Fuzzy Analysis of Financial Risk Management Strategies for Sustainable Public-Private Partnership Infrastructure Projects in Ghana

This version is not peer-reviewed.

Submitted:

21 March 2024

Posted:

26 March 2024

You are already at the latest version

A peer-reviewed article of this preprint also exists.

Abstract
Public-private partnership (PPP) is a prominent tool for sustainable infrastructure development. However, the positive contributions of PPPs towards attainment of sustainable, climate resilience and zero carbon infrastructure projects are hampered by poor financial risk management. This problem is more prevalent in developing countries like Ghana where private investment inflow has plummeted due to COVID-19 recession and poor project performance. Thus, this study aims at assessing the key financial risk management strategies in ensuring sustainable PPP infrastructure projects in Ghana. The study utilised primary data from PPP practitioners in Ghana solicited through survey questionnaires. Factor analysis, mean scores and fuzzy synthetic analysis are the data analysis techniques for this study. The results revealed sustainable and green funding models, effective cost reduction initiatives, competent team with committed leadership, and emerging technologies and regulations constitute the key strategies to manage financial risks of sustainable PPP infrastructure projects. Although, future studies must expand the scope of data gathering, the findings of the study enrichen the theoretical understanding of financial risks in sustainable investments in PPP infrastructures. Relevant remedies that will aid the development of practical financial risk management guidelines are provided in this study for PPP practitioners.
Keywords: 
;  ;  ;  ;  

1. Introduction

Achieving sustainable infrastructure development has been proven to be contending especially for developing economies. Developing nations such as Ghana are confronted with short-lived and poorly maintained public-sponsored infrastructure projects together with huge infrastructure deficit [1,2]. These limitations put a cap on the progress towards the attainment of sustainable development. The challenge is demonstrated in trafficked and congested transport networks, dilapidated school buildings, hospitals, and recreational centres, and polluted water supply among others [3,4]. In Ghana, the developmental challenges have worsened by rapid urbanization and high population growth rate [4]. The ever-increasing population demands eco-friendly and sustainable facilities and projects to meet the basic needs of life. However, the financial support from the Government of Ghana (GoG) is not enough to build and operate infrastructures for all the citizenry due to insufficient budgetary funds [5,6]. Recent COVID-19 recession and banking crisis in the country have impacted negatively on the flow of private investment into sustainable and environmentally-conscious development projects [7]. Project such as the extension of Accra-Tema Motorway including the eco-recreational parks, Ghana-Burkina Railway Interconnectivity, Installation of Lquid Waste Treatment Plant in Kotoku, Sogakope-Lome Transboundary Water Supply and Atuabo Natural Gas Processing Plant have been financed through the public-private partnership arrangements [8,9].
Nevertheless, these eco-friendly PPP projects have recorded monumental financial challenges. Scholarly works on financial challenges in Ghana together with project, and institutional reports from Ministry of Finance, Ghana, World Bank and African Development Bank position financial risks as the topmost obstacle to successful execution of sustainability-inspired and climate-friendly PPP projects. Financial risks such as rising costs of materials, operating the facilities, maintenance, and energy consumption, as well as lower than expected revenue from these projects pose threatening risks to the projects and financial investment returns for private financiers. Therefore, it is necessary that effective and sustainable financial measures are implemented to mitigate these negative consequences [10,11]. This study aims at analysing the financial risk management strategies for sustainable and eco-friendly PPP infrastructure projects in Ghana. The major significance of this article is twofold. The results provide relevant guiding measures on financial risks to assist PPP project managers and practitioners. The study could be an integral part of the strategies designed to improve organisational and project management processes on limiting financial losses for sustainable infrastructure development and future studies. The rest of the study presents literature review, methodology, the results from the data analysis, and conclusion.

2. Literature Review

2.1. Sustainable Public-Private Partnership Infrastructure Projects

Sustainable infrastructure development has become a well embraced concept in environmentally-conscious and social inclusion matters [12]. It requires a degree of environmental, social, and economic improvement to ensure the well-being of future generations [13]. Sustainable infrastructure development is embedded in the all the 17 goals of United Nation’s Sustainable Development Goals (SDGs) [14]. However, Villalba-Romero, et al. [15] explained that sustainable infrastructure development agenda could not achieved without the strong support private financiers who play paramount roles in shifting hitherto government-sponsored projects to public-private partnership (PPP) infrastructure projects. Fast-forward into the current and future PPP infrastructure development is the inclusion of environmental and social impact assessments of the projects together with net-zero and climate-friendly targets [16]. Similarly, the policies and programs of sustainability of renovating and improving the lifespan of existing PPP-built infrastructures are aimed at meeting the social needs of the society and preserve the environmental resources [17]. There is also a growing global recognition to consider the integration of sustainability and eco-friendly designs into infrastructure projects delivered through public–private partnerships (PPPs) [18]. The successful implementation of sustainable measures in infrastructural projects is considered as an important strategy for attaining sustainability [19].

2.2. Financial Risks in Sustainable PPP Infrastructure Projects

Prior and during the COVID-19 pandemic, financial risk has been recognised as a topical issue among PPP practitioners and financiers [20]. Financial risk is rated as a significant influencer of poor PPP infrastructure performance [21]. Financial risks encompass all the cashflow challenges related to the PPP infrastructure development [22]. They include rising loan interest charges, difficulty in soliciting for funds to build and maintain the PPP projects, additional construction budgeted costs, bloated operation and maintenance expenditure, low revenue from the project, poor investment returns to financiers and high market risks that emanates from unfavourable macroeconomic conditions. Akomea-Frimpong, et al. [23] identified fifty-four (54) topmost financial risks in relation to PPP projects. Among these 54 financial risks, financial charges associated with contractual loans was prominent followed by construction costs, inflation, and operation expenses. Osei-Kyei, et al. [24], study revealed the existence of shortage of funds to complete PPP projects in developing economies. Zhang, et al. [25], Xenidis and Angelides [26] and Yun, et al. [27] analysed the key variables that influence financial viability of PPP projects using credit worthiness of bond capital, the financial expertise of the project team, general prevailing economic conditions. The studies explored special purpose vehicles that undertook comparative analysis of project’s financial success. The analysis of the economic constraints of PPPs were analysed with the touch of both non-financial and economic models in transport, schools, hospitals, and playgrounds under the PPP arrangements. Prominent influencing factors that occasion financial difficulties are regulation-related with strict terms and caps on the amount that can be contracted and spent on PPPs [28,29]. The coronavirus pandemic also triggered lockdowns and compulsory restrictions putting on a strain on the usage of PPP infrastructures which are already in operation [30]. It has prompted revenue (cash inflow) crisis with PPP infrastructure operations closing with piling debts. However, it remains unexplored the multidimensional perspectives on measures to reduce the financial losses of PPP infrastructure projects.

