Ex-Post Value for Money (VfM) Analysis in US Highway Projects

Submitted:

19 October 2026

Posted:

20 October 2026

You are already at the latest version

Abstract
Public-private partnerships (P3s) have become an increasingly adopted delivery method for major U.S. highway infrastructure, with Value for Money (VfM) analysis serving as the primary analytical basis for procurement decisions. VfM assessments compare the estimated cost of conventional public delivery against the risk-adjusted cost of private delivery to determine the preferred pro-curement approach. While VfM analysis has been well-established at the procurement stage, no published peer-reviewed study has examined whether these estimates remain consistent with outcomes observed after project completion. This study addresses that gap by reconstructing pro-curement-stage and post-completion VfM values for seven completed U.S. highway projects using the FHWA P3-VALUE toolkit as a standardized analytical framework, with post-completion values updated using realized project data while maintaining a consistent model structure and discount rate. A Wilcoxon signed-rank test was applied to assess whether systematic differences existed between paired estimates. The Wilcoxon signed-rank test did not detect a statistically significant difference between procurement-stage and post-completion VfM estimates (exact two-sided p = 0.6875). VfM increased in three projects and decreased in four, while all seven projects retained their original directional VfM conclusions when the available post-completion information was incor-porated. However, the small sample size and limited statistical power mean that the non-significant result does not establish equivalence or demonstrate the general stability of procurement-stage VfM assessments.
Keywords: 
;  ;  ;  ;  

1. Introduction

Public-private partnerships (P3S) have become an increasingly important procurement mechanism for delivering large-scale highway infrastructure projects in the United States over the past two decades. They are primarily used for high-cost, capital-intensive projects where governments face significant funding constraints, complex risk profiles, and long-term operational commitments. Highway P3 projects often involve investments ranging from hundreds of millions to several billion dollars and establish contractual obligations that can extend for 30 to 50 years [1]. These characteristics make P3s particularly relevant for major infrastructure investments requiring substantial upfront capital and lifecycle management. According to the Congressional Budget Office [2] P3S have accounted for only 1-3% of highway, transit, and water infrastructure spending since 1990. However, their role in highway capital investment has grown over the past decade, with the share of private financing repaid directly by governments through availability payments rising from 17% to 44%, and the federal taxpayer subsidy share of private financing rising from 25% to 49% [2]. The Federal Highway Administration’s Report on Highway Public-Private Partnership Concessions in the United States [3] identified 28 highway P3 concessions implemented since 1992 and classified them into three categories: real toll concessions, availability payment concessions, and long-term leases of existing facilities. The report also documents a clear post-2009 migration from real toll to availability payment structures. More recent market assessments indicate continued growth to approximately 43 highway, bridge, and tunnel transportation P3 projects that have reached financial close in the United States, including 22 Design-build-finance-operate-maintain (DBFOM) toll projects, 15 availability payment projects, and 6 long-term lease concessions.
Given the scale and duration of these projects, governments must evaluate whether infrastructure should be delivered through traditional procurement methods, such as design-bid-build (DBB), or through a P3 arrangement. This decision cannot be based solely on initial construction costs because the two approaches differ in their risk allocation, financing mechanisms, and operational and maintenance responsibilities throughout the asset lifecycle. Selecting the procurement approach, therefore, requires a comprehensive assessment of long-term costs, risks, and project performance outcomes. Value for Money (VfM) analysis addresses this need by providing a structured framework for comparing traditional procurement and P3 delivery on a common basis. It is the formal analytical tool used by governments to determine whether a project should proceed through conventional delivery methods, such as design-bid-build (DBB), or through a P3 arrangement. Rather than focusing only on initial construction costs, VfM evaluates which procurement approach delivers greater value over the project lifecycle. The widely accepted definition of VfM as the optimum combination of whole-of-life costs and quality to meet user requirements originated from the United Kingdom’s Private Finance Initiative framework and was later adopted in U.S. transportation practice [4,5].
The analytical core of VfM is the comparison between the Public Sector Comparator (PSC) and the shadow bid (or actual P3 bid). The PSC estimates the risk-adjusted whole-of-life cost of conventional public procurement, while the shadow bid represents the equivalent lifecycle cost under P3 delivery. The procurement decision is then based on comparing the net present costs of the alternatives [1]. This comparison incorporates four key components: whole-of-life costing, risk adjustment, discounting, and net present cost evaluation. Together, these elements account for differences in lifecycle costs, risk allocation, financing structures, and long-term obligations between procurement methods [1]. VfM has become a standard evaluation tool in P3 practice internationally and has been operationalized in the United States through Federal Highway Administration guidance and the P3 VALUE toolset [6,7,8,9]. More recently, the Bipartisan Infrastructure Law of 2021 (§70701) formalized its role by requiring VfM analysis for transportation P3 projects receiving federal support [10].
While VfM is widely applied before procurement decisions are made, it is rarely revisited after project delivery. The Public-Private Infrastructure Advisory Facility (PPIAF, 2013) and the World Bank Institute (2013) note that few governments systematically conduct ex-post VfM assessments, while the UK National Audit Office (2011) reported insufficient evidence to determine whether private finance consistently delivered better value than traditional procurement, despite decades of Private Finance Initiative (PFI) experience. This gap is particularly evident in the United States, where no published peer-reviewed study has conducted an ex-post reassessment of a U.S. highway P3 VfM analysis using post-completion project data. Existing international evidence remains limited but raises questions regarding the accuracy of ex-ante VfM assumptions and outcomes [11,12].
This study addresses this gap by conducting an ex-post reassessment of VfM outcomes for U.S. highway P3 projects. The study focuses on highway projects that underwent VfM analysis during the procurement stage and for which sufficient public information is available. Procurement-stage assumptions and inputs are compiled from the original project documentation, while post-completion and operational information is collected from project records. The study then revisits the original procurement-stage evaluations, using project performance information obtained after implementation, to examine whether the initial VfM conclusions remain consistent over time. Unlike previous studies that primarily examine VfM guidance, methodologies, or theoretical applications, this research evaluates actual project-level VfM analyses used in procurement decision-making. To ensure comparability across projects, all evaluations are conducted using a common analytical framework based on the FHWA P3 VALUE 2.3 toolkit, as agency-developed VfM models are often unavailable or inconsistent. This standardized approach enables differences between ex-ante and ex-post results to reflect project performance and outcomes rather than methodological variation. In this study, ex-post VfM refers to a reassessment of the original procurement-stage comparison using available post-completion information for the implemented delivery alternative. It does not fully measure realized whole-life VfM because the unselected procurement alternative cannot be directly observed, and comparable lifecycle information remains incomplete. Accordingly, the results are interpreted as partial updates to the original procurement-stage estimates rather than definitive evaluations of whole-life VfM outcomes.

2. Research Objectives

The objectives of this study are:
  • To examine the magnitude, direction, and project-level patterns of differences between procurement-stage and post-completion VfM estimates for completed U.S. highway projects and to assess whether the original directional VfM conclusions are retained.
  • To examine changes in key project inputs associated with differences between procurement-stage and post-completion VfM estimates.

3. Literature Review

3.1. VfM Methodology

Value for Money (VfM) analysis serves as the principal framework for determining whether a government project should be delivered through conventional public procurement or a public–private partnership (P3) arrangement. Developed from the United Kingdom’s Private Finance Initiative and subsequently improved in jurisdictions such as Australia, Canada, and the United States, the methodology evaluates alternative procurement approaches by comparing their risk-adjusted costs over an equivalent concession period [4,5]. Central to this assessment is the Public Sector Comparator (PSC), a benchmark representing the expected whole-of-life cost of conventional public delivery. The PSC is constructed from four components: (1) the raw PSC, representing baseline capital and operating costs under traditional procurement financed through public debt; (2) a competitive neutrality adjustment, which removes advantages associated with government taxation status, insurance arrangements and borrowing costs; (3) transferable risk, valued as the probabilistic present value of risks that can be allocated to a private partner; and (4) retained risk, representing the expected cost of risks that remain with the public sector [1,13]. The PSC compares the cost of delivering the project under a P3 structure. The shadow bid incorporates baseline construction and operating costs, private financing costs based on the project’s weighted-average cost of capital, tax obligations, transferred-risk contingencies, and retained-risk allocations. Federal Highway Administration guidance further allows for assumed private-sector efficiency gains, typically ranging from 0 to 15% relative to the PSC baseline [8]. Together, these elements generate risk-adjusted present value estimates for each procurement alternative. A positive VfM outcome occurs when the risk-adjusted present value of the shadow bid is lower than that of the PSC, indicating that private-sector delivery is expected to provide greater value for taxpayers and thereby justifying the selection of the P3 procurement model [1].
The institutional architecture of VfM has converged around a small set of frameworks. The World Bank PPP Reference Guide [14,15] and the OECD Principles for Public Governance of Public-Private Partnerships [16] jointly establish the international template. Burger & Hawkesworth emphasize that differences in capital and budget treatment can bias procurement choices when P3s receive favorable accounting treatment unavailable under traditional procurement [15]. Consequently, VfM analysis is intended to ensure that procurement choices reflect the underlying economic value rather than capital costs. Within the U.S. context, the Federal Highway Administration P3 VALUE tool [9] operationalizes this framework with a specific set of structural assumptions: an agency borrowing rate for the PSC, a market-based weighted average cost of capital for the P3, and a Monte Carlo simulation for risk quantification. Kweun [17] conducted the only published comparative academic analysis of U.S. highway VfM studies. They found substantial variation across state agencies in the treatment of transferred risks, cost benchmarks, and financing assumptions. This variation reflects the non-mandatory nature of federal guidance. Boardman & Hellowell [18] reached a similar conclusion in their cross-jurisdictional review of VfM methodologies. They argued that many VfM analyses deviate from theoretical best practice and are therefore conducted incorrectly. This finding is particularly important for ex-post validation research because it suggests that errors may originate in the ex-ante methodology itself rather than in differences between forecasts and post-completion outcomes.
The theoretical case for P3 procurement is grounded in the work of Hart [19] and later developed by Iossa & Martimort [20]. Their central argument is that bundling design, construction, and operations within a single long-term contract creates positive impacts between upfront construction quality and lifecycle maintenance costs. When construction quality and future maintenance costs are positively linked, a private partner has an incentive to invest more during construction to reduce future operating and maintenance expenses. These lifecycle savings can offset the higher financing costs typically associated with private capital. However, Engel [21] demonstrates that P3s do not generate additional public resources in present-value terms. As a result, the justification for P3 procurement cannot rest on fiscal relief or financing advantages. Instead, any value gain must come from genuine efficiency improvements and effective risk transfer. These theoretical conditions provide the basis for ex-post VfM validation.

