80 value of 201.9 weeks is still significantly above the 107-week plan, and thus, the use of mitigation reduces the penalty but it will not remove the penalty (Chopra & Sodhi, 2004; Tang, 2006).
Spare reallocation reduces the median by 22.5 weeks and the 10th percentile by approximately 32 weeks, while it only reduces the P90 by 10.6 weeks, because the full manufacturing delay is applied in trials which do not include spares. The typical benefits of the strategy are greater than the risk of negative outcomes (Blackhurst et al., 2011) and the benefits are dependent on the owner’s capacity to maintain or secure appropriate spares (Christopher & Peck, 2004).
Combined, the three strategies further reduce the median to 179.9 weeks and the P80 to 201.9 weeks, which are decreases of 31.7 and 37.0 weeks, respectively. This suggests that mitigation can more than compensate for about one third of the market-shift penalty at the median but can’t match pre-shortage performance (Ho et al., 2015), which falls well short of the combined P80.
5.3.3.1. Interpretation of the Mitigation Ranking
The ranking by median reduction places spare reallocation first, early slot reservation second and dual sourcing third, whereas the ranking by tail protection places the combination first and dual sourcing next. Owners with a high tolerance for late outcomes and a preference for low cost might favor the strategies that improve the median (Lovallo & Kahneman, 2003), while owners with hard in-service dates would value tail protection more (Pich et al., 2002).
5.3.3.2. Costs of Mitigation
The simulation does not price the strategies, and cost is the other half of the decision. Reservation fees, price premiums for smaller lots and the carrying cost of spares all reduce the net benefit, and a strategy is justified only when its cost is below the expected saving in delay cost (Shane et al., 2009). Section 5.4 sets out the break-even condition.
5.3.4. Input Moments and Contingency Requirement
The moments in Equations 3 and 4 represent the extent to which the market for transformers has changed. The means and standard deviations for the baseline range (22, 45, 69) and the current range (80, 120, 210) are 45.3 weeks and 9.6 weeks respectively, and 136.7 weeks and 27.2 weeks respectively. The manufacturing time is therefore increased by 91.3 weeks or approximately 201 percent, and the standard deviation is increased by a factor of approximately 2.8, which results in a shift of the mean and the spread of the distribution in the market (U.S. Department of Energy, 2012).
The contingency that an owner would need to hold to reach a chosen confidence level, a practice recommended by Hulett (2009), can be expressed as the uplift in Equation 8 (Flyvbjerg, 2008), in which Pq is the q-th percentile of simulated duration and Tp is the plan.
Equation 8 expresses contingency as a percentage of the plan. The term Pq is the duration that the simulation says will be met or beaten in q percent of trials, so the numerator is the extra time beyond the plan Tp that must be held to reach that level of confidence. For example, an uplift of 25 percent on a plan of 100 weeks means that 25 weeks must be added before the owner can say there is an 80 percent chance of finishing on time. The higher the confidence demanded, the higher the percentile and the larger the uplift.
The logic follows the reference-class uplift proposed by Flyvbjerg (2008): instead of adding an arbitrary allowance, the planner chooses an acceptable risk of overrun and reads the required uplift off the distribution of outcomes. Hulett (2009) makes the same point for schedules by asking the owner to choose explicitly the confidence level at which a date is committed. The choice of q is a management decision, since an owner with a hard in-service date will favor a high percentile and an owner with deferrable benefits a lower one. Because κq is only as good as the inputs behind Pq, it must be recalculated whenever lead-time quotes change, since stale inputs produce a stale contingency.
The plan of 107 weeks has 24.4 percent uplift at the 80th percentile for baseline inputs and 123.3 percent uplift for current-market inputs; the combined three mitigation strategies reduce the uplift to 88.7 percent. These values are similar to the pre-shortage market’s contingency values as recommended by Flyvbjerg (2006), showing that such a contingency would be deficient by approximately a hundred percentage points (Flyvbjerg, 2008). The uplift at the median is 16.3 percent in baseline and 97.7 percent in current inputs, and demonstrates that it is not just the tail that is affected by the shift.
5.3.5. Statistical Precision of the Simulated Estimates
Each simulated probability is an estimate from a finite number of trials, a point stressed in the Monte Carlo guidance of Kwak and Ingall (2007). With N trials, the standard error of an estimated probability p is given by Equation 9, which (Hulett, 2009) has a maximum of 0.005 when p equals 0.5 and N is 10,000.
Equation 9 gives the standard error of a probability estimated from N independent trials. It shows that precision depends on only two things, the probability itself and the number of trials. The numerator p(1 − p) is largest at p = 0.5, so probabilities near the middle are the least precise and those near 0 or 1 the most precise. The denominator contains the square root of N, so precision improves slowly: quadrupling the number of trials only halves the standard error. With 1,000 trials the worst-case standard error would be about 0.016, compared with 0.005 at 10,000 trials.
A standard error of 0.005 indicates that, approximately 95 percent of the time, a simulated probability close to 0.5 will be within about 1 percentage point of the probability that an infinitely long run would yield (Kwak & Ingall, 2007). The statement only applies to sampling noise. It doesn’t mean that the distributions assumed are correct, which is the more major source of uncertainty in any schedule model (Hulett, 2009) and that is why in Section 5.5 alternative distributions, correlations and modes are tested for rather than simply adding trials. It is important to report the number of trials, and the random seed, like Section 4.5 does, so that the reader can verify the precision for themselves.
The standard error is small relative to the differences between the scenarios at 80 percentiles (0.004) and at 3 percent of the probability of meeting the baseline plan (0.002) (Kwak & Ingall, 2007). The difference in the median duration between the current-market case and the combined mitigation case is therefore many times larger than any sampling noise, but is still dependent on assumptions made for the inputs (Hulett, 2009). The robustness checks in Section 5.5 focus on the more important source of uncertainty related to the choice of distributions and correlations.