3. Research Methodology

3.1. Questionnaire Survey Data

The starting point in designing the survey questionnaire was the search for the appropriate variables to be included in the survey. So, a review of existing literature was conducted using the terms “financial risk management strategies” and “sustainable and eco-friendly public-private partnership projects”. Scholarly literature from Web of Science, EBSCOhost, Scopus, Web of Science, and Google Scholar were retrieved and thoroughly analysed to extract data for the content of the survey questionnaire. These bibliographic databases are prominent in searching and extracting relevant literature for academic research in the Architecture, Engineering, and Construction research field. After thorough review of the articles retrieved with more emphasis on Ghana, forty-one (41) financial risk management strategies (FRMSs) were extracted from the literature. The 41 FRMSs were given to five experts (two senior academics and three practitioners who are knowledgeable in PPP projects) through pilot testing. The feedback received from the experts assisted in making changes to the variables to meet the PPP project-setting of Ghana. Some of the 41 variables were either deleted or merged with other variables reducing the number to twenty-three as shown in Table 1. Two sections included in the survey questionnaire were the profile of respondents (Section 1), and financial risk management strategies (Section 2). The variables (statements) in Section 2 were the items demonstrated in Table 1.
The targeted participant to respond to the statements in the surveys were practitioners and experts on PPP projects in Ghana. To participate in this study, a respondent must have taken a significant part in the construction and operation of a PPP project or PPP-related activity. Purposively, the respondents (participants) were selected were encouraged to nominate or recommend colleagues to be involved in the data collection process. In summary, a total of 403 participants were compiled with personal and career profiles. Emails were sent to the targeted participants but 334 responded to the emails and responded to the Qualtric links of the survey questionnaires attached to the emails. Upon thorough data cleaning, 283 surveys were accepted, and 51 responses were deleted due to failure to respond to the statements in the questionnaire. The 287 surveys were fully filled and analysed. This sample size (287 responses) is sufficient and it is supported by prior statistical models on the adequacy of sample size by Sunindijo and Kamardeen [31], Kotrlik and Higgins [32] and Cochran [33]. The mathematical equation is demonstrated as follows:
N = t 2 X s 2 d 2
The N refers to the sample size, t is the significance level at 0.05 (5%) with a critical value of 1.96, s represents the estimated variance of deviation within the 5 points Likert scale, d is the points or scales on a Likert scale multiplied by a margin of error. Therefore, the expected sample size from this mathematical equation is supposed to be:
N = 1.96 2 X 1 2 ( 5 * 0.05 ) 2 = 61
The results from the mathematical formula of 61 respondents is lower than the accepted sample size of this study of 287 responses, confirming the sufficiency of the dataset. Table 2 demonstrates the description of the respondents.

3.2. Analysis of Data

Statistically, the dataset’s reliability was tested to ascertain the internal consistency of the data within the SPSS statistical software 29 (Statistical Package for the Social Sciences). With the aid of Cronbach Alpha (CA), a 0.872 CA score was realised for the reliability test, a reflection of the internal consistency of the multiple items in the questionnaire [34]. Further, the Shapiro-Wilk test was conducted to establish the nature of the normality of the data [35]. The outcomes of the analysis show p-values of less than 0.000, an indication of non-normal distribution of the dataset [36]. With this result, it settled the stage for the usage of non-parametric data analysis techniques of Kruskal-Wallis test together with Mann-Whitney U test [37,38]. These non-parametric statistical tools assisted in establishing the differences views of the participants of this study [39]. The two statistical techniques are commonly utilized to assess the significant differences in non-parametric datasets [40]. Three categories of data were analysis to determine the differences and criticality of the 287 datasets: PPP practitioners, PPP project types and PPP sectors.
Further, exploratory factor analysis (EFA) was used to extract principal factors from the 287 datasets. EFA explores the causal relationships between the latent variables and the measured items acting as common factor model [41]. In EFA, the fundamental tests to determine the reliability and validity of the model include Kaiser-Meyer-Olkin (KMO) that measures the sampling adequacy of the dataset. Its significance and adequacy are established by Bartlett’s Sphericity test. Communalities within the EFA analysis indicate the sum of loadings of the variance explained by a variable (or factor). With the rotation results showcasing the minimisation of variables to retain significant financial risk management variables.
Lastly, the data is analysed with fuzzy synthetic evaluation method. Linguistically, fuzzy logic theory rectifies the anomalies in complicated reasoning and vague terms that appear in subjective views on a subject into a more objective set of outcomes [42]. With fuzzy analysis, the subjective opinions can be operationalised and computed to ascertain desired results for decision making. Fuzzy synthetic evaluation (FSE) promotes the evaluation of diverse responses for decision-making based on different set of ranking criteria [43]. Previous studies such as Nguyen and Macchion [42] and Kukah, et al. [44] mentioned that FSE is appropriate the analysis of diverse factors (or criteria) in different fields. Within the construction project management literature, Xu, et al. [45], Wuni, Shen and Osei-Kyei [35] and Ekanayake, et al. [46] stated that FSE establishes weights and membership functions that ensures objective analysis of matters associated with the management of construction firms and projects. Additionally, Owusu-Manu, et al. [47] and Osei-Kyei, et al. [48] recounted the appropriateness of FSEs in choosing the critical factors in multi-criteria decision making scenarios. The FSE in this study is modelled as follows.
Step one: Establish the principal groups from the exploratory factor analysis, P C F R = f 1 ,   f 2 ,   f i , f m .
Step two: Set a grading alternatives, G t = g t 1 ,   g t 2 ,   g t 3 , g t e where: g t 1 = Strongly disagree, g t 2 = Disagree, g t 3 = Neutral, g t 4 = Agree and g t 5 =Strongly agree.
Step three: Determine the weightings (Wi) of each of the financial risk management strategies and the principal groups using their mean scores.
Step four: Construct the fuzzy evaluation matrix from the principal groups:
R i = X 11 X 12 X 13 X 14 X 15 X 21 X 22 X 23 X 24 X 25 X 31 X 32 X 33 X 34 X 35 X m 1 X m 2 X m 3 X m t
Where R i is the fuzzy evaluation matrix,
Step five: Undertake the fuzzy synthetic evaluation as:
D i = W i R i
Where D i represents the FSE value, W i   is the weightings function, R i   is the membership functions of the principal groups and “●” is the fuzzy composite operator.
D i = w t 1 ,   w t 2 ,   w t 3 , w t m X 11 X 12 X 13 X 14 X 15 X 21 X 22 X 23 X 24 X 25 X 31 X 32 X 33 X 34 X 35 X m 1 X m 2 X m 3 X m t
Step six: Calculate both criticality indexes of the entire dataset and each principal (group) factor using:
K = i = 1 5 D x G
Where G = ( 1,2 , 3,4 , 5 ) , the grading alternatives.