3.2. Factors Contributing to VfM Analysis

3.2.1. Construction and Lifecycle Cost Estimates

Construction and lifecycle cost estimates are among the most influential inputs in VfM analysis. Because P3 concessions typically bundle design, construction, financing, operations, and maintenance over periods of 25 to 50 years, the VfM outcome depends on assumptions about costs throughout the asset lifecycle [1,19]. Errors in these estimates can materially affect both the Public Sector Comparator (PSC) and the P3 shadow bid, creating differences between ex-ante forecasts and ex-post outcomes. Evidence suggests that capital costs are frequently underestimated during project planning. Flyvbjerg [22] reported average cost overruns of 20.4% for road projects and found a slight improvement in forecasting accuracy over time. Similar patterns have been documented across jurisdictions, although the magnitude of overruns varies with institutional context and project development stage [23,24]. Research also indicates that conventional procurement may not fully capture the cost of construction risk. Edwards [25] identified a construction cost premium of approximately 25% for UK public-finance-initiative road projects relative to conventional procurement. Blanc-Brude [26] reported a similar 24% premium across 227 European road projects and found that the cost overruns closely corresponded to that of typically observed in traditionally procured roads. Their findings suggest that higher PPP bid prices may reflect the explicit pricing of construction risk rather than inefficiency. Recent U.S. evidence points to differences in post-completion cost performance across delivery models. Shrestha [27] compared highway projects delivered through P3, Design-Build, and Design-Bid-Build methods and found lower average cost growth for P3 projects than for conventionally procured alternatives. These findings highlight the importance of construction and lifecycle cost assumptions in shaping both ex-ante and ex-post VfM assessments.

3.2.2. Traffic and Revenue Projections

For real toll P3 concessions, traffic and revenue forecasts are among the most important assumptions in VfM analysis. These forecasts influence project revenues, financing viability, and the valuation of demand risk transfer between the public and private sectors. Evidence suggests that toll road traffic forecasts are often overly optimistic. In an analysis of more than 100 internationally financed toll roads, Bain [28] reported an average Year 1 actual-to-forecast traffic ratio of 0.77, indicating a 23% overestimation of demand. The study found that this bias persisted through Year 5 and could not be explained solely by traffic ramp-up effects. Importantly, Bain observed that comparable forecasts for toll-free public roads did not exhibit the same pattern, suggesting that optimism may be associated with the commercial forecasting environment of toll concessions rather than with transportation modeling techniques themselves. More recent evidence from the United States indicates that demand forecasting remains a significant challenge for highway P3 projects. Gifford [29] has documented several highway concessions that experienced substantial traffic and revenue shortfalls relative to projections at the procurement stage. Such deviations can affect the post-completion allocation of demand risk and alter the concession’s financial performance. Because demand forecasts influence both projected revenues and the pricing of risk transfer, errors in these assumptions can contribute to differences between ex-ante and ex-post VfM results. Traffic and revenue forecasts, therefore, represent an important source of uncertainty in VfM analysis.

3.2.3. Risk Evaluation

Risk adjustment is one of the most influential components of VfM analysis. Within the Public Sector Comparator (PSC), transferable risks are assigned a monetary value and added to the estimated cost of conventional procurement. Because these adjustments can be substantial, the treatment of risk often plays a decisive role in determining whether a P3 project appears to offer greater value than traditional delivery. Most VfM frameworks estimate transferable risk using probabilistic risk registers and simulation techniques such as Monte Carlo analysis. In contrast, retained risks are valued according to their expected cost to the public sector [30]. Although these methods provide a structured approach to risk assessment, their reliability depends heavily on the quality of underlying data and the assumptions used to generate risk distributions [31,32]. In many cases, these assumptions are not publicly disclosed or independently validated [33,34]. Siemiatycki & Farooqi [35], in an analysis of 28 Ontario P3 projects, found that risk premiums averaged 49% of PSC base costs and were responsible for generating positive VfM results. Although the P3 projects had higher base costs than comparable design-bid-build projects, the assigned risk premiums more than offset the financing premium associated with private delivery. The Office of the Auditor General of Ontario [11] later concluded that the risk valuations used in these assessments lacked support and estimated that the additional cost of P3 delivery across 74 projects was approximately C$8 billion relative to conventional procurement. These findings have generated broader theoretical criticism of VfM risk adjustment practices. Froud [36] argues that PSC methodologies may convert uncertainty into quantified risk without adequate justification. Similarly, Quiggin [34] contends that public-sector risk pooling reduces the social cost of risk-bearing, calling into question the magnitude of risk premiums often assigned to conventional procurement. Together, these concerns suggest that risk valuation remains a significant source of uncertainty in VfM analysis and a potential contributor to divergence between ex-ante forecasts and ex-post outcomes.

3.2.4. Discount Rate

The choice of discount rate is another of the most influential assumptions in VfM analysis because it determines how future costs and benefits are converted to present value. Since P3 concessions typically extend over several decades, even small changes in the discount rate can have a substantial effect on estimated project costs and the resulting VfM outcome. A longstanding debate concerns whether future cash flows should be discounted using a Social Time Preference Rate (STPR) or a project-specific Weighted Average Cost of Capital (WACC). Grout [37] and Spackman [38] demonstrate that applying different discounting methodologies to the same cash flows can yield substantially different, and sometimes opposite, VfM conclusions. This issue is particularly important in P3 evaluations because many frameworks apply a social discount rate to the Public Sector Comparator (PSC) while incorporating market-based financing costs into the P3 option. Research demonstrates the sensitivity of VfM results to discount rate assumptions. Zwalf [39] found that a one-percentage-point change in the discount rate can alter net present costs by 10 to 20% over a 30-year concession period. Such changes may be large enough to reverse the procurement recommendation. Other scholars have similarly argued that discount rate selection can influence VfM outcomes and may contribute to inconsistencies across jurisdictions [33,40,41].