5.4. Linking Schedule Saving to Cost: A Break-Even Condition
The cost escalation factor is correlated with the duration of the implementation phase (Flyvbjerg et al. 2004) and therefore each week saved can be monetized as a cost-mitigation measure (Sovacool et al. 2014b). If the cost of one week of delay to the owner can be expressed as the sum of financing cost (as described by Creedy et al., 2010), extended supervision and engineering cost, replacement energy or congestion cost, and escalation of any remaining purchases, then a measure will be worthwhile if the premium is less than the expected weeks saved multiplied by that weekly cost (Shane et al., 2009).
Early slot reservation (cost-of-delay equal to 17.2 weeks on median, cost of reservation less than 31.7 weeks of delay cost) and the combined package (cost-of-delay equal to 31.7 weeks on median, cost of reservation less than 31.7 weeks) are worthwhile as long as the cost of the reservation is less than roughly seventeen weeks of delay. While the calculation is straightforward, it is not often declared and if it is, it turns an argument over principle into an argument between two numbers (Ahiaga-Dagbui & Smith, 2014; Kwak & Ingall, 2007).
One key nuance is the weekly cost of delay is variable. If a connection is needed to unlock a large generation resource (Battaglini et al., 2009), or to free up a binding congestion constraint, the weekly cost may be orders of magnitude higher than it would be for a connection supporting a deferrable benefit (Battaglini et al., 2009), and the distribution of procurement attention ought to be adjusted accordingly (Joskow, 2012).
5.5. Robustness of the Simulation Results
Four checks of the present market situation were performed to see if the findings are model choice dependent. When rerun using a different random seed (Hazır, 2015) the median is 211.8 weeks and the 80th percentile is 240.0 weeks, showing that the original results, when rerun with a different random seed are stable to sampling variation (Kwak & Ingall, 2007).
The first check involves substituting the triangular distributions with PERT-beta distributions which focus the probability on the most likely value and are less sensitive to the extremes (Malcolm et al., 1959). This drops the median to 197.7 weeks and 80th percentile to 220.9 weeks, down approximately 14 and 19 weeks respectively, but still zero probability of meeting the 107-week plan. Choices of distribution will impact the magnitude of the results but not the message (Hulett, 2009).
The second check adds positive correlation between the manufacturing-related activities via a common factor, with 0.3 and 0.6 correlation coefficients. The median is nearly identical at 211.7 weeks, although both the 80th percentile and 90th percentile have increased to 241.3 and 256.2 weeks, respectively, and 243.3 and 259.0 weeks, respectively. Ignoring the upper tail thus under-estimates the risk of a late outcome (Williams, 1995) and correlation is expected to fatten the upper tail (Craighead et al., 2007).
The third check adds extra uncertainty of another 20 weeks for the most likely transformer lead time to reach 140 weeks. Finally, the median increases by approximately 9 weeks to 221.2 weeks for the 80th percentile to 247.2 weeks, indicating that the results are not hypersensitive to the key input and respond sensibly to it. The consequence of the error in the reported average (Hendricks & Singhal, 2005) is also captured as the result was set to be in line with the reported average.
The results are the same throughout the checks: The plan is very unlikely to be achieved under current conditions, Transformer manufacture is the dominant exposure and mitigation reduces the exposure but does not eliminate the penalty. The ranking of the mitigation strategies was not re-tested for each variation (Browning & Eppinger, 2002) and a fuller robustness study is recommended for future work (Lyneis & Ford, 2007).
6. Discussion
6.1. Interpretation of the Principal Findings
Three findings stand out (Sovacool et al., 2014c). The first is that the historical record places transmission projects among the better-performing classes of electricity infrastructure in cost and time, with a mean escalation of 8 percent and a mean time overrun of about 7 percent, yet roughly two in five still exceed budget (Sovacool et al., 2014a). The second is that a plan built from modal durations is unlikely to be met even before the market shifts, since the baseline simulation gives a 3 percent probability of success. The third is that the transformer market shift dominates the schedule exposure of a substation program (National Infrastructure Advisory Council, 2024), with a rank correlation of 0.95 between transformer manufacture and total duration (Van Slyke, 1963).
Taken together, the findings show that a favorable historical average is a poor guide to the exposure of an individual equipment-intensive project under changed market conditions (Flyvbjerg, 2006). The historical record describes a period in which lead times were shorter and suppliers had spare capacity, and a reference class is informative only to the extent that the present resembles the past (U.S. Department of Energy, 2012). Reference class forecasting remains valuable, but the class must be updated (Flyvbjerg, 2008), and the choice of class should be examined whenever a structural change is suspected (Love & Ahiaga-Dagbui, 2018).
The simulation also shows why informal attention to schedule risk tends to be misdirected. Because most procurement lines have little influence on the finish date (Hulett, 2009), a review that treats all lines equally spreads effort thinly, whereas a review that follows the sensitivity ranking concentrates effort where it pays (Kraljic, 1983).
6.2. Preventable Planning Failures Versus Unavoidable External Factors
6.2.1. What the Decomposition Shows
The decomposition in Section 5.3.1 attributes 17 percent of the gap between plan and expected outcome to planning method and 83 percent to the market shift. Such an interpretation is incorrect as the three mitigation options together are able to recover approximately 36 percent of the market-shift penalty at the median (Christopher & Peck, 2004). This reading estimates that about 17 percent (plus 30 percent) of the gap is due to owner decisions, but that 53 percent is what remains unaddressable by any single owner (Ho et al., 2015; Tang, 2006).