4. Results

4.1. Mean Scoring Analysis

In this section, the mitigating strategies on financial risks to increase the financial outcomes of sustainable and eco-friendly PPP projects are analysed. The criticality threshold varies in past studies of 2.5, 3, 4 and 4.5 [59]. In this analysis, the minimum of mean of 3.0 adopted based on the outcomes of the dataset and importance of the FRMSs in comparison with researches such as Babatunde, Opawole and Akinsiku [54] and Tang and Shen [60]. From the Table 3, 4 and 5, it is noticeable that almost all means of the FRMSs range from 3 to 5. These ratings provided by respondents presupposes that these critical financial risk management strategies of sustainable infrastructures in Ghana. Consequently, to assess the difference in perceptions held by the two main parties involved in PPP projects i.e., public, and private sectors, when it came to the ranking of the 23 identified FRMSs, Mann-Whitney U test (at 5% level of significance). The null hypothesis posited no difference in the perceptions of both sectors on FRMSs. As vividly demonstrated in Table 3 of the test results and it indicates statistically significant values that for all the identified FRMs. That means, the two sectors related to the PPP projects in Ghana hold different views about management strategies on financial risks to enhance sustainable infrastructures in the country within the PPP arrangements. In Table 4 and Table 5 tested differences in perspectives of four groups of PPP practitioners in Ghana and three groups of PPP project types with Kruskal-Wallis test. The aim was to depict the statistically significant differences in comparing the various groupings with results indicating statistical significance values at p-value of 0.050. Substantially, the null hypothesis of no differences in views of practitioners on FRMSs of sustainable and eco-friendly PPP projects in Ghana is rejected. This indicates that there are real differences in the perception of practitioners on the FRMSs. The expansive results in Table 5 buttresses the differing perspectives of participants on the financial risk management measures on project types: social, economic, and environmental PPP projects. The analysis was set on the null hypothesis that a project type will not trigger the adoption of a particular FRMS. However, the outputs of the Kruskal-Wallis test analysis give a different result where nineteen of the FRMSs recorded significant values less than 5% [17].

4.2. Factor Analysis

To examine the underlying relationships of the twenty-three (23) FRMSs, the exploratory factor analysis (EFA) technique was employed. Previously, studies such as Muhammad and Johar [61] and Rachmawati, et al. [62] have adopted EFA to assess the relationships between variables and given vivid explanations of the complex phenomena surrounding the variables in PPP research. Zhang [63] also argued that EFA is useful to condense bulky data into an abridged version. The preliminary statistical tests that were performed before conducting the EFA for the FRMSs (Chan et al., 2010). The KMO score was established from the analysis as 0.884 greater than the recommended threshold value of 0.60 used in existing literature [64]. The Bartlett’s test of Sphericity results include chi-square = 9268.672 with significance level = 0.000 approving the suitability of the survey data for the appropriate analysis on the 23 FRMSs in the FA [65,66]. Following these tests of the dataset, the extraction of the groups with principal component analysis (PCA) using a varimax rotation was undertaken and the outcome a six-factor solution shown in Table 6. The popularity of varimax rotation is known in the PPP research domain due to its simplification of the interpretation comparative to other rotation methods [67]. Table 6 shows the four-factor components producing eigenvalues more than 1.0 and explains 74.96% of the variances in the respondents given by the participants of the survey. The factor loadings of the variables indicate the portion a variable contributes to a principal component [34]. With the factor loadings and the eigenvalues of the groups, all the 23 FRMSs belong to a principal group, with factor loadings more than 0.7, the required threshold [68].

