Figure 1.
Overview of a pico-grid in a building at SIT Punggol campus.
Figure 1.
Overview of a pico-grid in a building at SIT Punggol campus.
Figure 2.
SS530 lighting power density guideline.
Figure 2.
SS530 lighting power density guideline.
Figure 3.
Proposed topology used in BESS.
Figure 3.
Proposed topology used in BESS.
Figure 4.
Proposed control algorithm used to control BESS.
Figure 4.
Proposed control algorithm used to control BESS.
Figure 5.
Proposed topology used in single-phase inverter.
Figure 5.
Proposed topology used in single-phase inverter.
Figure 6.
Proposed topology used in single-phase inverter.
Figure 6.
Proposed topology used in single-phase inverter.
Figure 7.
Overview of nano-grid system a building at SIT Punggol campus.
Figure 7.
Overview of nano-grid system a building at SIT Punggol campus.
Figure 8.
Proposed topology used in solar PV boost converter.
Figure 8.
Proposed topology used in solar PV boost converter.
Figure 9.
Proposed control algorithm used to control boost converter.
Figure 9.
Proposed control algorithm used to control boost converter.
Figure 10.
Proposed P&O algorithm for MPPT operation.
Figure 10.
Proposed P&O algorithm for MPPT operation.
Figure 11.
Proposed topology used in three-phase inverter.
Figure 11.
Proposed topology used in three-phase inverter.
Figure 12.
Proposed control algorithm used to control three-phase inverter.
Figure 12.
Proposed control algorithm used to control three-phase inverter.
Figure 13.
Simulation model of BESS integration with single-phase inverter.
Figure 13.
Simulation model of BESS integration with single-phase inverter.
Figure 14.
Load demand estimation of DC and AC loads for pico-grid system.
Figure 14.
Load demand estimation of DC and AC loads for pico-grid system.
Figure 15.
The SOC level of the BESS during discharging in pico-grid system.
Figure 15.
The SOC level of the BESS during discharging in pico-grid system.
Figure 16.
The battery voltage of the BESS during discharging in pico-grid system.
Figure 16.
The battery voltage of the BESS during discharging in pico-grid system.
Figure 17.
Battery current of BESS during discharging in pico-grid system.
Figure 17.
Battery current of BESS during discharging in pico-grid system.
Figure 18.
Battery capacity of BESS during discharging in pico-grid system.
Figure 18.
Battery capacity of BESS during discharging in pico-grid system.
Figure 19.
Voltage level at DC busbar in pico-grid system.
Figure 19.
Voltage level at DC busbar in pico-grid system.
Figure 20.
Surplus power delivered to the grid in pico-grid system.
Figure 20.
Surplus power delivered to the grid in pico-grid system.
Figure 21.
SOC level of the BESS during charging in pico-grid system.
Figure 21.
SOC level of the BESS during charging in pico-grid system.
Figure 22.
Battery voltage of the BESS during charging in pico-grid system.
Figure 22.
Battery voltage of the BESS during charging in pico-grid system.
Figure 23.
Battery voltage of the BESS during charging in pico-grid system.
Figure 23.
Battery voltage of the BESS during charging in pico-grid system.
Figure 24.
Battery current of BESS during charging in pico-grid system.
Figure 24.
Battery current of BESS during charging in pico-grid system.
Figure 25.
Battery capacity of BESS during charging in pico-grid system.
Figure 25.
Battery capacity of BESS during charging in pico-grid system.
Figure 26.
Drawing power from the grid to charge the battery in pico-grid system.
Figure 26.
Drawing power from the grid to charge the battery in pico-grid system.
Figure 27.
Two parallel pico-grids connected to the single-phase grid.
Figure 27.
Two parallel pico-grids connected to the single-phase grid.
Figure 28.
DC and AC loads before increase for two pico-grids system.
Figure 28.
DC and AC loads before increase for two pico-grids system.
Figure 29.
DC and AC loads before increase for two pico-grids system.
Figure 29.
DC and AC loads before increase for two pico-grids system.
Figure 30.
Surplus power from the system sent to the grid for two pico-grids system.
Figure 30.
Surplus power from the system sent to the grid for two pico-grids system.
Figure 31.
Simulation model of integration of solar PV, BESS with three-phase inverter.
Figure 31.
Simulation model of integration of solar PV, BESS with three-phase inverter.
Figure 32.
Solar PV array waveform.
Figure 32.
Solar PV array waveform.
Figure 33.
Load demand estimation of AC loads in nano-grid system.
Figure 33.
Load demand estimation of AC loads in nano-grid system.
Figure 34.
SOC of battery during discharging in nano-grid system.
Figure 34.
SOC of battery during discharging in nano-grid system.
Figure 35.