The figures were presented as examples of the logic and are not intended as an estimate of any particular owner (Hulett, 2009). The added value in their role is that they proved that the preventable share is not so small and not so big, and that they provide a way for an owner to calculate his/her own (Kwak & Ingall, 2007). Only three-point estimates and a well-defined set of scenarios are needed for the method.
6.2.2. Material Price Volatility Revisited
The framing in the topic of this paper suggests a contrast between planning failures and external factors such as material price volatility (Sambasivan & Soon, 2007). The simulation addresses duration rather than price, but the logic carries across. A rise in the price of copper, steel or insulating materials is an external event, and its effect on the budget depends on the owner’s contract form, on whether purchases were made early and on whether escalation clauses are in place (Shane et al., 2009).
Escalation on purchases made late because of delay is also a consequence of schedule slippage (Creedy et al., 2010). The two dimensions are therefore linked, and a schedule that is protected against delay is also protected, to a degree, against price movement that occurs while the project waits (Flyvbjerg et al., 2004). Fixed-price contracts with long validity periods transfer price risk to suppliers (Chopra & Sodhi, 2004), but suppliers who are asked to bear it will price it, and the net effect on total cost depends on the owner’s relative ability to manage the risk (Pich et al., 2002).
6.2.3. The Role of Incentives and Information
Incentives influence which failures are preventable in practice. Where a project is approved on the basis of an optimistic schedule and budget, the person who introduces realism may be penalized, and the organization learns to withhold bad news until late (Flyvbjerg et al., 2002). Optimism and misrepresentation need not be deliberate (Flyvbjerg, 2006), and the correctives, namely independent review, reference-class benchmarks and explicit confidence levels, work whether the cause is cognitive or strategic (Lovallo & Kahneman, 2003).
Information asymmetry between owner and supplier compounds the problem (Gosling & Naim, 2009). Suppliers know their own order books and the state of their factories, but owners generally see only the quoted lead time, which suppliers have an incentive to keep attractive until contract signature (Tang, 2006). Requiring suppliers to state lead times as ranges with confidence levels (Christopher & Peck, 2004), and to update them at defined intervals, reduces that asymmetry at little cost (Herroelen & Leus, 2005).
6.3. A Governance Framework for Long-Lead Procurement
The results suggest a governance framework built on three principles: probabilistic planning, criticality-based attention and early commitment where the market justifies it. Table 12 sets out leading indicators that an owner or regulator can monitor (Craighead et al., 2007), together with the trigger conditions and the actions that should follow (Project Management Institute, 2017).
Table 12 converts the findings into monitoring rules. Each row names an indicator, how it is measured, the threshold at which it triggers and the action required when it does. Most are leading indicators: a quote older than six months, or a factory slot that slips by more than four weeks, signals trouble well before the in-service date is missed, which is the purpose of early warning in managing disruption (Craighead et al., 2007). The third row uses the rank correlation of Equation 6 with a threshold of 0.5, and the last row links to Equation 11 by comparing the weekly cost of delay with the premium per week saved. An owner can adopt the thresholds as stated or recalibrate them to its own data (Project Management Institute, 2017).
6.3.1. Before Project Approval
At the approval stage the owner should require a probabilistic schedule with explicit lead-time ranges for each long-lead item, an outside-view check against a relevant reference class, and a statement of the confidence level attached to the approved date. These requirements address the planning fallacy directly, and they raise the cost of presenting an optimistic schedule (Buehler et al., 1994; Flyvbjerg, 2006).
A register of long-lead items, with the date of the last confirmed quote and the supplier’s stated range, should form part of the approval package. A quote older than a defined number of months should be treated as stale (Gosling & Naim, 2009), and any schedule that relies on it should carry a flag (U.S. Department of Energy, 2012).
6.3.2. At the Procurement Strategy Stage
The criticality of the item should dictate the procurement strategy and not convention of the category (Chopra & Sodhi, 2004). When the item is identified in strategic or bottleneck quadrant of the purchasing portfolio the owner should think about framework agreements, capacity reservation, supplier development and standardization of specifications of the item across projects (Kraljic, 1983). The value of standardization is particularly evident because spares and slots can be moved from one project to another (Blackhurst et al., 2011) and this is how the spare reallocation strategy is reflected in the simulation (Christopher & Peck, 2004).
6.3.2.1. Capacity Reservation and Early Ordering
Early slot reservation was the second most effective single strategy for the median and, together with the others, produced the largest tail protection (Cain & Nelson, 2013). Its cost is the reservation fee and the risk of paying for a slot for a project that is later canceled or delayed, which is a real risk where permitting is uncertain (Vajjhala & Fischbeck, 2007). The break-even condition in Section 5.4 provides the criterion for deciding when the fee is justified (Flyvbjerg et al., 2004; Shane et al., 2009).
6.3.2.2. Dual Sourcing and Supplier Diversification
Dual sourcing protects against the tail and has little effect on the median. It is most important for owners with hard in-service dates and for items where supplier-specific failure is a material risk. Its cost is the loss of scale and the additional engineering required to qualify a second design, so it is best justified where the supply base is wide enough to offer genuine alternatives (Tang, 2006).
6.3.2.3. Spares and Fleet Management
The median saw the best single strategy as “spare reallocation. It is a requirement of the owner to carry spares, to share spares with neighbors or to be part of a voluntary program for the industry, and relies on a standardization of voltage and impedance. The National Infrastructure Advisory Council and the federal assessment both emphasized the importance of spares and standardization to resilience (National Infrastructure Advisory Council, 2024) and the simulation provides a quantitative measure of the benefit (U.S. Department of Energy, 2012).