4.3. Fuzzy Synthetic Evaluation

From the results in Section 4.2 (factor analysis), the levels of fuzzy synthetic evaluation (FSE) can be drawn to further analyse the dataset on FRMS. The FSE involves the multi-factor and multi-level approach starting from the third level, the criticality of each of the items (FRMSs) in the four principal components (FRMSGs) are assessed [69,70]. This is followed by the second level analysis which determines the criticality of the principal components (FRMSGs). Finally, it is at the first level that the overall financial risk management strategies index is computed flowing from level two and three. To summarise the evaluation of the FSE as presented in Section 3.2, the following steps are applied:
a) Determine the weightings of the FRMSs and FRMSGs
Studies such as Chang, et al. [71] and Aghimien, Aigbavboa, Edwards, Mahamadu, Olomolaiye, Nash and Onyia [69] mentioned that the overall outcomes of the FSE analysis is dependent on the weights assigned to each of the FRMSs and FRMSGs. To compute the weightings, there are different types of techniques available in existing literature such as the mean normalisation method, the analytic hierarchy process, point allocation system, judgement method and unit weighting [72,73]. In this analysis, the mean scoring approach (using the overall mean criticality scores) is adopted due to its ability to transform and strengthen the stability of test data and the model [45,74]. The weightings of the FRMSGs and FRMSs are determined as follows:
w i = M C S i i = 1 5 M C S i , 0 < w i < 1 , a n d i = 1 n w i = 1
w i represents the weighting function of each of the FRMSs and the FRMSGs whiles M C S i demonstrates the mean criticality score of each of variables. i shows the scores on the 5-point Likert scale which is the grading scales. In summary, the weighting function is given as:
w i = w 1 , w 2 ,   w 3 ,   w 4 . , w n
For instance, in Table 7, the mean score of FRMS2 is 4.73, and it is part of FRMSG1 which has a total mean criticality score of 32.30. Therefore, the weighting of FRMS2 was determined as:
w t C F R 18 = 4.73 4.73 + 4.50 + 4.11 + 4.36 + 3.44 + 3.95 + 3.23 + 3.98 = 4.73 32.30 = 0.146
Similarly, the same calculation was done for all the FRMSs as shown in Table 7. The weightings form the basis the determination of the membership functions. The computation undertook for the FRMSGs include the following:
w t F R M S G 1 = 32.30 32.20 + 27.91 + 17.31 + 11.76 = 32.30 89.28 = 0.362
w t F R M S G 2 = 27.91 32.20 + 27.91 + 17.31 + 11.76 = 27.91 89.28 = 0.313
w t F R M S G 3 = 17.31 32.20 + 27.91 + 17.31 + 11.76 = 17.31 89.28 = 0.194
w t F R M S G 4 = 32.30 32.20 + 27.91 + 17.31 + 11.76 = 17.31 89.28 = 0.132
b) Membership functions of the FRMSs and FRMSGs
The source of the membership functions (MFs) of the FRMSs is the percentage of the overall responses to the questionnaire survey dataset. As mentioned in Section 3.1, Likert-scale of the financial risk management strategies was set as: Strongly disagree (1), SiD; Disagree (2), Di; Neutral (3), Ne; Agree (4), Ag; and Strongly Agree (5), SiA. Therefore, to determine the MF of the FRMS4 (strategic green financing alliance), the responses of 2.40% rating on “Strongly disagree”, 6.60% on “Disagree”, 30.70% on “Neutral”, 38.30% on “Agree” and 22.00% on “Strongly agree” ratings from the 287 datasets. Therefore, the MF of FRMS4 is computed as:
M F C F R 18 = 0.024 S i D ( 1 ) + 0.066 D i ( 2 ) + 0.307 N e ( 3 ) + 0.383 A g ( 4 ) + 0.220 S i A ( 5 )
Giving a membership function of FRMS4 is (0.024, 0.066, 0.307, 0.383, 0.220). The rest of the MFs of FRMSs are calculated using the same approach. Further, the MFs of the FRMSGs (level 2) are obtained from the MFs of the FRMSs (level 3) and their weightings. This establishes the fuzzy evaluation matrix which is the combination of the membership functions of FRMSs and the weightings as:
D i = W i R i
Where D i represents the FSE evaluation matrix, W i is the weightings function, R i is the fuzzy evaluation matrix and “●” is the fuzzy composite operator. Based on this explanation, the membership functions of the FRMSGs can be computed as:
D i = w 1 , w 2 , w i , w m X 11 X 12 X 13 X 14 X 15 X 21 X 22 X 23 X 24 X 25 X 31 X 32 X 33 X 34 X 35 X m 1 X m 2 X m 3 X m t
FRMSG1 had weights of w t F R M S G 4 = 0.322 , 0.286 , 0.392 , and membership function of FRMSG4 of
R F R M S G 4 = 0.010 0.042 0.244 0.348 0.355 0.035 0.094 0.105 0.453 0.314 0.000 0.042 0.087 0.244 0.627
Thus, the fuzzy evaluation matrix for the FRMSG4 is:
D F R M S G 4 = 0.322 , 0.286 , 0.392 0.010 0.042 0.244 0.348 0.355 0.035 0.094 0.105 0.453 0.314 0.000 0.042 0.087 0.244 0.627 = ( 0 . 013 , 0 . 057 , 0 . 143 , 0 . 337 , 0 . 0450 )
The same approach is applied to compute the fuzzy matrixes for FRMSG1, FRMSG2 and FRMSG3 as demonstrated in Table 8.
c) The criticality indexes of the principal groups and the entire dataset.
The combination of the fuzzy matrixes and the grade alternatives set from the overall outcomes of the financial risk management strategies on the Likert-scale of 1 to 5. In view of this, the criticality indices of the FRMSs are set as:
F R M S G i n d e x = i = 1 5 ( D i x G i )
Where G i = ( 1,2 , 3,4 , 5 ) on the ranging scale of the Likert concerning the total effectiveness of the financial risk management strategies, and D i is the Fuzzy evaluation matrix. Consequently, the critical factor groups were computed as:
F R M S G 1 = 0.031 , 0.097 , 0.265 , 0.374 , 0.232 X ( 1 , 2 , 3 , 4 , 5 ) = ( 0 . 031 * 1 + 0 . 097 * 2 + 0 . 265 * 3 + 0 . 374 * 4 + 0 . 232 * 5 ) = 3 . 679
F R M S G 2 = 0.023 , 0.048 , 0.208 , 0.362 , 0.359 X ( 1 , 2 , 3 , 4 , 5 ) = ( 0 . 023 * 1 + 0 . 048 * 2 + 0 . 208 * 3 + 0 . 362 * 4 + 0 . 359 * 5 ) = 3 . 985
F R M S G 3 = 0.020 , 0.076 , 0.131 , 0.373 , 0.400 X ( 1 , 2 , 3 , 4 , 5 ) = ( 0 . 020 * 1 + 0 . 076 * 2 + 0 . 131 * 3 + 0 . 373 * 4 + 0 . 400 * 5 ) = 4 . 058
F R M S G 4 = 0.013 , 0.057 , 0.143 , 0.337 , 0.450 X ( 1 , 2 , 3 , 4 , 5 ) = ( 0 . 013 * 1 + 0 . 057 * 2 + 0 . 143 * 3 + 0 . 337 * 4 + 0 . 450 * 5 ) = 4 . 154
The overall index of the FRMS was determined with the fuzzy matrices of FRMSGs and the sum weightings. First, the fuzzy evaluation matrix is computed from Table 7, the FRMSGs have weightings of W o v e r a l l F R M S G i = ( 0.362 , 0.313 , 0.194 , 0.132 ) and Table fuzzy matrixes:
R O v e r a l l F R M S G i = 0.031 0.097 0.265 0.374 0.232 0.023 0.048 0.208 0.362 0.359 0.020 0.076 0.131 0.373 0.400 0.013 0.057 0.143 0.337 0.450
Therefore, the overall financial risk management strategies matrix is computed as:
D o v e r a l l P C F R = W o v e r a l l P C F R R o v e r a l l P C F R
D o v e r a l l P C F R = ( 0.362 , 0.313 , 0.194 , 0.132 ) X 0.031 0.097 0.265 0.374 0.232 0.023 0.048 0.208 0.362 0.359 0.020 0.076 0.131 0.373 0.400 0.013 0.057 0.143 0.337 0.450
= (0.024, 0.072, 0.205, 0.365, 0.333)
Then, the overall financial risk management strategies index is calculated as:
O v e r a l l F R M S i n d e x = 0.024 , 0.072 , 0.205 , 0.365 , 0.333 X ( 1,2 , 3,4 , 5 ) = ( 0 . 024 * 1 ) + ( 0 . 072 * 2 ) + ( 0 . 205 * 3 ) + ( 0 . 365 * 4 ) + ( 0 . 333 * 5 ) = 3 . 911