Battery voltage of the BESS during discharging in nano-grid system.
Figure 35.
Battery voltage of the BESS during discharging in nano-grid system.
Figure 36.
Battery current of BESS during discharging in nano-grid system.
Figure 36.
Battery current of BESS during discharging in nano-grid system.
Figure 37.
Battery capacity of BESS during discharging in nano-grid system.
Figure 37.
Battery capacity of BESS during discharging in nano-grid system.
Figure 38.
Voltage level at DC busbar in nano-grid system.
Figure 38.
Voltage level at DC busbar in nano-grid system.
Figure 39.
Surplus power delivered to the grid in nano-grid system.
Figure 39.
Surplus power delivered to the grid in nano-grid system.
Figure 40.
Simulation model to demonstrate charging of battery.
Figure 40.
Simulation model to demonstrate charging of battery.
Figure 41.
SOC of battery during charging in nano-grid system.
Figure 41.
SOC of battery during charging in nano-grid system.
Figure 42.
Battery voltage of the BESS during charging in nano-grid system.
Figure 42.
Battery voltage of the BESS during charging in nano-grid system.
Figure 43.
Voltage level at DC busbar in nano-grid system.
Figure 43.
Voltage level at DC busbar in nano-grid system.
Figure 44.
Battery current of BESS during charging in nano-grid system.
Figure 44.
Battery current of BESS during charging in nano-grid system.
Figure 45.
Battery capacity of BESS during charging in nano-grid system.
Figure 45.
Battery capacity of BESS during charging in nano-grid system.
Figure 46.
Drawing power from the grid to charge the battery in nano-grid system.
Figure 46.
Drawing power from the grid to charge the battery in nano-grid system.
Figure 47.
Simulation model to demonstrate a rainy day operation.
Figure 47.
Simulation model to demonstrate a rainy day operation.
Figure 48.
Load demand estimation of AC loads in nano-grid system.
Figure 48.
Load demand estimation of AC loads in nano-grid system.
Figure 49.
Solar PV power generated using stair generator in nano-grid system.
Figure 49.
Solar PV power generated using stair generator in nano-grid system.
Figure 50.
Power supplied by the grid to the load in nano-grid system.
Figure 50.
Power supplied by the grid to the load in nano-grid system.
Figure 51.
Simulation model to demonstrate a sunny day operation.
Figure 51.
Simulation model to demonstrate a sunny day operation.
Figure 52.
Load demand estimation of AC loads in nano-grid system.
Figure 52.
Load demand estimation of AC loads in nano-grid system.
Figure 53.
Solar PV power generated in nano-grid system.
Figure 53.
Solar PV power generated in nano-grid system.
Figure 54.
SOC of battery during charging in nano-grid system.
Figure 54.
SOC of battery during charging in nano-grid system.
Figure 55.
Battery capacity of BESS during charging in nano-grid system.
Figure 55.
Battery capacity of BESS during charging in nano-grid system.
Figure 56.
Surplus power delivered to the grid in nano-grid system.
Figure 56.
Surplus power delivered to the grid in nano-grid system.
Figure 57.
Two parallel nano-grids connected to the three-phase grid.
Figure 57.
Two parallel nano-grids connected to the three-phase grid.
Figure 58.
AC loads before increase for two nano-grids system.
Figure 58.
AC loads before increase for two nano-grids system.
Figure 59.
AC loads after increase for two nano-grids system.
Figure 59.
AC loads after increase for two nano-grids system.
Figure 60.
Surplus power from the system sent to the grid for two nano-grids system.
Figure 60.
Surplus power from the system sent to the grid for two nano-grids system.
Table 1.
Receptacle loads values for different space.
Table 1.
Receptacle loads values for different space.
| Receptacle loads |
Nominal values |
| Computer intensive office |
22 W/m2
|
| General office areas |
16 W/m2
|
| Large conference areas |
11 W/m2
|
| Schools (Tertiary/IHLs) |
8 W/m2
|
| Schools (Primary/Secondary) |
5 W/m2
|
| Server/computer rooms |
540 W/m2
|
Table 2.
DC loads estimation of Level B1 to B2 of SIT Punggol Campus.
Table 2.
DC loads estimation of Level B1 to B2 of SIT Punggol Campus.
Table 3.
AC loads estimation of Level B1 to B2 of SIT Punggol Campus.
Table 3.
AC loads estimation of Level B1 to B2 of SIT Punggol Campus.
Table 4.
Estimated load demand of Electric Charging Stations for B1 and B2.
Table 4.
Estimated load demand of Electric Charging Stations for B1 and B2.
Table 5.
DC loads estimation of Level L1 to L3 of SIT Punggol Campus.
Table 5.