6.3.3. During Contract Execution
The owner should monitor the indicators in Table 12 in accordance with the execution, such as the age of the last supplier status report, the percentage of design drawings approved against plan, the position in the factory test queue and the status of transport permits. If any of these is delayed, then the new simulation should be performed (Hazır, 2015), as the chances of achieving the date are subject to the evolution of information received (Hulett, 2009).
Rework cycles need to be considered during execution. Late changes to specifications result in redesign in the factory and rework in protection and control systems; the system dynamics literature indicates that the impact of late changes increases as a function of the stage of the project at which the change occurs (Lyneis & Ford, 2007). The normal preventive measure is formal change freeze, which has a senior sign off for exceptions (Ahiaga-Dagbui & Smith, 2014; Shane et al., 2009).
6.4. Implications for Technology Choice and Network Planning
The simulation results presented in Section 3 demonstrate that the cost of the terminal equipment has a considerably larger proportion of HVDC cost compared to HVAC cost, and the simulation results further indicate that the lead time for the terminal equipment can be very significant. Combined these results suggest that the choice of technology should be evaluated after assessing the scheduled exposure as well as cost and losses (Bahrman & Johnson, 2007), especially when the market has limited converter capacity (Flourentzou et al., 2009).
The break-even distances discussed in Section 3.2.3 have been obtained from the cost only. In a market with long converter lead times, such a scheme would include an expected cost of delay, weighted by the probability distribution of converter lead times, and this could shift the break-even point toward greater distances (Alassi et al., 2019). Although this adjustment may not be always in favor of alternating current (U.S. Department of Energy, 2012), it is done to compare the two on the same footing (Van Hertem & Ghandhari, 2010).
Network-level correlation of demand implies network level coordination. Joint procurement, common frameworks and published orders pipelines would enable producers to plan capacity and decrease the strategic unknowns of the other producers (Battaglini et al., 2009). Any proposal of a supergrid (Battaglini et al., 2009) strengthens the case for coordination, since it suggests orders of a magnitude no single owner could place (Van Hertem & Ghandhari, 2010).
6.5. Implications for Regulators and Policy Makers
Budgets are approved by regulators and, in many jurisdictions, are the basis for the incentives that utilities will rely upon for returns on capital (Flyvbjerg, 2014). Under the approach of a deterministic budget and binding utility constraints, there is an incentive to provide an overly optimistic budget and to try to get off the hook if the budget does not materialize. The conversation would change if the schedules were to be made probabilistic with confidence levels, since an outcome late in the range would be a foreseen event and not a failure (Joskow, 2012).
The supply side (Craighead et al., 2007) can also be a target of policy action. The advisory council suggested steps to increase the capacity of local industries and to lessen reliance on imports, and this takes years to show results. Means to reach standardization, shared spares programs and clarity of regulatory treatment of reservation fees are achievable in the meantime and will mitigate the effective lead time experienced by owners (National Infrastructure Advisory Council, 2024).
The last implication is with regard to data (Flyvbjerg, 2005). The data on which reference-class forecasting relies were compiled by academic groups from public sources; the equipment-level data required for the analysis, which is presented here, are privately held by utilities and manufacturers. The existing absence of a standardized class of long-lead items to include substation equipment would be made available if there was a regulatory requirement to report the planned and actual delivery dates of these items in standardized format (Sovacool et al., 2014b).
6.6. Limitations and Directions for Future Research
The main drawback is the assumption of input values for all activities except for the manufacturing of transformers (Williams, 1995). Numerical results are therefore representative of structure and not predictions, and the owner of a site using the approach should use their own data in place of the assumptions. The second is the assumption of independence of activity, which can underestimate joint risk if a common cause contributes to a number of items, and the addition of correlation would increase the distribution (Hulett, 2009).
A third is issues with how the values read from published charts are used (Sovacool et al., 2014a). The values read from some of the published graphs used in Section 5 was approximate and only used for ordering and for comparing qualitatively. The axis labeling was not consistent in some of the graphs and some had lost labels. Conclusions that rely on precise numbers should be validated by checking with the original publications (Sovacool et al., 2014b).
Further study could go in four directions (Lovallo & Kahneman, 2003). Firstly, the data of the owners and producers can be gathered and lead-time distributions of substation equipment can be estimated empirically (Hazır, 2015). Secondly, the model could be expanded with the inclusion of discrete risk events and the estimation of correlation structures from data. Third, an explicit model of the cost side could be constructed, which would allow the break-even condition to be used in actual projects. Fourth, behavioral studies could be conducted to determine if there is a change in the quality of planning submitted based on the probabilistic nature of planning requirements (Zidane & Andersen, 2018).
7. Conclusions
The study has examined the contribution of long-lead equipment procurement to cost overrun and schedule risk in bulk electric system transmission and substation projects. Historical evidence from large reference classes shows that overruns are common (Flyvbjerg et al., 2002), asymmetric and heavy-tailed, and that transmission projects perform better than most other electricity infrastructure on average while still exceeding budget in about two of every five cases (Sovacool et al., 2014a).
Even with pre-shortage inputs, a plan constructed from modal durations only has a 3 percent probability of being achieved by a Monte Carlo model of a 500 kV substation program, and the changed transformer lead times cause the median to increase from approximately 124 to approximately 212 weeks. Transformer manufacture dominates the sensitivity ranking with a rank correlation of 0.95, followed by transformer transport and delivery (0.17) and the owner’s own specification and award decisions (about 0.13 each) (Hulett, 2009), suggesting that owner decisions also influence exposure. The difference between plan and actual is around 17% due to planning method and 83% due to the market shift (of which approximately 36% can be recovered by implementing early slot reservation and dual sourcing and spare reallocation simultaneously).