4. Discussion

Authors The results from the above fuzzy synthetic analysis shown an overall criticality index of 3.911 of the datasets indicating the role the financial risk management strategies play in ensuring the sustainability of PPP infrastructures in Ghana even in the face of the country’s economic crisis. In addition, the findings indicate four principal groupings of the financial risk management strategies with criticality scores above 3.0 the threshold set for this analysis. A further demonstration of the relevance of these strategies presented in this study for practice and project policies. The FRMSs have cumulative variance explained of 74.96% (see Table 6) with factor loadings of the FRMSs (> 0.7) [75,76]. The principal groupings are explained as follows:
Component 1: Sustainable funding for the project (FRMSG1).
This principal group of the FRMSs explains 30.134 per cent of the principal components generated of the eigenvectors with a critical score of 3.68 from the fuzzy synthetic analysis. In agreement with the findings of Debela [68], the basis of curtailing financial risks on sustainable and climate funding to support resilient PPP projects. The requirement to attain this goal is through strategic financial alliance. This alliance consists of collaboration between local financial institutions in Ghana, international financers, and consortium of investors. In recent decades, project funding through the PPP arrangements has embrace private investments to support paltry national budget to construction projects in Ghana. While some of the finance alliance were triggered by arrangements instituted by the Breton Woods institutions as part of Structural Adjustment Programs (SAP) to reform and develop the country’s infrastructures [50,77]. Other strategic alliances are deliberately entered into by the Ghanaian government with international donor agencies and private financiers to accelerate the development of the country [10]. Even though, these strategic alliances bring in financial supports, downsides resulting from non-involvement of stakeholders during critical decision making processes in such financing arrangements in constructing and maintaining PPP infrastructures at every region of Ghana could result to numerous unsolicited misunderstandings and conflicts among all concerned parties i.e. the general public and project parties [55]. Some disputes and legal actions taken to challenge the investment of private investors and rogue nations have led to public uproar and non-achievement of targets set for certain projects. Thus, as a means of ensuring openness and transparency through high levels of accessibility, parties to the project particularly the public departments and agencies need to liaise with all other concerned stakeholders when critical matters resulting in decisions are to be discussed. These issues might resort to financial contracts that have a tendency to influence the tariffs, pricing, and conditions of service provisions of the project [78]. Moreover, in situations where private financiers form a consortium to finance the project, there must be clear regulations and documentations to guide the responsibilities of the financiers [79]. Several private institutions within Ghana and investors on the capital market should agree to jointly supervise the funding of projects in the country with the facilitation ensured by the government. Unlike in a loan syndication, consortium allows banks and investors to pull together a large amount of capital to fund a PPP project [80]. Effective consortiums handle large or too risky funds of projects. Instituting a wide coverage of insurance also contributes substantially to ensuring the sustainability and success of the project. Any of the projects constructed using a PPP arrangement should be covered including property, fire, and health insurance policies for both the infrastructure and human beings (construction workers and users of the project). The process of purchasing an insurance policy for the project must be unbiased and non-discriminatory and even more so, the premiums and claims should be reported to the appropriate stakeholders of the project [81]. As another means to enhance the transparency in the insurance policies, it is becoming a necessity for project stakeholders to be clear on mutual insurance rewards and specifically detail the duties of the partners within the partnership pact. Insurance coverages go a long way to reduce accidental claims from the project [82].
Component 2: Cost reduction initiatives (FRMSG2)
In Table 7, 21.55% is the fraction of the explained variance on FRMSs of PPPs in Ghana is attributed to this factor component. The position of this principal group is third with criticality score of 3.985. This outcome buttresses the outputs of Aladaǧ and Işik [21], where that study posited that establishing effective cost reduction strategies and efficient revenue mobilisation influence positively on the financial outcomes of climate-friendly PPP projects. Carbonara, et al. [83] mentioned the need for clear cost reduction strategies while fulfilling the societal pact to serve the community at a lesser to no profit from the project. This singular step aids in achieving the financial targets of the project by clarifying communication in minimizing negative perceptions and conflicts. Further, Ke, et al. [84] also stated that it important that project managers assume broad-consultation of the tariffs of the PPP project in Ghana with the users so charges and fees do not become a surprise amount to be dealt with for the users. Quick and adequate information sharing lead to understanding and it stands a chance of increasing the demand and access to the project if users understand the details of the charges expected from them [85]. Information sharing and consultation with users of the project are also key in avoiding undue agitation from pressure groups who are likely give the project a bad name and draw people away from using the project in Ghana that could in the long run affect the revenue targets of the project negatively [86]. Ideally, using financial software boost information sharing and management of the financial transactions of the project. Within the financial software of CostX, the cost of the project can be monitored consistently with the revenue outcomes during the operational stage of the project. In addition, financial software packages and reporting guidelines suitable for the sustainable zero carbon PPP project need to adopt to enhance the transparency of financial data on the infrastructure projects by key allied parties [87]. Providing quick reports to the partners and even the public in general minimize the challenges of the poor demand for sustainable PPP projects in Ghana. With technology in use the records on the project cost sharing together with revenue disbursement is facilitated with the assistance of financial experts. Ensuring efficiency and large quantum of revenue from the project are retained necessitates thorough and fact-based revenue risk evaluation and the suitable allocation of revenue risks among stakeholders [88]. At the early phases of the projects, investment appraisal software needs to be comprehensively used to review, identify, and project all sources with a high potential of revenue risks that could derail the financial rewards of the project [89].
Component 3: Competent team with committed leadership (FRMSG3).
This crucial factor component accounts for 14.192% of the variance explained in Table 7. The results of Demirag, et al. [90] study correspond with good leadership and component people-cantered measures to assess and control financial deficits recorded on sustainable infrastructures under the PPP contracts in Ghana. By employing the right and competent people with the sole aim of reducing overall projects costs and boosting returns of capital investment minimizes financial risks [58,63]. Aldrete, Bujanda and Valdez [53] reiterates the role of competent personnel in the success of sustainable PPP projects cannot be overemphasized. Thus, the focus of robust financial risk management must be on the level of expertise and training of the people managing the financial risks. First, stakeholders especially project managers and construction workers who are the centre of reporting losses, must be trained to know the constituents of these financial reports and measures to improve upon the outcomes across all sectors of the PPP market [51]. Also, competent quantity surveyors, financial consultants, project cost managers, and auditors should be the priority of the top management of the project to position the project against incurring avoidable costs. The extent of commitment and expertise exhibited by these experts have influence of the net revenue [91]. At the pre-construction stage of the project, loopholes in the procurement contract and potential corrupt practices could be detected with pre-design controllable practices to minimize the expected costs during the entire lifespan of the project. However, the personal financial interests of the experts must be checked when such competent people are engaged to avoid role conflicts and misapplication of the project funds [92]. Furthermore, a strong partnership must be built among stakeholders, and measures must be implemented to manage stakeholder conflicts [93]. Lasting financial alliances should be encouraged to create a consortium of financers for a project and similar projects in the future [94].
Component 4: Innovative technologies and regulations (FRMSG4).
The outcome of the EFA of this fourth component shows variance explained of 9.08% and it occupies the first position of the fuzzy synthetic analysis. This establishes this component as the key financial risk controlling strategy for sustainable PPP project development in Ghana. Financial regulations provide the step-by-step method needed for the implementation of the financial controls to minimize the financial risks of the PPP projects specified clearly in the legal books [76]. These measures encompass relevant steps of action taken in planning, monitoring, and providing feedback to appropriate authorities through a sound financial system to mitigate cost overruns which are determined by an industry practice or legal framework [95]. The attainment of risk maturity on financial transactions of the projects requires a sound legal process regarding the structures and systems to upgrade the financial success of the project. Recently, the Ghanaian government passed a public-private partnership Act, 2020 [57]. However, the bureaucratic and complex processes of reporting the financial transactions on PPP projects together with unclear legal provisions were found in the regulations [96]. Thus, there is a need for review of the current regulations to account for the account for adequate legal backing in managing expenses and income generated in operating the project. The financial systems on PPP projects in the country must be reviewed and integrated in the national governance processes where a competent experts supervise and give timely reports to top state officials and key private financiers about the progress of the project. Also, it is necessary that the project governance committee understand the legal processes involved in securing capital from financiers of the project (private investors and financial institutions) and maintain a sound financial management of the project funds [49]. Yun, et al. [97] mentioned that the stimulation of clear financial regulations mitigates financial losses. Consequently, a comprehensive and accessible regulatory framework must embody a broad-based viewpoint of stakeholders on PPP contracts. Financial standards and laws on accessing capital, sharing of financial risks, and investment returns need to spell out clearly the managerial roles of prominent stakeholders of the projects. Moreover, contracts on PPP projects are secured and yield greater financial success when there are well-established regulations, including exclusion clauses, contingency provisions, fixed-price supplies, performance-based payments, and quality standards [98,99]. Also, stringent regulations on Minimum Revenue Guarantee (MRG) provides private investors the confidence to make available capital investments for similar projects [100]. The role of the state at this crucial point is to boost and secure private financial alliances for similar PPP infrastructure projects in the future [101]. Favourable pricing policies on user tariffs must embrace the broad consultations of stakeholders and market forces to take into consideration the standard of living of Ghanaians to the project [85]. Such regulations on tariffs should be monitored and supervised by state officials, the project’s team members such as quantity surveyors and professional project finance experts continuously through the project’s lifecycle to reduce overall project costs.