3.3. Ex Post Validation of VfM

Given the sensitivities embedded in VfM analysis, an important question is whether the ex-ante conclusions used to justify P3 procurement are supported by actual project outcomes. Existing research suggests that this question has received surprisingly little attention. In the U.S. highway sector, no study has reconstructed completed projects to determine whether the original VfM conclusion remains valid when evaluated using post-completion data. A distinction must be made between conventional ex-post evaluation and ex-post VfM validation. Conventional ex-post evaluation focuses on project performance. Typical measures include whether costs were on budget, whether schedules were met, and whether services were delivered as specified. Ex-post VfM validation addresses a different question: whether the original procurement decision was justified. Answering this question requires reconstructing PSC and P3 comparison using post-completion project data and reassessing the resulting procurement outcome. The literature contains numerous studies of project delivery performance, but few attempts to validate ex-ante VfM conclusions. As a result, there remains limited evidence on whether the procurement decisions supported by VfM analysis are confirmed or contradicted by actual project experience.
The literature on ex-post evaluation of P3S is fragmented and spans several distinct research traditions. Broadly, existing studies can be grouped into three categories: (1) academic studies that reconstruct the original VfM comparison using outturn data, (2) performance and audit studies that assess project outcomes against procurement stage expectations, and (3) forensic financial analyses that examine realized investor returns and special purpose vehicle (SPV) performance. While all three contribute to understanding P3 outcomes, they differ in their objectives and methods.
The first category is the most directly relevant to ex-post VfM validation because it reassesses the original procurement decision. However, such studies remain rare. Sukasuka [42], in a PRISMA-based scoping, reviews only 27 peer-reviewed studies worldwide addressed ex-post P3 evaluation. Ghorban and Cui developed one of the first formal frameworks for ex-post VfM analysis. Their framework specifies the processes, data requirements, and analytical procedures needed to reassess VfM at various stages of the project lifecycle. It provides a methodological foundation for systematic ex-post validation. Despite this contribution, the applications remain limited. The clearest example of ex-post VfM reconstruction is provided by Kim [12], who has reopened the original ex-ante VfM models for three Korean road P3 projects and replaced forecast assumptions with outturn values for discount rates, interest rates, traffic volumes, and project costs while maintaining the original analytical framework. Two of the three projects no longer delivered the VfM anticipated at the time of procurement, primarily because financing conditions changed significantly after contract execution. Their substitution approach, which holds the model structure constant while replacing forecast inputs with observed values, provides the closest methodological precedent for the present study. An earlier example is Boardman [43], who conducted an ex-post cost-benefit analysis of the Coquihalla Highway in British Columbia and reported a less favorable outcome than predicted in the original appraisal.
The second category consists of performance and audit studies. These studies typically assess project delivery, operational performance, and contract management rather than reconstructing the full PSC-versus-P3 comparison. A substantial body of research has evaluated post-completion project performance using measures such as cost growth, schedule performance, and service outcomes. For example, Chasey [44] compared completed P3 projects with traditional delivery methods, while Shrestha [27] examined cost and schedule performance across U.S. highway projects delivered through P3, Design-Build, and Design-Bid-Build methods. Such studies provide useful evidence on delivery performance but do not reassess whether the original procurement decision remained value-enhancing when evaluated using outturn data. The UK National Audit Office [45] has conducted the most extensive program of operational P3 reviews. NAO [45] found that 76% of PFI projects were completed on time and 78% on budget, outperforming conventional procurement on both measures. However, later reviews raised broader questions regarding long-term value. The NAO [46] concluded that systematic ex-post VfM evaluation had not been undertaken across the PFI portfolio and that available evidence was insufficient to determine whether private finance had consistently delivered value. Its subsequent review of more than 700 operational PFI and PF2 contracts questioned several assumptions embedded in procurement stage assessments and found limited evidence that higher financing costs were consistently offset by improved performance [47]. Similarly, the Office of the Auditor General of Ontario [11] estimated C$8 billion in additional costs across 74 Infrastructure Ontario projects and challenged the risk premium assumptions used in the original analyses.
Performance and audit reviews have also identified broader challenges in ex-post evaluation. The European PPP Expertise Center [48] identified substantial limitations in data availability and methodological consistency across international PPP evaluations, making it difficult to determine whether projects achieved their anticipated VfM. The UK House of Lords Economic Affairs Committee similarly emphasized the importance of evaluating operational PPP projects against their original objectives. Still, it noted the absence of a formal requirement for such assessments. Shu [49] reached a similar conclusion, finding that post-project evaluations remained uncommon despite the large number of operational PFI projects. Collectively, these studies point to a persistent weakness in the institutional feedback mechanisms needed to validate assumptions at the procurement stage and improve future VfM assessments. The evidence is not uniformly critical, however. The NAO [50] found that operational hospital PFI contracts had performed in line with expectations established at contract signing, demonstrating that ex-post assessments do not necessarily invalidate ex-ante conclusions.
The third category comprises forensic financial analyses that examine post-completion concession performance through SPV financial statements, refinancing transactions, and investor returns. Shaoul [51] reconstructed the financial history of the first eight UK DBFO shadow toll roads and found post-tax returns above the public sector cost of capital. Toms [52] reported similarly high realized returns in PFI hospital refinancing transactions, while Acerete [53] documented comparable patterns across two decades of UK and Spanish DBFO road projects. These studies question whether the financial outcomes realized by private investors are consistent with the levels of risk transfer assumed in ex ante VfM analyses. However, they focus on individual components of the VfM case rather than reconstructing the full PSC–P3 comparison.
Despite growing interest in ex-post PPP evaluation, direct validation of procurement decisions remains rare. Liu [54] notes that most ex-post studies focus on project delivery outcomes rather than procurement choice, while Hodge & Greve [55] argue that the lack of systematic reassessment can no longer be attributed to a lack of operational experience. International organizations, including the World Bank and the IMF, have similarly emphasized the need for the systematic collection of outturn performance data to improve future VfM assessments and better understand long-term fiscal risks.
The observed gap is significant in the United States. No published peer-reviewed study has reconstructed the ex-ante VfM model for a U.S. highway P3 project and recomputed the PSC–P3 net present cost comparison using outturn data. Garvin & Bosso [56] and Papajohn [57] characterize the U.S. P3 literature as limited in both theoretical development and post-evaluation. More recent studies remain partial in scope. Kweun [17] compared the methodology of seven U.S. highway VfM studies but did not examine post-completion outcomes. McCarthy [58] documented a high rate of cancellation and termination among U.S. surface transportation P3 projects but did not evaluate whether the original VfM conclusions remained valid. Gifford [29] examined several highway P3 renegotiations associated with revenue shortfalls and other performance deviations but did not reconstruct project-level VfM outcomes.
Several institutional factors help explain this gap. Key VfM inputs, including traffic forecasts, risk registers, discount rate assumptions, and shadow bid calculations, are often protected by commercial confidentiality. Unlike South Korea and Ontario, the United States has no comprehensive disclosure regime for project-level VfM analyses [59]. Although the U.S. Government Accountability Office [60] recommended a more rigorous upfront evaluation of P3 projects, as it did not establish a requirement for ex post reassessment. Likewise, the Bipartisan Infrastructure Law of 2021 requires Value for Money analysis for certain federally supported P3 projects but does not require that those analyses be reconciled with operational outcomes [10].
As a result, a growing portfolio of U.S. highway P3 projects has entered sustained operation without any systematic effort to determine whether the procurement decisions justified by ex-ante VfM analyses were borne out by observed project performance. This study addresses that gap by reconstructing the original VfM assessment using outturn project data and reevaluating the procurement decision in light of actual outcomes. A distinction is necessary between a complete ex-post assessment of realized whole-life VfM and a reassessment of procurement-stage VfM estimates using available post-completion information. A comprehensive assessment would require comparable information on capital expenditures, operating and maintenance costs, lifecycle renewal, contractual payments, financing outcomes, and realized risks over the full project lifecycle. However, long-term P3 concessions continue to incur operating and maintenance obligations after construction completion, and complete lifecycle outcomes may not be observable until much later. The present study therefore adopts an outturn-informed reassessment approach, incorporating available post-completion information into the implemented procurement alternative while retaining the unselected alternative at its original procurement-stage estimate.

4. Gaps in the Literature

Literature leads to three conclusions. First, while the conceptual foundations of VfM analysis are well established [1,19,20], the results remain highly sensitive to assumptions regarding risk valuation, cost estimates, traffic forecasts, and discount rates [18,33,35,39]. Second, evidence from completed projects suggests considerable uncertainty in construction costs, traffic forecasts, and risk valuation [22,35]. Third, despite these concerns, ex-post evaluation of VfM outcomes remains limited. Only one peer-reviewed study has conducted procurement-stage VfM estimates using post-completion project outcomes. Kim [12] and no comparable study has been identified for completed U.S. highway projects. This study addresses that gap by conducting procurement-stage and post-completion VfM estimates for completed U.S. highway projects using a consistent FHWA-based framework and evaluating whether procurement-stage VfM conclusions are sustained when post-completion project outcomes are incorporated.

5. Methodology

5.1. Data Collection and Sample Selection

This study adopts a quantitative paired comparison design in which each project serves as its own unit of analysis. The sample consists of completed U.S. highway projects for which a formal VfM analysis was conducted during procurement. Projects that did not undergo a formal procurement stage VfM assessment were excluded because, without a documented VfM analysis, no baseline VfM value exists against which post-completion outcomes can be compared. This screening process resulted in a final sample of seven projects. Although a larger number of U.S. highway projects have been delivered through P3, few satisfy the requirement for a procurement-stage VfM analysis and sufficient post-completion information to support the reconstruction of VfM outcomes. Data was collected from publicly available reports and records, as well as documents obtained through public records requests and direct requests to transportation agencies. Additional information was obtained, where necessary, from financial close documents, concession agreements, procurement analyses, audit reports, project completion reports, and transportation agency reports.
The FHWA P3 Value for Money Toolkit [7] was adopted as the analytical framework. For each project, a pre-procurement VfM value was obtained from or reconstructed using the procurement-stage VfM analysis, and a post-completion VfM value was calculated using the same FHWA model structure, with inputs updated to reflect post-completion project outcomes. The framework was applied consistently across both analyses to ensure that differences in VfM results reflect changes in project outcomes rather than methodological differences. To preserve consistency between the two analyses, the same model structure and discount rate were maintained throughout. Because VfM results are highly sensitive to discount rate assumptions, holding the discount rate constant ensures that observed differences are attributable to post-completion project performance rather than changes in time value of money assumptions. Inputs were updated only where documented post-completion information was available, including capital costs, schedule outcomes, risk realizations, operation and maintenance costs, and contractual payment streams. Where source documents did not disclose the required input, the analysis relied exclusively on documented values traceable to the original VfM analysis and supporting records. This approach minimizes researcher bias and ensures that differences between pre-procurement and post-completion VfM estimates reflect documented project outcomes rather than subjective adjustments. Because both VfM values were calculated for the same project using a common analytical framework, the design controls for project-specific characteristics that would otherwise confound cross-project comparisons were in place, including project scope, geographic context, traffic conditions, and contractual structure.