The difference between a planned failure and an uncontrollable external factor is one of degree (Chopra & Sodhi, 2004) because the external events determine the size of the penalty and the decisions of the owner determine what part of the penalty is borne (Flyvbjerg, 2014; Shane et al., 2009).
Recommendations for practice are given below. Owners should make a probabilistic plan, keep a long-lead item register that is up to date with quotes, focus by criticality and compare the costs of mitigation with the value of weeks saved. Regulators should seek maximum confidence statements rather than just specific dates and should encourage reports on equipment delivery performance, with some standardization and shared spares. The selection of technology to swap between alternating current (AC) and direct current (DC) also should consider schedule exposure as well as cost and losses (Kraljic, 1983; Project Management Institute, 2017).
Systematic collection of delivery data, at equipment level, would be useful to the evidence base for the sector. Until these data can be found, a realistic path forward for scheduling commitments to be honest about uncertainty and robust to market changes is the use of reference-class thinking (Flyvbjerg, 2006) and transparent simulation.
References
- Ahiaga-Dagbui, D. D., & Smith, S. D. (2014). Dealing with construction cost overruns using data mining. Construction Management and Economics, 32(7–8), 682–694. [CrossRef]
- Alassi, A., Bañales, S., Ellabban, O., Adam, G., & MacIver, C. (2019). HVDC transmission: Technology review, market trends and future outlook. Renewable and Sustainable Energy Reviews, 112, 530–554. [CrossRef]
- Ansar, A., Flyvbjerg, B., Budzier, A., & Lunn, D. (2014). Should we build more large dams? The actual costs of hydropower megaproject development. Energy Policy, 69, 43–56. Available at: https://arxiv.org/pdf/1409.0002.
- Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. [CrossRef]
- Bahrman, M. P., & Johnson, B. K. (2007). The ABCs of HVDC transmission technologies. IEEE Power and Energy Magazine, 5(2), 32–44. [CrossRef]
- Battaglini, A., Lilliestam, J., Haas, A., & Patt, A. (2009). Development of SuperSmart Grids for a more efficient utilisation of electricity from renewable sources. Journal of Cleaner Production, 17(10), 911–918. [CrossRef]
- Blackhurst, J., Dunn, K. S., & Craighead, C. W. (2011). An empirically derived framework of global supply chain resiliency. Journal of Business Logistics, 32(4), 374–391. [CrossRef]
- Browning, T. R., & Eppinger, S. D. (2002). Modeling impacts of process architecture on cost and schedule risk in product development. IEEE Transactions on Engineering Management, 49(4), 428–442. [CrossRef]
- Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381. [CrossRef]
- Cain, N. L., & Nelson, H. T. (2013). What drives opposition to high-voltage transmission lines? Land Use Policy, 33, 204–213.
- Cantarelli, C. C., Flyvbjerg, B., Molin, E. J. E., & van Wee, B. (2010). Cost overruns in large-scale transportation infrastructure projects: Explanations and their theoretical embeddedness. European Journal of Transport and Infrastructure Research, 10(1), 5–18. Available at: https://journals.open.tudelft.nl/ejtir/article/download/2864/3054/8043.
- Cantarelli, C. C., van Wee, B., Molin, E. J. E., & Flyvbjerg, B. (2012). Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the lock-in effect. Transport Policy, 22, 49–56. Available at: https://arxiv.org/pdf/1307.2178v1.
- Chopra, S., & Sodhi, M. S. (2004). Managing risk to avoid supply-chain breakdown. MIT Sloan Management Review, 46(1), 53–61. https://sloanreview.mit.edu/article/managing-risk-to-avoid-supplychain-breakdown/.
- Christopher, M., & Peck, H. (2004). Building the resilient supply chain. The International Journal of Logistics Management, 15(2), 1–14. [CrossRef]
- Craighead, C. W., Blackhurst, J., Rungtusanatham, M. J., & Handfield, R. B. (2007). The severity of supply chain disruptions: Design characteristics and mitigation capabilities. Decision Sciences, 38(1), 131–156. [CrossRef]
- Creedy, G. D., Skitmore, M., & Wong, J. K. W. (2010). Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. Journal of Construction Engineering and Management, 136(5), 528–537. [CrossRef]
- Creswell, J. W., & Plano Clark, V. L. (2018). Designing and conducting mixed methods research (3rd ed.). SAGE.
- Eash-Gates, P., Klemun, M. M., Kavlak, G., McNerney, J., Buongiorno, J., & Trancik, J. E. (2020). Sources of cost overrun in nuclear power plant construction call for a new approach to engineering design. Joule, 4(11), 2348–2373. Available at: https://dspace.mit.edu/handle/1721.1/133049.
- Flourentzou, N., Agelidis, V. G., & Demetriades, G. D. (2009). VSC-based HVDC power transmission systems: An overview. IEEE Transactions on Power Electronics, 24(3), 592–602.
- Flyvbjerg, B. (2005). Policy and planning for large infrastructure projects: Problems, causes, cures (Policy Research Working Paper 3781). The World Bank. Available at: https://ppp.worldbank.org/public-private-partnership/sites/default/files/2022-05/wps3781.pdf.
- Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5–15. Available at: https://arxiv.org/pdf/1302.3642.
- Flyvbjerg, B. (2008). Curbing optimism bias and strategic misrepresentation in planning: Reference class forecasting in practice. European Planning Studies, 16(1), 3–21. [CrossRef]
- Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6–19. Available at: https://journals.sagepub.com/doi/reader/10.1002/pmj.21408.
- Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge University Press. [CrossRef]
- Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279–295. Available at: https://arxiv.org/pdf/1303.6604.