6. Practical and Research Implications of the Study

In recent past, Ghana has been experiencing challenges with its economic outlook together with budgetary shortages as reported by the Ministry of Finance and Bank of Ghana. Moreover, the COVID-19 economic recession has taken a large hit on the economic advances of the country affecting the funding of PPP projects [52,102]. Thus, the results of this are important to understand and equip project managers to devise measures to attract funding and management financial risks in these challenging times. Learning from the consequences of the pandemic and past funding challenges to infrastructure projects in the country, project managers and key stakeholders can institute project-based financial policies and budgets to either minimise or lower current project account deficits, stimulate favourable investment outcomes and promote inclusive financial management solutions that care of fluctuations in exchange rate, interest charge and inflation rates [103]. With increasing focus on net-zero, climate resilience and sustainability-based financial risk management measures, this study provides key measures to meet the economic sustainability targets. Further, the relevance of this study is in the mitigation of shortages of funds and the establishment of guiding practice framework to support the construction and management of PPP projects in Ghana. In addition, the study is important to multiple-stakeholder partners who take active part in the PPP financing and development in Ghana in understanding project financial reporting systems and governance structures. Effective project finance risk management policies coupled with investment successes increase the confidence investors have in PPP projects and will increase private investments into Ghana’s public project development.
Future studies should use this study as a guide to delve deeper into the risks on the economic sustainability of PPP projects and similar developing countries who share key developmental features like Ghana. In addition, the financial management of PPP infrastructures in Ghana can be facilitated by solutions from researchers using innovative technological software to develop project-focused financial risk management framework to guide PPP projects. The advancement of health and safety technology-based financial assessment and management are important to understand the challenges of construction workers. Drawing lessons from this study, studies must investigate into financial risk management measures to manage climate change, nature-based solutions, social inclusion, and environmentally inspired risks of PPP infrastructure initiation, development, and management.

7. Conclusion and Limitations

ThisThis study identified, assessed, and established the financial risk management strategies (FRMSs) for sustainable PPP project development. It undertook questionnaire survey of knowledgeable and experienced PPP experts in the Ghanaian economy. The data analysis was done with non-parametric tests (Kruskal-Wallis and Mann-Whitney U) in addition to factor analysis and fuzzy synthetic evaluation to analyse the differences between PPP practitioners, sectors, and project types. Statistically, the results showed no significant differences between the views of the various groups on mitigation strategies on financials risks of PPPs. The study also evaluated the criticality of the principal components of the FRMSs using exploratory factor analysis and fuzzy synthetic evaluation method. The findings include the promotion of sustainable funding, effective cost reduction strategies, inclusion of competent team members together with good leadership who are focused on ensuring the sustainable development of PPP projects. Also, the study established emerging technologies and regulations and strong financial alliances towards climate-resilient PPP projects.
Despite these relevant findings aimed at mitigating financial risks on sustainable infrastructures like schools, roads, and hospitals in the PPP contracts for Ghana’s socio-economic development, the study has some limitations which must be addressed. Limited categories of analysis were done in this study using project type, sector, and practitioner. Further studies must expand the scope to include but not limited to analysis on project size, the capital investment, project settings and external stakeholders to attain more multidimensional framework to countermeasure financial risks. With a limited sample size of responses from PPP practitioners in Ghana, the generalizability of the application of the findings is affected. Thus, caution must be exercised in the applications of the findings of the study taking into consideration the project setting and economic environment.

Author Contributions

Conceptualization, literature review, methodology, data collection and analysis, writing—original draft preparation, and editing (Isaac Akomea-Frimpong), review, and supervision (Xiaohua Jin and Robert Osei-Kyei). All authors have read and agreed to the published version of the manuscript.

Data Availability Statement

Data for this article will be available upon request from the corresponding author.