5.2. Research Aim

The primary aim of this study is to examine the magnitude, direction, and project-level patterns of differences between procurement-stage and post-completion VfM estimates for completed U.S. highway projects. The analysis also examines whether the original directional VfM conclusion holds when the implemented procurement alternative incorporates available post-completion information. Differences are assessed using absolute monetary changes and percentage changes relative to procurement-stage VfM estimates, where the procurement-stage VfM value is positive. The Wilcoxon signed-rank test is used as a supplementary statistical procedure to examine whether the paired differences are centered on zero. Failure to reject the null hypothesis is not interpreted as evidence of equivalence or consistency between procurement-stage and post-completion VfM estimates.

5.3. VfM Reconstruction Using FHWA p3 Value Toolkit

The FHWA P3-VALUE Toolkit [9] was adopted as the principal analytical framework for this study. The toolkit applies discounted cash flow analysis to compare two procurement alternatives on a risk-adjusted present value basis. The first is the Public Sector Comparator (PSC), which represents the whole-life cost of conventional public delivery financed at the public agency’s borrowing rate. The second is the P3 shadow bid, which represents delivery through a public-private partnership financed using a market-based weighted average cost of capital. Both alternatives incorporate capital expenditure, operating and maintenance costs, financing assumptions, contractual payments, and quantified project risks. Risk is reflected through the toolkit’s risk-allocation, risk-premium, lifecycle-performance, and revenue-uncertainty adjustment mechanisms. A positive VfM result indicates that the risk-adjusted present value of the P3 shadow bid is lower than that of the PSC, favoring private delivery.
The FHWA P3-VALUE Toolkit was applied twice for each project. The first analysis produced the procurement-stage VfM estimate using inputs obtained from the original VfM reports and supporting procurement documents. The second analysis produced the post-completion VfM estimate by incorporating available post-completion project information into the procurement alternative that was actually implemented. The model structure, discount rate, risk settings, price basis, and analytical conventions remained consistent across both analyses.
The reconstruction was designed to assess whether the original procurement-stage VfM conclusion was retained when the implemented procurement alternative was reassessed using available post-completion information. Accordingly, we retained the original estimate of the unselected procurement alternative as a fixed counterfactual benchmark. For projects P1–P6, which were delivered through P3 arrangements, the P3 comparator was updated while the PSC was held at its procurement-stage value. For P7, delivered using the conventional design-build approach, the authors updated the public delivery comparator while keeping the P3 comparator unchanged. This approach reflects that project outcomes can be observed for the implemented delivery alternative, whereas the unselected alternative’s equivalent outcomes cannot be directly observed.
The VfM calculations were expressed as follows:
  • Procurement-stage VfM = PSCpre − P3pre
  • Post-completion VfM for P1–P6 = PSCpre − P3post
  • Post-completion VfM for P7 = PSCpost − P3pre
Five principal VfM input categories were examined for the delivered procurement alternative: capital costs, construction schedules, operations and maintenance (O&M) costs, milestone or availability payments, and realized project risks. Table 5 reports the percentage changes in these inputs for each project and identifies inputs recorded as updated, retained at their procurement-stage values, or not applicable. Table 1 presents the procurement-stage and post-completion net present costs of the PSC and P3 comparators, thereby identifying which procurement alternative was updated in each project.
Where comparable post-completion information was unavailable, the original procurement-stage assumption was retained. Although retaining the unselected procurement alternative as a fixed benchmark facilitates comparison with the original procurement decision, it does not account for changes that might have occurred under that alternative. Similarly, retaining procurement-stage assumptions for unavailable post-completion inputs may constrain or otherwise influence the magnitude of observed VfM differences. The extent and direction of these effects cannot be independently determined from the available data. Consequently, the reconstructed estimates represent a partial update to the original procurement-stage VfM comparison rather than a complete evaluation of realized whole-life costs under both procurement alternatives. P7 was retained in the full sample because its procurement-stage VfM assessment favored conventional design-build rather than P3 delivery. Including this project allows the study to examine whether the negative VfM conclusion supporting conventional delivery was retained after incorporating available post-completion information. However, P7 differs from the other six projects in its implemented delivery approach and comparator structure. Therefore, a sensitivity analysis was conducted by excluding P7 and repeating the statistical comparison for the six P3 projects. Results are presented for both the full sample (n = 7) and the sensitivity sample (n = 6).
The resulting pre- and post-completion VfM values were compared in pairs for each project. The direction and magnitude of project-level changes were first examined descriptively. The Wilcoxon signed-rank test was then applied to the paired VfM observations to assess whether the post-completion results differed systematically from the procurement-stage results across the sample.

5.4. Statistical Analysis

Descriptive analysis was the primary approach for examining differences between procurement-stage and post-completion VfM estimates. The study design produces paired observations, with each project contributing one procurement-stage VfM estimate and one post-completion VfM estimate. The analysis therefore focuses on within-project changes in the magnitude and direction of VfM. The Wilcoxon signed-rank test was applied as a supplementary inferential procedure to assess whether the paired differences were systematically shifted from zero.
The Wilcoxon signed-rank test is appropriate for three reasons. First, it is specifically designed for paired data and serves as the nonparametric alternative to the paired t-test [61]. Second, the sample size is small (n = 7), which limits the reliability of parametric methods that rely on distributional assumptions. Third, normality of the paired differences cannot be assumed because VfM values are derived from multiple discounted cash flow components, including capital costs, lifecycle costs, contractual payments, and risk adjustments, each of which may exhibit substantial variability. The Wilcoxon signed-rank test does not require normally distributed differences and is therefore well-suited to the characteristics of the data [61].
A two-tailed test is used because the direction of any difference between procurement stage and post-completion VfM estimates cannot be assumed in advance. Procurement-stage estimates may overstate post-completion outcomes due to forecasting errors, optimism bias, or changes in project conditions, while post-completion project performance, risk transfer, and operational efficiencies may improve VfM outcomes relative to initial expectations. The test, therefore, evaluates whether a systematic difference exists in either direction. The significance level for all hypothesis tests was set at α = 0.05. Given the small sample size (n = 7), exact two-sided p-values were calculated for the Wilcoxon signed-rank test and reported alongside the asymptotic p-values. A sensitivity analysis was also performed excluding P7 because its implemented procurement approach and VfM comparator structure differed from those of the six P3 projects. The Wilcoxon signed-rank test was repeated for the remaining six paired observations to examine whether the statistical interpretation changed when P7 was excluded. The Wilcoxon test was treated as a supplementary inferential procedure rather than the primary basis for evaluating consistency between procurement-stage and post-completion VfM estimates. Failure to reject the null hypothesis was interpreted as insufficient evidence to detect a systematic difference, rather than evidence that the two sets of VfM estimates were equivalent. The statistical results were therefore interpreted in conjunction with descriptive statistics and project-level changes.
The following statistical hypotheses were formulated for the supplementary Wilcoxon signed-rank test:
Null Hypothesis (H₀): The distribution of paired differences between procurement-stage and post-completion VfM estimates is symmetric about zero.
Alternative Hypothesis (H₁): The distribution of paired differences between procurement-stage and post-completion VfM estimates is not centered on zero.
These hypotheses are used exclusively for the supplementary statistical analysis. The study’s primary interpretation focuses on the magnitude, direction, and project-level patterns of VfM changes.

5.5. Project Level Changes in VfM Inputs

The Wilcoxon signed-rank test identifies whether pre-procurement and post-completion VfM values differ across the sample, but it does not explain the project-level reasons for those differences. Each project’s VfM change was compared with changes in five toolkit inputs: capital cost, construction schedule, O&M cost, milestone or availability payments, and realized risk.
Percentage change was calculated as:
% Δ = post   completion   value − pre   procurement   value pre   procurement   value ∗ 100
Where no independently confirmed and comparable post-completion value was available, the procurement-stage value was retained in the post-completion model. Such cases are reported as not confirmed rather than as zero change. Because each percentage is based on a different input and VfM reflects discounted cash flows over the full project term, changes in individual inputs cannot be directly translated into their respective contributions to the overall VfM difference. Therefore, the analysis examines documented input changes associated with the observed VfM differences rather than attributing a specific portion of the VfM change to individual inputs. Quantitative attribution would require controlled, one-at-a-time input substitutions using the underlying VfM models.