- Flyvbjerg, B., Holm, M. S., & Buhl, S. (2004). What causes cost overrun in transport infrastructure projects? Transport Reviews, 24(1), 3–18. Available at: https://arxiv.org/pdf/1304.4476.
- Goldratt, E. M. (1997). Critical chain. North River Press.
- Gosling, J., & Naim, M. M. (2009). Engineer-to-order supply chain management: A literature review and research agenda. International Journal of Production Economics, 122(2), 741–754. [CrossRef]
- Gündüz, M., Nielsen, Y., & Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of Management in Engineering, 29(2), 133–139. [CrossRef]
- Hazır, Ö. (2015). A review of analytical models, approaches and decision support tools in project monitoring and control. International Journal of Project Management, 33(4), 808–815. [CrossRef]
- Hendricks, K. B., & Singhal, V. R. (2005). An empirical analysis of the effect of supply chain disruptions on long-run stock price performance and equity risk of the firm. Production and Operations Management, 14(1), 35–52. [CrossRef]
- Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306. [CrossRef]
- Ho, W., Zheng, T., Yildiz, H., & Talluri, S. (2015). Supply chain risk management: A literature review. International Journal of Production Research, 53(16), 5031–5069. [CrossRef]
- Hulett, D. T. (2009). Practical schedule risk analysis. Gower Publishing.
- Joskow, P. L. (2012). Creating a smarter U.S. electricity grid. Journal of Economic Perspectives, 26(1), 29–48. [CrossRef]
- Kahneman, D., & Tversky, A. (1979). Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313–327.
- Kraljic, P. (1983). Purchasing must become supply management. Harvard Business Review, 61(5), 109–117.
- Kwak, Y. H., & Ingall, L. (2007). Exploring Monte Carlo simulation applications for project management. Risk Management, 9(1), 44–57. [CrossRef]
- Lovallo, D., & Kahneman, D. (2003). Delusions of success: How optimism undermines executives’ decisions. Harvard Business Review, 81(7), 56–63.
- Love, P. E. D., & Ahiaga-Dagbui, D. D. (2018). Debunking ‘fake news’ in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects. Transportation Research Part A: Policy and Practice, 113, 357–368. Available at: https://ideas.repec.org/a/eee/transa/v113y2018icp357-368.html.
- Lyneis, J. M., & Ford, D. N. (2007). System dynamics applied to project management: A survey, assessment, and directions for future research. System Dynamics Review, 23(2–3), 157–189. [CrossRef]
- Malcolm, D. G., Roseboom, J. H., Clark, C. E., & Fazar, W. (1959). Application of a technique for research and development program evaluation. Operations Research, 7(5), 646–669. [CrossRef]
- Meah, K., & Ula, S. (2007). Comparative evaluation of HVDC and HVAC transmission systems. In Proceedings of the IEEE Power Engineering Society General Meeting (pp. 1–5). IEEE. [CrossRef]
- National Infrastructure Advisory Council. (2024). Addressing the critical shortage of power transformers to ensure reliability of the U.S. grid (draft report, June 2024). Cybersecurity and Infrastructure Security Agency. Available at: https://cisa.gov/sites/default/files/2024-06/DRAFT_NIAC_Addressing%20the%20Critical%20Shortage%20of%20Power%20Transformers%20to%20Ensure%20Reliability%20of%20the%20U.S.%20Grid_Report_06052024_508c.pdf.
- Odeck, J. (2004). Cost overruns in road construction: What are their sizes and determinants? Transport Policy, 11(1), 43–53. [CrossRef]
- Pich, M. T., Loch, C. H., & De Meyer, A. (2002). On uncertainty, ambiguity, and complexity in project management. Management Science, 48(8), 1008–1023. [CrossRef]
- Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
- Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. [CrossRef]
- Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C. (2009). Construction project cost escalation factors. Journal of Management in Engineering, 25(4), 221–229. [CrossRef]
- Sovacool, B. K., Gilbert, A., & Nugent, D. (2014a). Risk, innovation, electricity infrastructure and construction cost overruns: Testing six hypotheses. Energy, 74, 906–917. Available at: https://ideas.repec.org/a/eee/energy/v74y2014icp906-917.html.
- Sovacool, B. K., Gilbert, A., & Nugent, D. (2014b). An international comparative assessment of construction cost overruns for electricity infrastructure. Energy Research & Social Science, 3, 152–160. Available at: https://sussex.figshare.com/articles/journal_contribution/An_international_comparative_assessment_of_construction_cost_overruns_for_electricity_infrastructure/23424974.
- Sovacool, B. K., Nugent, D., & Gilbert, A. (2014c). Construction cost overruns and electricity infrastructure: An unavoidable risk? The Electricity Journal, 27(4), 112–120. Available at: https://srodev.sussex.ac.uk/id/eprint/58376/.
- Tang, C. S. (2006). Perspectives in supply chain risk management. International Journal of Production Economics, 103(2), 451–488. [CrossRef]
- U.S. Department of Energy. (2012). Large power transformers and the U.S. electric grid. Office of Electricity Delivery and Energy Reliability (updated edition 2014). Available at: https://www.energy.gov/oe/articles/large-power-transformers-and-us-electric-grid-report-june-2012.
- Vajjhala, S. P., & Fischbeck, P. S. (2007). Quantifying siting difficulty: A case study of U.S. transmission line siting. Energy Policy, 35(1), 650–671.
- Van Hertem, D., & Ghandhari, M. (2010). Multi-terminal VSC HVDC for the European supergrid: Obstacles. Renewable and Sustainable Energy Reviews, 14(9), 3156–3163.