Acknowledgments

Authors are thankful for the immense contributions from reviewers and authors to produce rich research output.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R.; Kukah, A.S. Public–private partnerships for sustainable infrastructure development in Ghana: A systematic review and recommendations. Smart and Sustainable Built Environment 2021, 12, 237–257. [Google Scholar] [CrossRef]
  2. Mahmood, S.; Misra, P.; Sun, H.; Luqman, A.; Papa, A. Sustainable infrastructure, energy projects, and economic growth: Mediating role of sustainable supply chain management. Annals of Operations Research 2024, 1–32. [Google Scholar] [CrossRef]
  3. Aidoo, R. Ghana’s exceptionalism in economic reforms? Resolve vs. results. The Politics of Economic Reform in Ghana 2019. [Google Scholar]
  4. Owusu-Ansah, A.; Soyeh, K.W.; Asabere, P.K. Developer constraints on housing supply in urban Ghana. International Journal of Housing Markets and Analysis 2019, 12, 59–73. [Google Scholar] [CrossRef]
  5. Acheampong, R.A. Urbanization and Settlement Growth Management. In Spatial Planning in Ghana; Springer: 2019; pp. 171-203.
  6. Oteng-Ababio, M.; Smout, I.; Amankwaa, E.F.; Esson, J. The divergence between acceptability of municipal services and urbanization in developing countries: Insights from Accra and Sekondi-Takoradi, Ghana. Geografisk Tidsskrift-Danish Journal of Geography 2017, 117, 142–154. [Google Scholar] [CrossRef]
  7. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R.; Tumpa, R.J. A critical review of public–private partnerships in the COVID-19 pandemic: Key themes and future research agenda. Smart and Sustainable Built Environment 2022. [Google Scholar] [CrossRef]
  8. Owusu-Antwi, G.; Antwi, J.; Ashong, J.D.; Owusu-Peprah, N.T. Evidence on the Co-Integration of the Determinants of Foreign Direct Investment in Ghana. Journal of Finance and Economics 2016, 4, 23–45. [Google Scholar] [CrossRef]
  9. Anarfo, E.B.; Agoba, A.M.; Abebreseh, R. Foreign direct investment in Ghana: The role of infrastructural development and natural resources. African Development Review 2017, 29, 575–588. [Google Scholar] [CrossRef]
  10. Effah, E.A.; Chan, A.P.; Owusu-Manu, D.-G. Domestic private sector participation in small-town water supply services in Ghana: Reflections on experience and policy implications. Public Organization Review 2015, 15, 175–192. [Google Scholar] [CrossRef]
  11. Osei-Kyei, R.; Chan, A.P. Risk assessment in public-private partnership infrastructure projects. Construction innovation 2017. [Google Scholar] [CrossRef]
  12. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R.; Kukah, A.S. Public–private partnerships for sustainable infrastructure development in Ghana: A systematic review and recommendations. Smart and Sustainable Built Environment 2023, 12, 237–257. [Google Scholar] [CrossRef]
  13. Saha, P.; Islam, M.; Oyshi, J.T.; Khanum, R.; Nishat, A. A sustainability analysis on the trends and frequency of the channel flow of a carp breeding river against human interventions and governing public–private partnership (PPP) as adaptation. SN Applied Sciences 2020, 2, 1–17. [Google Scholar] [CrossRef]
  14. UN. Closing the infrastructure gap. 2020.
  15. Villalba-Romero, F.; Liyanage, C.; Roumboutsos, A. Sustainable PPPs: A comparative approach for road infrastructure. Case Studies on Transport Policy 2015, 3, 243–250. [Google Scholar] [CrossRef]
  16. Ogunde, A.O.; Amos, V.; Tunji-Olayeni, P.; Akinbile, B.; Ogunde, A. Evaluation of application of eco friendly systems in buildings in Nigeria. Int. J. Civ. Eng. Technol 2018, 9, 568–576. [Google Scholar]
  17. Agarchand, N.; Laishram, B. Sustainable infrastructure development challenges through PPP procurement process: Indian perspective. International Journal of Managing Projects in Business 2017, 10, 642–662. [Google Scholar] [CrossRef]
  18. Akomea-Frimpong, I.; Agyekum, A.K.; Amoakwa, A.B.; Babon-Ayeng, P.; Pariafsai, F. Toward the attainment of climate-smart PPP infrastructure projects: A critical review and recommendations. Environment, Development and Sustainability, 2023; 1–35. [Google Scholar]
  19. Shen, L.; Tam, V.; Gan, L.; Ye, K.; Zhao, Z. Improving sustainability performance for public-private-partnership (PPP) projects. Sustainability 2016, 8, 289. [Google Scholar] [CrossRef]
  20. Casady, C.B.; Baxter, D. Pandemics, public-private partnerships (PPPs), and force majeure| COVID-19 expectations and implications. Construction management and economics 2020, 38, 1077–1085. [Google Scholar] [CrossRef]
  21. Aladaǧ, H.; Işik, Z. Role of Financial Risks in BOT Megatransportation Projects in Developing Countries. Journal of Management in Engineering 2017, 33. [Google Scholar] [CrossRef]
  22. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Managing financial risks to improve financial success of public—private partnership projects: A theoretical framework. Journal of Facilities Management, 2021; ahead-of-print. [Google Scholar] [CrossRef]
  23. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. A holistic review of research studies on financial risk management in public–private partnership projects. Engineering, construction and architectural management 2021, 28, 2549–2569. [Google Scholar] [CrossRef]
  24. Osei-Kyei, R.; Jin, X.; Nnaji, C.; Akomea-Frimpong, I.; Wuni, I.Y. Review of risk management studies in public-private partnerships: A scientometric analysis. International Journal of Construction Management 2022, 1–12. [Google Scholar] [CrossRef]
  25. Zhang, S.; Li, J.; Li, Y.; Zhang, X. Revenue Risk Allocation Mechanism in Public-Private Partnership Projects: Swing Option Approach. Journal of Construction Engineering and Management 2021, 147, 04020153. [Google Scholar] [CrossRef]
  26. Xenidis, Y.; Angelides, D. The financial risks in build-operate-transfer projects. Construction Management and Economics 2005, 23, 431–441. [Google Scholar] [CrossRef]
  27. Yun, S.; Han, S.H.; Kim, H.; Ho Ock, J. Capital structure optimization for build-operate- transfer (BOT) projects using a stochastic and multi-objective approach. Canadian Journal of Civil Engineering 2009, 36, 777–790. [Google Scholar] [CrossRef]
  28. Duarte, J.M.D.; Fernandez, R.N.; Silva, R.V. Public-private Partnerships for Medicine Provision: An alternative to the combat to the covid-19 pandemic. Revista Do Servico Publico 2020, 71, 91–110. [Google Scholar] [CrossRef]
  29. Castelblanco, G.; Guevara, J.; Salazar, J. Remedies to the PPP crisis in the COVID-19 pandemic: Lessons from the 2008 global financial crisis. Journal of Management in Engineering 2022, 38, 04022017. [Google Scholar] [CrossRef]
  30. Baxter, D.; Casady, C.B. A coronavirus (COVID-19) triage framework for (sub) national public–private partnership (PPP) programs. Sustainability 2020, 12, 5253. [Google Scholar] [CrossRef]
  31. Sunindijo, R.Y.; Kamardeen, I. Work stress is a threat to gender diversity in the construction industry. Journal of Construction Engineering and Management 2017, 143, 04017073. [Google Scholar] [CrossRef]
  32. Kotrlik, J.; Higgins, C. Organizational research: Determining appropriate sample size in survey research appropriate sample size in survey research. Information technology, learning, and performance journal 2001, 19, 43. [Google Scholar]
  33. Cochran, W.G. Sampling Techniques: 3d Ed; Wiley: 1977.
  34. Alteneiji, K.; Alkass, S.; Abu Dabous, S. Critical success factors for public–private partnerships in affordable housing in the United Arab Emirates. International Journal of Housing Markets and Analysis 2020, 13, 753–768. [Google Scholar] [CrossRef]
  35. Wuni, I.Y.; Shen, G.Q.; Osei-Kyei, R. Quantitative evaluation and ranking of the critical success factors for modular integrated construction projects. International Journal of Construction Management 2020, 1–13. [Google Scholar] [CrossRef]
  36. Fathi, M.; Shrestha, P.P. Public–Private Partnership Project Performance Analysis Compared to Design-Build in Highway Projects. Journal of Construction Engineering and Management 2022, 148, 04022118. [Google Scholar] [CrossRef]
  37. Owusu; Chan, A.P.C.; Shan, M. Causal Factors of Corruption in Construction Project Management: An Overview. Sci. Eng. Ethics 2019, 25, 1–31. [Google Scholar] [CrossRef] [PubMed]