6. Results

6.1 VfM Reconstruction Results

Seven completed U.S. highway projects met the study’s inclusion criteria of having a formal procurement stage, VfM analysis, and post-completion information to support VfM reconstruction. Of these, five projects were delivered under an availability-payment P3 structure, one was delivered under a toll-based P3, and one was delivered under a conventional design-build approach. For each project, the FHWA P3 VALUE Toolkit was applied twice: first, using procurement-stage inputs to estimate pre-procurement VfM, and subsequently, using post-completion project outcomes to estimate post-completion VfM. Post-completion analyses incorporated updated information on capital costs, schedule performance, risk realizations, operations and maintenance costs, and contractual payment streams, while maintaining the original model structure and discount rate.
All seven projects retained the same overall VfM conclusion at both stages of analysis. Six projects produced positive VfM estimates at both the procurement and post-completion stages, while P7 produced negative VfM estimates at both stages, consistent with its selection of the conventional design-build alternative. Post-completion VfM values should not be interpreted as indicators of project success or failure; rather, they represent the results of applying the same VfM framework using post-completion project outcomes. Three projects (P1, P5, and P6) produced higher post-completion VfM values than estimated at procurement, while four projects (P2, P3, P4, and P7) produced lower values. Table 1 presents the original reported VfM values alongside the reconstructed procurement-stage estimates, demonstrating that the FHWA model reproduced the VfM conclusions for all seven projects.
Table 1. Procurement and Post Completion VfM Estimates.
Table 1. Procurement and Post Completion VfM Estimates.
Project Delivery Report VfM, NPV ($M) Pre-Procurement VfM using tool, NPV ($M) Post-Completion VfM using tool, NPV ($M)
P1 P3 Availability 147 226 307
P2 P3 Availability 104 60 53
P3 P3 Toll 2 11 7
P4 P3 Availability 746 390 331
P5 P3 Availability 199 186 249
P6 P3 Availability 249 298 353
P7 DB Selected -15 -11 -14
As shown in Table 1, six projects were delivered through P3 arrangements, while P7 was delivered using the conventional design-build approach. In the post-completion reconstruction, only the procurement alternative actually implemented was updated using available project outcomes. For P1–P6, changes in VfM estimates therefore reflect changes in the P3 comparator relative to the original PSC. For P7, changes reflect updates to the public delivery comparator relative to the original P3 estimate. The unselected procurement alternative was maintained at its procurement-stage value to provide a consistent benchmark for examining whether the original directional VfM conclusion was retained.

6.2. Wilcoxon Signed Rank Test

Table 2 summarizes the paired differences under both comparisons. Under the tool pre vs. post comparison, the mean difference was +$18.0M, the median was −$3.0M, and the standard deviation was $49.7M. The 95% confidence interval for the mean spanned zero (−$28.0M to +$64.0M). Three projects produced positive differences and four produced negative differences. For the secondary comparison (report pre vs. tool post), the mean difference was −$20.9M and the median was +$4.8M, with a standard deviation of $187.4M.
The Wilcoxon signed rank test evaluates whether the distribution of paired differences is symmetric around zero. For each pair, the test ranks the absolute magnitudes of the differences and assigns signs based on direction; it then compares the sum of positive ranks (W⁺) against the sum of negative ranks (W⁻). The test statistic T is the smaller of W⁺ and W⁻ and the corresponding Z statistic and p value indicate whether the observed imbalance between positive and negative ranks exceeds what would be expected by chance. The Wilcoxon signed-rank test does not require normally distributed differences, although its conventional interpretation as a test of location assumes a symmetric distribution of paired differences. It was used as a supplementary analysis alongside the descriptive project-level comparisons. Two paired comparisons were examined: (1) reconstructed procurement-stage VfM versus reconstructed post-completion VfM, which represents the principal comparison, and (2) originally reported procurement-stage VfM versus reconstructed post-completion VfM, which provides a secondary comparison.
Results are presented in Table 3. For the tool-based procurement-stage versus post-completion comparison, the positive and negative rank sums were W⁺ = 17.0 and W⁻ = 11.0, respectively, yielding a Wilcoxon test statistic of T = 11.0. The asymptotic test produced Z = −0.507 and a two-sided p-value of 0.612, while the exact two-sided p-value was 0.6875. Neither result provided sufficient statistical evidence to reject the null hypothesis at the 5% significance level. However, failing to reject the null hypothesis indicates only that the available sample did not detect a systematic difference; it does not establish that procurement-stage and post-completion VfM estimates are equivalent or that procurement-stage estimates are inherently stable.
The Wilcoxon signed-rank test did not detect a statistically significant systematic difference between procurement-stage and post-completion VfM estimates. However, this result should be interpreted cautiously because the small sample size (n = 7) substantially limits statistical power. For the tool-based comparison, the standardized paired mean difference was dz = 0.36, with estimated statistical power of approximately 0.13 at α = 0.05. Consequently, the non-significant result should not be interpreted as demonstrating equivalence or confirming the reliability of procurement-stage VfM estimates. Rather, the statistical analysis provides supplementary evidence alongside the descriptive results, which show that VfM increased in three projects and decreased in four. Although all seven projects retained their original directional VfM conclusions under the available post-completion information, the observed changes and limited statistical power prevent broader conclusions regarding the general stability of procurement-stage VfM assessments. To examine P7’s influence on the statistical results, we repeated the Wilcoxon signed-rank test using only the six P3 projects. Among these projects, VfM increased for three (P1, P5, and P6) and decreased for three (P2, P3, and P4). The sensitivity analysis yielded positive and negative rank sums of W⁺ = 14.0 and W⁻ = 7.0, respectively, with T = 7.0 and an exact two-sided p-value of 0.5625. The result did not indicate a statistically significant difference between procurement-stage and post-completion VfM estimates at α = 0.05. All six projects also retained positive directional VfM conclusions. Thus, the descriptive finding of directional retention persisted when P7 was excluded. However, this result should not be interpreted as evidence of equivalence or general stability, particularly given the small sample size.
To further examine the magnitude and direction of project-level VfM changes, Table 4 presents the reconstructed procurement-stage and post-completion VfM estimates, together with their absolute and percentage differences. The results show that VfM increased for three projects (P1, P5, and P6) and decreased for four projects (P2, P3, P4, and P7). Among the six projects with positive procurement-stage VfM estimates, percentage changes ranged from −36.4% to +35.8%. P1 showed the largest positive change (+$81 million), followed by P5 (+$63 million) and P6 (+$55 million). P4 exhibited the largest negative change (−$59 million). Although all seven projects retained their original directional VfM conclusions, the magnitude and direction of the changes varied across projects. These findings highlight the importance of examining project-level differences rather than relying solely on statistical significance.

6.3. Project Level Results

Five principal VfM input categories were examined for each project: capital costs, construction schedules, operations and maintenance (O&M) costs, milestone or availability payments, and realized project risks. Table 5 reports the percentage changes in these input categories for the procurement alternative implemented in each project. For P1-P6, the reported changes relate to the P3 delivery alternative, while for P7, they relate to the conventional design-build alternative. The unselected procurement alternative was retained at its original procurement-stage estimate. Inputs are classified as updated (U), retained at their procurement-stage values (R), or not applicable (N/A). The reported percentages therefore represent changes within the implemented procurement alternative rather than differences between the PSC and P3 comparators. The classification reflects the reported reconstruction inputs, while the availability of independently verified post-completion supporting records varies across projects.
Table 5. Procurement-Stage and Post-Completion VfM Input Results.
Table 5. Procurement-Stage and Post-Completion VfM Input Results.
Project Δ VfM Capital cost change Schedule change O&M result Payment change Risk result
P1 +81 -7.4%
(U)
-22.1%
(U)
+12.1%
(U)
NA
(R)
+15%
(U)
P2 -7 +5.0%
(U)
-28.5%
(U)
NA
(R)
NA
(R)
-5%
(U)
P3 -4 +2.6%
(U)
-6.0%
(U)
-15.5%
(U)
NA
(R)
NA
(R)
P4 -59 +12.2%
(U)
+19.6%
(U)
NA
(R)
NA
(R)
+22%
(U)
P5 +63 -15.0%
(U)
-29.5%
(U)
-8.0%
(U)
-29%
(U)
-73%
(U)
P6 +55 -13.7%
(U)
-28.5%
(U)
+16.1%
(U)
NA
(R)
NA
(R)
P7 -3 +22.1%
(U)
+100%
(U)
-19.2%
(U)
NA
(R)
NA
(R)
Across P1-P6, capital cost inputs decreased in three projects and increased in three, while construction duration decreased in five projects and increased in one. O&M inputs were updated for five projects (P1, P3, P5, P6, and P7), while the original procurement-stage assumptions were retained for P2 and P4. A payment input change was reported for P5, whereas comparable payment changes were unavailable or not applicable for the remaining projects. Quantified risk-input changes were reported for P1, P2, P4, and P5, while risk events or exposures were documented for some of the remaining projects without comparable percentage changes. All reported percentages refer to procurement-to-post-completion changes in the relevant inputs of the selected delivery alternative rather than differences between competing delivery alternatives. Because several inputs changed simultaneously and their effects are combined within the discounted cash flow model, the individual contribution of each input to the overall VfM change could not be isolated. The findings are therefore interpreted as descriptive project-level associations. P7 is considered separately because its delivery and comparator structures differ from those of the six P3 projects.