- Van Slyke, R. M. (1963). Monte Carlo methods and the PERT problem. Operations Research, 11(5), 839–860. [CrossRef]
- Williams, T. M. (1995). A classified bibliography of recent research relating to project risk management. European Journal of Operational Research, 85(1), 18–38. [CrossRef]
- Zidane, Y. J.-T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business, 11(3), 650–672. [CrossRef]
Figure 1.
Frequency distribution of cost escalation across 401 electricity infrastructure projects (redrawn by the author; data from Sovacool et al., 2014a, 2014c).
Figure 1.
Frequency distribution of cost escalation across 401 electricity infrastructure projects (redrawn by the author; data from Sovacool et al., 2014a, 2014c).

Figure 3.
Rank-correlation sensitivity of project duration to individual procurement activities.

Figure 4.
Median and P80 project duration under alternative procurement strategies.

Table 1.
Principal empirical datasets on cost and schedule overruns used as reference classes.
| Study | Sample | Period | Principal finding relevant to this paper |
|---|---|---|---|
| Flyvbjerg et al. (2002, 2004) | 258 transport projects (rail, bridges, tunnels, roads), about US$90 billion | Multi-decade | Mean cost 28% above estimate; nine of ten projects overran; escalation rises with implementation-phase length |
| Sovacool et al. (2014a, 2014b) | 401 electricity projects in 57 countries; about US$820 billion; 8,495 km of line | 1936–2014 | Nuclear highest in percentage terms, hydro in absolute dollars; financing, partnerships, modularity and accountability matter |
| Sovacool et al. (2014c) | Same 401-project dataset | 1936–2014 | Three of four projects underestimated; only 39 with no overrun |
| Ansar et al. (2014) | 245 large dams in 65 countries | 1934–2007 | Mean cost overrun of 96%; eight of ten dams late |
| Eash-Gates et al. (2020) | 107 U.S. nuclear plants (overnight cost) | Five decades | Soft costs (engineering, procurement, planning, scheduling) drive escalation |
| Odeck (2004) | 620 Norwegian road projects | Multi-year | Just over half overran, by a mean of about 8% |
| Cantarelli et al. (2012) | Dutch transport infrastructure projects | Multi-year | Lock-in effect associated with larger overruns |
Table 2.
Classification of escalation sources into preventable planning failures and external factors.
Table 2.
Classification of escalation sources into preventable planning failures and external factors.
| Source of escalation | Primary class | Owner-controllable exposure | Illustrative mitigation |
|---|---|---|---|
| Optimistic duration assumptions (inside view) | Preventable | Full | Outside-view benchmarks; probabilistic schedule |
| Stale or unverified vendor lead times | Preventable | Full | Dated quote register; refresh triggers |
| Scope incomplete at award; late design change | Preventable | Full | Scope freeze; change control board |
| Weak interface and protection/control integration | Preventable | High | Early interface specification; factory acceptance testing |
| Contract form that leaves risk with weaker party | Preventable | High | Risk allocation review; indexation clauses |
| Slow internal approvals and award decisions | Preventable | Full | Decision-time targets; delegated authority |
| Commodity price shock (steel, copper) | External | Partial (timing, contract form) | Early purchase; price indexation; hedging |
| Market-wide manufacturing capacity shortage | External | Partial (reservation, standardization) | Slot reservation; framework agreements; spares |
| Permitting and law changes | External | Partial (stakeholder engagement) | Early engagement; staged commitment |
| Geopolitical or transport disruption | External | Low to partial | Supplier diversification; route planning |
| Extreme weather and force majeure | External | Low | Schedule buffers; insurance |
Table 3.
Comparison of schedule analysis approaches against the needs of long-lead procurement.
| Approach | Core idea | Strengths | Limitations for long-lead items |
|---|---|---|---|
| Critical path method (CPM) | Longest path of deterministic activities governs finish | Simple; widely used; identifies float | Ignores uncertainty; understates merge effects |
| PERT three-point estimate | Beta-type durations with fixed critical path | Introduces ranges; easy to audit | Bias when several near-critical paths merge |
| Monte Carlo schedule risk analysis | Sample durations; recompute network; summarize distribution | Probability of date; driver ranking; scenario testing | Needs credible inputs; correlation often ignored |
| Critical chain and buffers | Remove padding; manage project and feeding buffers | Targets behavior; clear buffer signals | Addresses variation more than structural mean shift |
| System dynamics | Feedback loops of rework and pressure | Captures rework and knock-on effects | Data-hungry; harder to audit |
| Design structure matrix modeling | Task interdependence and iteration | Shows iteration risk in design phases | Less suited to purchase-and-deliver chains |
| Reference class forecasting | Outside view from comparable projects | Bypasses optimism bias | Class must be current and comparable |
Table 4.
Principal long-lead equipment classes and the features that make them schedule-critical.
| Equipment class | Typical lead-time driver | Schedule risk characteristic | Procurement note |
|---|---|---|---|
| Large power transformers (100 MVA and above) | Core steel supply, design, winding, testing, heavy transport | Dominant critical-path item; lead times 5–16 months before the shortage, 80–210 weeks in 2024 | Strategic item; consider reservation and standardization |
| Generator step-up and converter transformers | Special design; limited supplier base | Very long lead; few alternatives | Early engagement with vendors |
| Shunt and series reactors | Shared factory capacity with transformers | Lead time rises with transformer demand | Procure alongside transformers |
| Gas-insulated switchgear and HV breakers | Per-project configuration; factory slots | Moderate; becomes tight in high-demand periods | Framework agreements |
| HVDC converter valves and controls | Specialized design; few suppliers | Terminal cost share high; supplier concentration | Technology choice should weigh supply risk |
| Protection, control and communications | Engineering, integration and factory acceptance tests | Late scope change causes rework | Freeze philosophy early |
| Structures, conductors and hardware | Steel and aluminum supply; fabrication | Usually off the critical path unless scope changes | Standard catalog purchasing |
Table 5.