DC loads estimation of Level L1 to L3 of SIT Punggol Campus.
Table 6.
AC loads estimation of Level L1 to L3 of SIT Punggol Campus.
Table 6.
AC loads estimation of Level L1 to L3 of SIT Punggol Campus.
Table 7.
DC loads estimation of Level L4 of SIT Punggol Campus.
Table 7.
DC loads estimation of Level L4 of SIT Punggol Campus.
Table 8.
AC loads estimation of Level L4 of SIT Punggol Campus.
Table 8.
AC loads estimation of Level L4 of SIT Punggol Campus.
Table 9.
Estimated load demand of server room.
Table 9.
Estimated load demand of server room.
Table 10.
Switching states of the single-phase inverter.
Table 10.
Switching states of the single-phase inverter.
| Cycle |
S1 |
S2 |
S3 |
S4 |
Voltage at Bridge Output |
State |
| Positive half cycle |
ON |
OFF |
OFF |
ON |
VDC |
1 |
| OFF |
ON |
OFF |
ON |
0 |
2 |
| Negative half cycle |
OFF |
ON |
ON |
OFF |
-VDC |
3 |
| ON |
OFF |
ON |
OFF |
0 |
4 |
Table 11.
Load demand estimation for centralized cooling.
Table 11.
Load demand estimation for centralized cooling.
Table 12.
Switching states of the three-phase inverter.
Table 12.
Switching states of the three-phase inverter.
| S1
|
S2
|
S3
|
S4
|
S5
|
S6
|
Vab
|
Vbc
|
Vca
|
State No |
| ON |
OFF |
ON |
OFF |
ON |
OFF |
0 |
0 |
0 |
1 |
| OFF |
ON |
ON |
OFF |
ON |
OFF |
-VDC
|
0 |
VDC
|
2 |
| ON |
OFF |
OFF |
ON |
ON |
OFF |
VDC
|
-VDC
|
0 |
3 |
| ON |
OFF |
ON |
OFF |
OFF |
ON |
0 |
VDC
|
-VDC
|
4 |
| ON |
ON |
OFF |
OFF |
ON |
OFF |
0 |
-VDC
|
VDC
|
5 |
| ON |
OFF |
OFF |
ON |
OFF |
ON |
VDC
|
0 |
-VDC
|
6 |
| OFF |
ON |
ON |
OFF |
OFF |
ON |
- VDC
|
VDC
|
0 |
7 |
| OFF |
ON |
OFF |
ON |
OFF |
ON |
0 |
0 |
0 |
8 |
Table 13.
Parameters of BESS.
Table 13.
Parameters of BESS.
| Parameters |
Value |
| Battery nominal voltage |
Vbatt = 48 V |
| Battery rated capacity |
Ibatt = 300 Ah |
| Initial SOC |
SOC = 45% |
| Switching frequency |
Fsw = 20 kHz |
| Inductor value |
L = 5 mH |
Table 14.
Parameters of single-phase inverter.
Table 14.
Parameters of single-phase inverter.
| Parameters |
Value |
| Switching frequency |
Fsw = 5 kHz |
| Filter inductor |
L = 5 mH |
| Filter capacitor |
C = 5 µF |
| DC link voltage |
VDC = 400 V |
| Distribution grid voltage |
Vgrid = 230 V (phase) |
Table 15.
Parameters of solar PV system.
Table 15.
Parameters of solar PV system.
| Parameters |
Value |
| Series connected strings |
10 |
| Parallel connected strings |
10 |
| Vmp
|
Vmp = 40.8 V |
| Imp
|
Imp = 9.81 A |
| Sun irradiance |
Ir = 1000 W/m2
|
| Cell temperature |
T = 25 °C |
Table 16.
Parameters of boost converter.
Table 16.
Parameters of boost converter.
| Parameters |
Value |
| Switching frequency |
Fsw = 5kHz |
| Inductor value |
L = 2.5 mH |
| Input capacitor value |
Cin = 1000 µF |
| Output capacitor value |
Cout = 4000 µF |
Table 17.
Parameters of BESS.
Table 17.
Parameters of BESS.
| Parameters |
Value |
| Battery nominal voltage |
Vbatt = 400 V |
| Battery rated capacity |
Ibatt = 300 Ah |
| Initial SOC |
SOC = 45% |
| Switching frequency |
Fsw = 10 kHz |
| Inductor value |
L = 1 mH |
Table 18.
Parameters of three phase inverter.
Table 18.
Parameters of three phase inverter.
| Parameters |
Value |
| Switching frequency |
Fsw = 10 kHz |
| Inductor value |
L = 10 mH |
| DC link voltage |
VDC = 1000 V |
| Distribution grid voltage |
Vgrid = 400 V (line) |