Project Level Results

P1: VfM increased from 226 to 307. For the selected P3 delivery alternative, the post-completion capital cost input decreased by approximately 7.4%, and the construction duration decreased by approximately 22.1% relative to their procurement-stage estimates. The updated O&M input was approximately 12.1% higher than the initial procurement-stage O&M estimate for the same delivery alternative. A settlement related to third-party permitting delays and disputed extra work was approximately 15% above the procurement-stage risk reserve. The individual contribution of these input changes to the overall VfM difference could not be isolated. A comparable post-completion milestone payment input was not available, so the procurement-stage assumption was retained. Revenue and demand were not applicable because the project was non-tolled. A change in private equity ownership was documented after completion.
P2: VfM decreased from 60 to 53. For the selected P3 delivery alternative, the updated capital cost input increased by approximately 5.0%, while the construction duration decreased by approximately 28.5% relative to procurement-stage estimates. The reconstruction recorded a 5% decrease in the risk input compared with its initial procurement-stage value. Available closeout information also indicated limited utilization of the original contingency allowance. Comparable post-completion O&M and milestone or availability payment inputs were unavailable; therefore, their procurement-stage assumptions were retained. A change in private equity ownership was documented during construction.
P3: VfM decreased from 11 to 7. For the selected toll-based P3 delivery alternative, the updated capital cost input increased by approximately 2.6%, while the construction duration decreased by approximately 6.0% relative to the procurement-stage estimates. The capital cost baseline was obtained from an independent supporting source because the original procurement report did not disclose a directly comparable value. The updated O&M input decreased by approximately 15.5% compared with the initial procurement-stage O&M estimate for the same P3 alternative. A construction-related settlement was documented, but no directly comparable procurement-stage risk allowance was available to calculate a percentage change; therefore, the original risk input was retained in the reconstruction. Actual revenue information was available, but no directly comparable procurement-stage forecast was disclosed, preventing calculation of a revenue change. An availability-payment comparison was not applicable because the project was toll-based. A change in private equity ownership occurred after completion.
P4: VfM decreased from 390 to 331. For the selected P3 delivery alternative, the updated capital cost input increased by approximately 12.2%, and construction duration increased by approximately 19.6% relative to procurement-stage estimates. The reported risk input increased by approximately 22% compared with the original procurement-stage allowance. Comparable post-completion O&M information was unavailable, so the procurement-stage O&M input was retained. Although milestone payment figures appeared in the post-completion documentation, they could not be independently confirmed as comparable actual payments; therefore, the original payment assumption was retained. Revenue and demand were not applicable to the P3 input comparison because toll revenue remained with the public sector. A change in private equity ownership was completed several years after substantial completion.
P5: VfM increased from 186 to 249. For the selected P3 delivery alternative, the updated capital cost input decreased by approximately 15.0%, and construction duration decreased by approximately 29.5% relative to their procurement-stage estimates. The updated O&M input was approximately 8.0% lower than the initial procurement-stage O&M estimate for the same alternative. The payment input decreased by approximately 29% relative to the procurement-stage plan. Reported risk utilization was approximately 27% of the original planned allowance, corresponding to a 73% reduction relative to that allowance. The schedule baseline was an assumption carried over from another project rather than an independently confirmed contractual duration. A related financing facility increased by approximately 12% after financial close to fund additional project costs; this is presented as contextual information and is not included in the capital cost change reported in Table 5. Revenue and demand were not applicable because toll revenue remained with the public sector. The individual contributions of capital cost, schedule, O&M, payment, and risk changes to the overall VfM difference were not calculated separately.
P6: VfM increased from 298 to 353. For the selected P3 delivery alternative, the updated capital cost input decreased by approximately 13.7%, and construction duration decreased by approximately 28.5% relative to procurement-stage estimates. The updated O&M input increased by approximately 16.1% compared with the initial procurement-stage O&M estimate for the same alternative. A mechanical or commissioning issue was documented during startup, but it fell outside the risk category covered by the procurement-stage allowance, and no comparable percentage change could be calculated. Accordingly, the procurement-stage risk input was retained. Comparable post-completion milestone payment information was not available, so the original payment assumption was also retained. Revenue and demand were not applicable because the project was non-tolled. No change in financing or private equity ownership was identified.
P7: VfM decreased from −$11 million to −$14 million. Unlike P1–P6, P7 was delivered through a conventional design-build arrangement with TIFIA financing rather than a P3 arrangement. Its VfM measure reflects the estimated funding disadvantage of the unselected DBFOM alternative relative to the selected public delivery structure and is therefore interpreted separately from the six P3 projects. For the selected conventional delivery alternative, the updated total project cost input increased by approximately 22.1% relative to the comparable procurement-stage total-uses estimate. A separate construction-only final outturn was not disclosed. The estimated delivery period increased by approximately 100% based on available audited information indicating that tolling commenced more than two years later than initially anticipated; this represents an approximate minimum measure. The updated O&M input decreased by approximately 19.2% relative to the initial procurement-stage assumption for the selected conventional delivery alternative. Revenue-related risk also materialized, as traffic growth and toll collections were below forecast and an O&M backup loan was approved and drawn. However, no directly comparable procurement-stage risk allowance was available to calculate a percentage change, so the original risk input was retained. A milestone or availability-payment comparison was not applicable because the project used public toll-revenue debt and other public contributions rather than availability payments. Because P7 differs from the other projects in its implemented delivery and comparator structures, its findings are considered separately.