Cost structure of HVAC and HVDC options reported in the literature and associated schedule exposure (approximate values; Alassi et al., 2019; Flourentzou et al., 2009; Meah & Ula, 2007).
Table 5.
Cost structure of HVAC and HVDC options reported in the literature and associated schedule exposure (approximate values; Alassi et al., 2019; Flourentzou et al., 2009; Meah & Ula, 2007).
| Option (600 km, overhead) | Overhead line share | Terminal or station share | Break-even or distance note | Schedule exposure |
|---|---|---|---|---|
| HVAC, 2,000 MW single circuit, 500 kV | 83% | 10% substation, 7% series capacitor | AC cost rises more steeply with distance | Mostly line construction and permitting; moderate equipment risk |
| HVAC, 4,000 MW double circuit, 500 kV | About 81% (derived) | 11% substation, 8% series capacitor | Same relationship | As above, with more transformers and compensation |
| HVDC LCC, 3,000 MW, ±500 kV | 57% | Converter stations make up most of the remainder; electrode line very small | Break-even about 600–800 km overhead; about 48–96 km cable; about 50 km submarine | Concentrated in converter transformers and valves; narrow supplier base |
| HVDC VSC with cable (cost per kWh chart) | Not applicable | Converter stations | Reported as lowest cost at long distance | Similar converter concentration |
Table 6.
Procurement milestones used in the model and the schedule risk checkpoint at each.
| Milestone | Model activity | Checkpoint question | Evidence required |
|---|---|---|---|
| Needs identification and specification | Specification and approvals | Is scope frozen and are ratings standardized? | Signed specification; change log |
| Market sounding | Specification and approvals | Are quoted lead times dated and given as ranges? | Quote register with dates and confidence |
| Bid evaluation and award | Bid evaluation and award | Was schedule weighed alongside price? | Evaluation matrix with schedule score |
| Manufacture of main item | Transformer, GIS, reactor, P&C supply | Is factory slot confirmed and tracked? | Slot confirmation; monthly progress |
| Factory acceptance and shipment | Transformer transport and delivery | Are transport permits and routes secured? | Route survey; permit status |
| Site installation | Installation | Are foundations and outages ready? | Civil completion certificate; outage plan |
| Testing and energization | Testing and commissioning | Are protection and control tests scheduled? | Test plan and resources |
Table 9.
Simulated total project duration (weeks) by scenario, 10,000 trials each; plan = 107 weeks.
Table 9.
Simulated total project duration (weeks) by scenario, 10,000 trials each; plan = 107 weeks.
| Scenario | Mean | P10 | P50 | P80 | P90 | P(finish within plan) |
|---|---|---|---|---|---|---|
| Baseline (pre-shortage inputs) | 124.6 | 111.9 | 124.4 | 133.1 | 137.5 | 3% |
| Current market (2024 range) | 214.3 | 180.7 | 211.6 | 238.9 | 253.5 | 0% |
| M1 early slot reservation | 198.2 | 166.8 | 194.3 | 221.3 | 236.1 | 0% |
| M2 dual sourcing | 211.0 | 182.6 | 208.7 | 230.7 | 242.1 | 0% |
| M3 spare reallocation | 192.4 | 148.7 | 189.0 | 224.0 | 242.9 | 0% |
| M1+M2+M3 combined | 181.1 | 148.3 | 179.9 | 201.9 | 216.2 | 0% |
Table 11.
Effect of mitigation strategies relative to the current-market case (weeks saved).
| Strategy | Mechanism modeled | Median saved | P80 saved | P90 saved | Principal trade-off |
|---|---|---|---|---|---|
| Early slot reservation (M1) | Transformer clock starts after approvals, before award | 17.2 | 17.6 | 17.4 | Reservation fee; stranded-cost risk |
| Dual sourcing (M2) | Two suppliers, earliest delivery, +10% duration for split lots | 2.9 | 8.2 | 11.4 | Lost scale; second design qualification |
| Spare reallocation (M3) | 40% chance a spare replaces manufacture | 22.5 | 15.0 | 10.6 | Carrying cost of spares; standardization |
| Combined (M1+M2+M3) | All three applied together | 31.7 | 37.0 | 37.4 | Sum of the above |
Table 12.
Leading indicators for governance of long-lead procurement.
| Indicator | Measurement | Trigger condition | Required action |
|---|---|---|---|
| Age of last confirmed lead-time quote | Months since quote | Greater than 6 months | Refresh quote; rerun simulation |
| Probability of meeting committed date | Simulation output | Below stated confidence level | Escalate; review mitigation options |
| Share of schedule variance from top item | Rank correlation | Above 0.5 | Assign senior owner to the item |
| Design drawing approval versus plan | Percent behind plan | More than 10% behind | Executive review; resource addition |
| Position in factory test queue | Weeks to slot | Slot slips by more than 4 weeks | Invoke contract remedies; consider spare |
| Change requests after scope freeze | Count per quarter | More than 2 for a critical item | Change board; cost and schedule impact statement |
| Transport permit and route status | Percent complete | Not complete at factory test | Expedite permits; alternative route |
| Weekly cost of delay | Currency per week | Rises above mitigation premium per week saved | Exercise reservation or spare option |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the author. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Copyright: This open access article is published under a Creative Commons CC BY 4.0 license, which permit the free download, distribution, and reuse, provided that the author and preprint are cited in any reuse.