7. Discussion & Conclusions

This study examines the magnitude, direction, and project-level patterns of differences between procurement-stage and post-completion VfM estimates for seven completed U.S. highway projects with formal procurement-stage VfM analyses. For each project, the implemented procurement alternative was reassessed using available post-completion information, while the unselected alternative was retained at its original procurement-stage estimate. The analysis employed a consistent FHWA-based analytical framework, maintaining the same model structure and discount rate across the two assessments. Descriptive statistics were used to examine project-level VfM changes, while the Wilcoxon signed-rank test was applied as a supplementary statistical procedure.
The results showed that VfM estimates increased for three projects and decreased for four, with differences varying in both magnitude and direction. All seven projects retained their original directional VfM conclusions when available post-completion information was incorporated. The supplementary Wilcoxon signed-rank test did not detect a statistically significant systematic difference between procurement-stage and post-completion VfM estimates (exact two-sided p = 0.6875). A sensitivity analysis excluding P7 similarly did not identify a statistically significant difference (exact two-sided p = 0.5625). However, the small sample size and limited statistical power mean that these non-significant results do not establish equivalence or demonstrate the general stability of procurement-stage VfM estimates. The findings are therefore interpreted primarily through the observed project-level changes rather than the statistical test alone.
The findings of this study both contrast with and extend the limited international evidence on ex post VfM assessment. Kim [12] examined three Korean highway P3 projects and found that only one retained a positive VfM outcome under post-completion conditions, attributing the two ex post failures primarily to declining discount rates and more favorable Treasury bond financing conditions than originally assumed. By contrast, all seven U.S. highway projects in this study retained their original VfM outcome when recalculated using post-completion data. This difference may reflect several factors: the discount rate was held constant in this study to isolate realized project outcomes from broader financial-market changes; the U.S. sample consisted predominantly of availability-payment projects, which may be less exposed to VfM erosion from demand and revenue risk than toll concessions; and project, contractual, and institutional conditions differ across the two contexts. The UK National Audit Office [46] identified a related evidence gap, concluding that insufficient post-completion evaluation had been conducted to determine whether private finance delivered better or worse value than conventional procurement. This study helps address that gap in the U.S. highway context by reconstructing the PSC-P3 comparison using documented post-completion data across seven completed projects. The retention of the original directional VfM conclusions in all seven projects does not establish that P3 procurement generally delivers superior value. Rather, it indicates that the original directional conclusions were retained within the examined sample when available post-completion information was incorporated into the implemented delivery alternative against the original procurement-stage counterfactual.
The project level results indicate that post-completion VfM values changed in both directions, though for project-specific rather than shared reasons. Three projects (P1, P5, and P6) recorded higher post-completion VfM estimates than at procurement. All three also showed lower capital costs and shorter construction periods. P5 recorded payments below plan and limited use of its planned risk allowance, while P1 experienced a settlement exceeding its original risk reserve. P6 also recorded a startup-related risk event, although it could not be compared directly with the procurement-stage allowance. P2, P3, and P4 recorded lower post-completion VfM. P2 and P3 experienced modest increases in capital costs alongside shorter schedules. P4 recorded both a capital cost increase and a longer construction period, while realized risk exceeded the original allowance. P7 likewise recorded a lower VfM result, along with a higher total project cost, a substantially longer delivery period, and a materialized revenue-support risk; however, it is treated separately because its delivery and comparator structure differed from those of the other projects. Across the six P3 projects, the observed VfM differences were accompanied by varying changes in capital costs, construction schedules, O&M inputs, payments, and reported risk outcomes. These changes are examined as project-level associations rather than as independently established causes of the overall VfM differences. Projects with higher VfM generally recorded lower costs and shorter schedules, while the projects with lower VfM included capital-cost increases, schedule delays, or higher realized risk. No single input, however, accounted for every project’s result.
The project-level input analysis provides additional context for these findings. Capital cost and construction schedule changes were reported across the seven projects, while O&M input changes were reported for five projects (P1, P3, P5, P6, and P7). Procurement-stage O&M assumptions were retained for P2 and P4 because comparable post-completion information was unavailable. A payment input change was reported for only one project (P5), while comparable payment changes were unavailable or not applicable for the remaining projects. However, the availability and comparability of supporting post-completion O&M information varied, and the reported input changes do not necessarily represent complete, independently verified lifecycle O&M expenditures. Therefore, although the reconstruction incorporated available changes in key project inputs, the limited lifecycle information prevents the results from being interpreted as comprehensive ex-post assessments of realized whole-life VfM.
An important observation from the analysis is that some divergence between the procurement stage and post-completion VfM estimates is unavoidable. VfM assessments are completed before procurement has fully concluded, whereas the delivered project reflects subsequent negotiations, financial close activities, contractual refinements, bid outcomes, and risk reallocations. Consequently, procurement stage models cannot fully anticipate all the conditions under which a project will be delivered and operated. Some portion of the observed deviation, therefore, reflects the evolution of the project after the VfM assessment rather than forecasting error alone. This interpretation helps explain why some projects achieve higher post-completion VfM values while others achieve lower ones.
There are several limitations to this study. First, the small sample size (n = 7) constrains statistical power, and the failure to reject the null hypothesis should not be interpreted as evidence of equivalence or the absence of systematic differences. The sample was limited to completed U.S. highway projects with formal procurement-stage VfM documentation and sufficient post-completion information to support reconstruction; therefore, the findings may not be generalizable to all U.S. highway P3 projects. Second, although available post-completion information was incorporated into the implemented procurement alternative, procurement-stage values were retained where comparable information was unavailable. O&M input changes were reported for five projects, while procurement-stage O&M values were retained for P2 and P4. However, complete and independently verified lifecycle O&M expenditure histories were not available for all projects. Similarly, a payment input change was reported for only one project, and comprehensive post-completion payment information was unavailable or insufficiently disaggregated for several projects. Retaining procurement-stage assumptions may constrain or otherwise influence the observed VfM differences. Third, the unselected procurement alternative was held at its original procurement-stage estimate as a fixed counterfactual benchmark. While this approach allows changes in the implemented alternative to be evaluated against the original procurement assumptions, it does not account for potential changes that might have occurred under the unselected alternative. Consequently, the reconstructed VfM estimates represent partially updated reassessments rather than comprehensive measurements of realized whole-life VfM. Finally, the analysis maintained a constant discount rate between procurement-stage and post-completion calculations to preserve methodological consistency. Although this approach isolates the effects of the documented input changes from changes in discounting assumptions, it does not capture broader financial-market changes that may have occurred between procurement and project completion.
This study provides a multi-project, outturn-informed reassessment of procurement-stage VfM estimates for seven completed U.S. highway projects using a standardized analytical framework. The results demonstrate that project-level VfM differences occurred in both positive and negative directions, with three projects showing increases and four showing decreases. All seven projects retained their original directional VfM conclusions when available post-completion information was incorporated into the implemented procurement alternative. However, retention of the original directional VfM conclusions does not establish the accuracy of the procurement-stage estimates. The limited sample size, incomplete lifecycle information, and fixed-counterfactual reconstruction approach also prevent broader conclusions regarding the general stability or reliability of procurement-stage VfM assessments. The findings demonstrate the potential usefulness of post-completion VfM reassessment as a complementary tool for evaluating original procurement decisions. Future research should expand the sample as additional projects reach completion, incorporate more comprehensive and disaggregated O&M and contractual payment information, examine sensitivity to changing financing conditions, and investigate the institutional and disclosure practices influencing VfM analysis in U.S. transportation infrastructure.

References

  1. D. Grimsey and M. K. Lewis, “Are Public Private Partnerships value for money?: Evaluating alternative approaches and comparing academic and practitioner views,” Accounting Forum, vol. 29, no. 4, pp. 345–378, 2005. [CrossRef]
  2. Congressional Budget Office, “Public-Private Partnerships for Transportation and Water Infrastructure,” Transportation Research Board, Jan. 2020. [CrossRef]
  3. D. Morallos, A. Amekudzi, C. Ross, and M. Meyer, “Value for Money Analysis in U.S. Transportation Public–Private Partnerships,” Transp. Res. Rec., no. 2115, pp. 27–36, 2009. [CrossRef]
  4. D. Morallos and A. Amekudzi, “The State of the Practice of Value for Money Analysis in Comparing Public Private Partnerships to Traditional Procurements,”, vol. 13, no. 2, pp. 114–125, Oct. 2008. [CrossRef]
  5. Federal Highway Administration, “Value for money state-of-the-practice,” U.S. Department of Transportation, 2011.
  6. Federal Highway Administration, “Value for money assessment for public-private partnerships: A primer,” U.S. Department of Transportation, 2012.
  7. Federal Highway Administration, “Guidebook for value for money assessment,” U.S. Department of Transportation, 2013.
  8. Federal Highway Administration, “P3-VALUE 2.0 through 2.3 user guide and technical documentation,” U.S. Department of Transportation, Build America Bureau, 2016.
  9. W. J. Mallett, “Public-Private Partnerships (P3s) in Transportation,” 2021. Accessed: Mar. 06, 2025. [Online]. Available: https://crsreports.congress.gov.
  10. Office of the Auditor General of Ontario, “Infrastructure Ontario - alternative financing and procurement,” In 2014 Annual Report, Chapter 3, Section 3.05. Queen’s Printer for Ontario, 2014. Accessed: Jul. 03, 2026. [Online]. Available: https://www.auditor.on.ca/en/content/annualreports/arreports/en14/305en14.pdf.
  11. J. Kim, B. Kim, J. Shin, and K. Lee, “Do public private partnership projects deliver value for money? An ex-post value for money test on three road projects in Korea,” International Journal of Urban Sciences, vol. 22, no. 4, pp. 567–585, 2018. [CrossRef]
  12. P. Victoria, “Public sector comparator: Technical note,” Department of Treasury and Finance, Victoria, Australia, 2001.
  13. World Bank Institute, “Value-for-Money Analysis-Practices and Challenges: How Governments Choose When to Use PPP to Deliver Public Infrastructure and Services,” 2013.
  14. W. B. G. / P.-P. I. A. F. (PPIAF), “Value-for-money analysis — practices and challenges: How governments choose when to use PPP to deliver public infrastructure and services,” World Bank, 2013.
  15. P. Burger and I. Hawkesworth, “How to attain value for money: comparing PPP and traditional infrastructure public procurement,” OECD Journal on budgeting, vol. 11, no. 1, pp. 91–146, 2011.
  16. J. Y. Kweun, P. K. Wheeler, and J. L. Gifford, “Evaluating highway public-private partnerships: Evidence from U.S. value for money studies,” Transp. Policy (Oxf)., vol. 62, pp. 12–20, 2018. [CrossRef]
  17. A. Boardman and M. Hellowell, “A comparative analysis and evaluation of specialist PPP units’ methodologies for conducting value for money appraisals,” Journal of Comparative Policy Analysis, vol. 19, no. 3, pp. 191–206, 2017. [CrossRef]
  18. O. Hart, “Incomplete contracts and public ownership: Remarks, and an application to public-private partnerships,” Economic Journal, vol. 113, no. 486, pp. C69–C76, 2003. [CrossRef]
  19. E. Iossa and D. Martimort, “The simple microeconomics of public-private partnerships,” J. Public Econ. Theory, vol. 17, no. 1, pp. 4–48, 2015. [CrossRef]
  20. B. Flyvbjerg, M. K. S. Holm, and S. L. Buhl, “Underestimating costs in public works projects: Error or lie?,” Journal of the American Planning Association, vol. 68, no. 3, pp. 279–295, 2002. [CrossRef]
  21. J. Odeck, “Cost overruns in road construction — what are their sizes and determinants?,” Transp. Policy (Oxf)., vol. 11, no. 1, pp. 43–53, 2004. [CrossRef]
  22. C. C. Cantarelli, B. Flyvbjerg, B. van Wee, and E. J. E. Molin, “Lock-in and its influence on the project performance of large-scale transportation infrastructure projects,” Environment and Planning B, vol. 37, no. 5, pp. 792–807, 2010. [CrossRef]
  23. P. Edwards, J. Shaoul, A. Stafford, and L. Arblaster, “Evaluating the operations of PFI in roads and hospitals,” ACCA Research Report 84. ACCA, 2004. Accessed: Jul. 03, 2026. [Online]. Available: https://image.guardian.co.uk/sys-files/Society/documents/2004/11/24/PFI.pdf.
  24. F. Blanc-Brude, H. Goldsmith, and T. Välilä, “A comparison of construction contract prices for traditionally procured roads and public-private partnerships,” Rev. Ind. Organ., vol. 35, no. 1, pp. 19–40, 2009. [CrossRef]
  25. B. Shrestha and P. P. Shrestha, “Project Performance Comparison of Public–Private Partnership (P3) Highway Projects against Design Build (DB) and Design Bid Build (DBB) Highway Projects,” Buildings 2024, Vol. 14, Page 2622, vol. 14, no. 9, p. 2622, Aug. 2024. [CrossRef]
  26. R. Bain, “Error and optimism bias in toll road traffic forecasts,” Transportation (Amst)., vol. 36, no. 5, pp. 469–482, 2009. [CrossRef]
  27. J. L. Gifford, L. Bolaños, N. Daito, and C. B. Casady, “What triggers public-private partnership renegotiations in the United States?,” Public Management Review, vol. 26, no. 6, pp. 1583–1609, 2023. [CrossRef]
  28. P. Victoria, “Public sector comparator: Technical note,” Department of Treasury and Finance, Victoria, Australia, 2000. Accessed: Jul. 03, 2026. [Online]. Available: https://mf.gov.cz/assets/attachments/PPP-Australia-Partnerships-Victoria-Practitioners-Guide.pdf.
  29. Federal Highway Administration, “Value for money assessment for public-private partnerships : a primer.,” Jan. 2015. [CrossRef]
  30. E. R. Yescombe and E. Farquharson, Public-Private Partnerships for Infrastructure: Principles of Policy and Finance. Elsevier, 2018. [CrossRef]
  31. D. Heald, “Value for money tests and accounting treatment in PFI schemes,” Accounting, Auditing & Accountability Journal, vol. 16, no. 3, pp. 342–371, Aug. 2003. [CrossRef]
  32. J. Quiggin, “Risk, PPPs and the public sector comparator,” Australian Accounting Review, vol. 14, no. 33, pp. 51–61, Jul. 2004. [CrossRef]
  33. M. Siemiatycki and N. Farooqi, “Value for money and risk in public-private partnerships: Evaluating the evidence,” Journal of the American Planning Association, vol. 78, no. 3, pp. 286–299, 2012. [CrossRef]
  34. J. Froud, “The Private Finance Initiative: risk, uncertainty and the state,” Accounting, Organizations and Society, vol. 28, no. 6, pp. 567–589, Aug. 2003. [CrossRef]
  35. P. Grout, “The economics of the private finance initiative,” Oxf. Rev. Econ. Policy, vol. 13, no. 4, pp. 53–66, 1997. [CrossRef]
  36. M. Spackman, “Time discounting and of the cost of capital in government,” Fisc. Stud., vol. 25, no. 4, pp. 467–518, Dec. 2004. [CrossRef]
  37. S. Zwalf, G. Hodge, and Q. Alam, “Choose your own adventure: Finding a suitable discount rate for evaluating value for money in public-private partnership proposals,” Australian Journal of Public Administration, vol. 76, no. 3, pp. 301–315, 2017. [CrossRef]
  38. E. Reeves and J. Ryan, “Piloting public-private partnerships: Expensive lessons from Ireland’s schools’ sector,” Public Money and Management, vol. 27, no. 5, pp. 331–338, Nov. 2007. [CrossRef]
  39. P. Brinckerhoff, “International Public-Private Partnership Synthesis Report,” Apr. 2013. [CrossRef]
  40. G. N. Sukasuka, I. Musonda, M. S. Ramabodu, and S. L. Zulu, “Social dimensions in ex-post evaluation of public private partnership infrastructure projects,” Sustainability, vol. 14, no. 23, p. 15808, 2022. [CrossRef]
  41. A. E. Boardman, W. L. Mallery, and A. R. Vining, “Learning from ex ante/ex post cost-benefit analysis comparisons: The Coquihalla Highway example,” Socioecon. Plann. Sci., vol. 28, no. 2, pp. 69–84, 1994. [CrossRef]
  42. A. D. Chasey, W. E. Maddex, and A. Bansal, “Comparison of public-private partnerships and traditional procurement methods in north American highway construction,” Transp. Res. Rec., vol. 2268, pp. 26–32, 2012. [CrossRef]
  43. National Audit Office, “PFI: Construction performance,” HC 371. The Stationery Office, 2003.
  44. National Audit Office, “Lessons from PFI and other projects,” HC 920. The Stationery Office, 2011.
  45. National Audit Office, “PFI and PF2,” HC 718. The Stationery Office, 2018.
  46. EIB, “EPEC Guide to Public-Private Partnerships,” 2021. [CrossRef]
  47. X. Shu, S. Smyth, and J. Haslam, “Post-decision project evaluation of UK public–private partnerships: insights from planning practice,” Public Money & Management, vol. 41, no. 6, pp. 477–486, Aug. 2021. [CrossRef]
  48. National Audit Office, “The performance and management of hospital PFI contracts,” HC 68. The Stationery Office, 2010.
  49. J. Shaoul, A. Stafford, and P. Stapleton, “Highway robbery? A financial analysis of design, build, finance and operate (DBFO) in UK roads,” Transp. Rev., vol. 26, no. 3, pp. 257–274, 2006. [CrossRef]
  50. S. Toms, M. Beck, and D. Asenova, “Accounting, regulation and profitability: The case of PFI hospital refinancing,” Critical Perspectives on Accounting, vol. 22, no. 7, pp. 668–681, 2011. [CrossRef]
  51. B. Acerete, M. Gasca, and A. Stafford, “Two decades of DBFO roads in the UK and Spain,” Annals of Public and Cooperative Economics, vol. 90, no. 2, pp. 269–289, 2019. [CrossRef]
  52. H. J. Liu, P. E. D. Love, J. Smith, M. Regan, and E. Palaneeswaran, “Review of performance measurement: Implications for public-private partnerships,” Built Environment Project and Asset Management, vol. 5, no. 1, pp. 35–51, 2015. [CrossRef]
  53. G. A. Hodge and C. Greve, “PPPs: THE PASSAGE OF TIME PERMITS A SOBER REFLECTION,” Economic Affairs, vol. 29, no. 1, pp. 33–39, Mar. 2009. [CrossRef]
  54. M. J. Garvin and D. Bosso, “Assessing the Effectiveness of Infrastructure Public—Private Partnership Programs and Projects,” Public Works Management & Policy, vol. 13, no. 2, pp. 162–178, 2008. [CrossRef]
  55. D. Papajohn, Q. Cui, and M. E. Bayraktar, “Public-private partnerships in U.S. transportation: Research overview and a path forward,” Journal of Management in Engineering, vol. 27, no. 3, pp. 126–135, 2011. [CrossRef]
  56. L. N. McCarthy, L. Bolaños, J. Y. Kweun, and J. L. Gifford, “Understanding project cancellation risks in U.S. P3 surface transportation infrastructure,” Transp. Policy (Oxf)., vol. 98, pp. 197–207, 2020. [CrossRef]
  57. C. B. Casady and R. R. Geddes, “Private participation in US infrastructure: The role of PPP units,” American Enterprise Institute, 2016. Accessed: Jul. 03, 2026. [Online]. Available: https://www.aei.org/research-products/report/private-participation-in-us-infrastructure-the-role-of-ppp-units/.
  58. U.S. GAO, “Highway public-private partnerships: More rigorous up-front analysis could better secure potential benefits and protect the public interest,” GAO-08-44. GAO, 2008. Accessed: Jul. 03, 2026. [Online]. Available: https://www.gao.gov/products/gao-08-44.
  59. F. Wilcoxon, “Individual Comparisons by Ranking Methods,” Biometrics Bulletin, vol. 1, no. 6, p. 80, Dec. 1945. [CrossRef]
Table 2. Descriptive Statistics between Procurement and Post Completion VfM Estimates.
Table 2. Descriptive Statistics between Procurement and Post Completion VfM Estimates.
Statistic Tool Pre vs. Post Report Pre vs. Post
Mean difference $18.0M -$20.9M
Median difference -$3.0M $4.8M
Standard deviation $49.7M $187.4M
95% CI for mean (lower) -$28.0M -$187.4M
95% CI for mean (upper) $64.0M -$192.4M
Minimum -$59M -$415M
Maximum $81M $160M
Table 3. Wilcoxon Signed Rank Test Results.
Table 3. Wilcoxon Signed Rank Test Results.
Statistic Tool Pre vs. Post
(n=7)
Tool Pre vs. Post, excluding P7
(n=6)
Report Tool Pre vs. Post
Positive rank sum (W⁺) 17.0 14.0 17.0
Negative rank sum (W⁻) 11.0 7.0 11.0
Test statistic (T = min W) 11.0 7.0 11.0
Z -0.507 -0.734 -0.507
Asymptotic p-value (2-tailed) 0.612 0.463 0.612
Exact p-value (2-tailed) 0.6875 0.5625 0.6875
Table 4. Magnitude and Direction of Changes in VfM Estimates.
Table 4. Magnitude and Direction of Changes in VfM Estimates.
Project Pre VfM ($M) Post VfM ($M) Difference ($M) Change (%)
P1 226 307 +81 +35.8%
P2 60 53 -7 -11.7%
P3 11 7 -4 -36.4%
P4 390 331 -59 -15.1%
P5 186 249 +63 +33.9%
P6 298 353 +55 +18.5%
P7 -11 -14 -3 N/A
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.