  38. Paek, S.Y.; Nalla, M.K.; Lee, J. Determinants of police officers’ support for the public-private partnerships (PPPs) in policing cyberspace. Policing-an International Journal of Police Strategies & Management 2020, 43, 877–892. [Google Scholar] [CrossRef]
  39. Osei-Kyei; Chan. Perceptions of stakeholders on the critical success factors for operational management of public-private partnership projects. Facilities 2017.
  40. Ismail, S.; Haris, F.A. Constraints in implementing public private partnership (PPP) in Malaysia. Built Environment Project and Asset Management 2014. [Google Scholar] [CrossRef]
  41. Zhang, X. Factor analysis of public clients’ best-value objective in public–privately partnered infrastructure projects. Journal of Construction Engineering and management 2006, 132, 956–965. [Google Scholar] [CrossRef]
  42. Nguyen, H.D.; Macchion, L. A comprehensive risk assessment model based on a fuzzy synthetic evaluation approach for green building projects: The case of Vietnam. Engineering, Construction and Architectural Management 2023, 30, 2837–2861. [Google Scholar] [CrossRef]
  43. Zimmermann, H.-J. Fuzzy set theory—and its applications; Springer Science & Business Media: 2011.
  44. Kukah, A.S.K.; Owusu-Manu, D.-G.; Badu, E.; Edwards, D.J. Evaluation of risk factors in Ghanaian public-private-partnership (PPP) power projects using fuzzy synthetic evaluation methodology (FSEM). Benchmarking: An International Journal 2023, 30, 2554–2582. [Google Scholar] [CrossRef]
  45. Xu, Y.; Yeung, J.F.; Chan, A.P.; Chan, D.W.; Wang, S.Q.; Ke, Y. Developing a risk assessment model for PPP projects in China—A fuzzy synthetic evaluation approach. Automation in construction 2010, 19, 929–943. [Google Scholar] [CrossRef]
  46. Ekanayake, E.; Shen, G.; Kumaraswamy, M.; Owusu, E.K. A fuzzy synthetic evaluation of vulnerabilities affecting supply chain resilience of industrialized construction in Hong Kong. Engineering, Construction and Architectural Management 2022, 29, 2358–2381. [Google Scholar] [CrossRef]
  47. Owusu-Manu, D.-G.; Kukah, A.S.K.; Edwards, D.J.; Ameyaw, E.E. Fuzzy synthetic evaluation of moral hazard and adverse selection of public private partnership projects. International Journal of Construction Management 2021, 1–10. [Google Scholar] [CrossRef]
  48. Osei-Kyei, R.; Chan, A.P.; Ameyaw, E.E. A fuzzy synthetic evaluation analysis of operational management critical success factors for public-private partnership infrastructure projects. Benchmarking: An International Journal 2017.
  49. Kwofie, T.E.; Afram, S.; Botchway, E. A critical success model for PPP public housing delivery in Ghana. Built Environment Project and Asset Management 2016, 6, 58–73. [Google Scholar] [CrossRef]
  50. Konadu-Agyemang, K. IMF and World Bank sponsored structural adjustment programs in Africa: Ghana’s experience, 1983-1999; Routledge: 2018.
  51. Babatunde, S.O.; Perera, S.; Zhou, L.; Udeaja, C. Stakeholder perceptions on critical success factors for public-private partnership projects in Nigeria. Built Environment Project and Asset Management 2016, 6, 74–91. [Google Scholar] [CrossRef]
  52. Asante, L.A.; Mills, R.O. Exploring the socio-economic impact of COVID-19 pandemic in marketplaces in urban Ghana. Africa Spectrum 2020, 55, 170–181. [Google Scholar] [CrossRef]
  53. Aldrete, R.; Bujanda, A.; Valdez, G.A. Valuing public-sector revenue risk exposure in transportation public–private partnerships. Transportation Research Record 2012, 2297, 88–96. [Google Scholar] [CrossRef]
  54. Babatunde, S.O.; Opawole, A.; Akinsiku, O.E. Critical success factors in public-private partnership (PPP) on infrastructure delivery in Nigeria. Journal of facilities management 2012, 10, 212–225. [Google Scholar] [CrossRef]
  55. Badu, E.; Owusu-Manu, D.-G.; Edwards, D.J.; Holt, G.D. Innovative financing (IF) of infrastructure projects in Ghana: Conceptual and empirical observations. Engineering Project Organization Journal 2011, 1, 255–268. [Google Scholar] [CrossRef]
  56. Eyiah-Botwe, E.; Aigbavboa, C.O.; Thwala, W.D. Curbing PPP construction projects’ failure using enhanced stakeholder management success in developing countries. Built Environment Project and Asset Management 2019, 10, 50–63. [Google Scholar] [CrossRef]
  57. Ghana, G.o. Public Private Parternship Act. 2020.
  58. Luo, C.; Ju, Y.; Dong, P.; Gonzalez, E.D.S.; Wang, A. Risk assessment for PPP waste-to-energy incineration plant projects in china based on hybrid weight methods and weighted multigranulation fuzzy rough sets. Sustainable Cities and Society 2021, 74, 103120. [Google Scholar] [CrossRef]
  59. Ismail; Takim, R.; Nawawi, A.H. The evaluation criteria of Value for Money (VFM) of Public Private Partnership (PPP) bids. In Proceedings of the International Conference on Intelligent Building and Management, 2011; pp. 349-355.
  60. Tang, L.; Shen, Q. Factors affecting effectiveness and efficiency of analyzing stakeholders’ needs at the briefing stage of public private partnership projects. International Journal of Project Management 2013, 31, 513–521. [Google Scholar] [CrossRef]
  61. Muhammad, Z.; Johar, F. Critical success factors of public–private partnership projects: A comparative analysis of the housing sector between Malaysia and Nigeria. International Journal of Construction Management 2019, 19, 257–269. [Google Scholar] [CrossRef]
  62. Rachmawati, F.; Soemitro, R.A.A.; Adi, T.J.W.; Susilawati, C. Critical success factor for partnership in low-cost apartments project: Indonesia perspective. Pacific Rim Property Research Journal 2018, 24, 149–160. [Google Scholar] [CrossRef]
  63. Zhang, X. Critical success factors for public-private partnerships in infrastructure development. Journal of Construction Engineering and Management 2005, 131, 3–14. [Google Scholar] [CrossRef]
  64. Gebremeskel, M.N.; Kim, S.Y.; Nguyen, M.V. Forming a driving index for implementing public-private partnership projects in emerging economy: Ethiopian perception. Engineering, Construction and Architectural Management, 2020. [Google Scholar]
  65. Dithebe, K.; Aigbavboa, C.O.; Thwala, W.D.; Oke, A.E. Factor analysis of critical success factors for water infrastructure projects delivered under public–private partnerships. Journal of Financial Management of Property and Construction 2019. [Google Scholar] [CrossRef]
  66. Ismail, S.; Mohamad, R.; Said, J.M. Performance indicators for lifecycle process of public private partnership (PPP) projects in Malaysia. Built Environment Project and Asset Management 2021. [Google Scholar] [CrossRef]
  67. Du, J.; Wu, H.; Zhao, X. Critical factors on the capital structure of Public-Private Partnership projects: A sustainability perspective. Sustainability (Switzerland) 2018, 10. [Google Scholar] [CrossRef]
  68. Debela, G.Y. Critical success factors (CSFs) of public–private partnership (PPP) road projects in Ethiopia. International Journal of Construction Management 2019. [Google Scholar] [CrossRef]
  69. Aghimien, D.O.; Aigbavboa, C.; Edwards, D.J.; Mahamadu, A.-M.; Olomolaiye, P.; Nash, H.; Onyia, M. A fuzzy synthetic evaluation of the challenges of smart city development in developing countries. Smart and Sustainable Built Environment 2020, 11, 405–421. [Google Scholar] [CrossRef]
  70. Alfaro-García, V.G.; Merigó, J.M.; Pedrycz, W.; Gómez Monge, R. Citation analysis of fuzzy set theory journals: Bibliometric insights about authors and research areas. International Journal of Fuzzy Systems 2020, 22, 2414–2448. [Google Scholar] [CrossRef]
  71. Chang, N.-B.; Chen, H.-W.; Ning, S.-K. Identification of river water quality using the fuzzy synthetic evaluation approach. Journal of environmental management 2001, 63, 293–305. [Google Scholar] [CrossRef] [PubMed]
  72. Ameyaw, E.E.; Chan, A.P. Evaluation and ranking of risk factors in public–private partnership water supply projects in developing countries using fuzzy synthetic evaluation approach. Expert Systems with Applications 2015, 42, 5102–5116. [Google Scholar] [CrossRef]
  73. Wuni, I.Y.; Shen, G.Q.; Osei-Kyei, R.; Agyeman-Yeboah, S. Modelling the critical risk factors for modular integrated construction projects. International journal of construction management 2022, 22, 2013–2026. [Google Scholar] [CrossRef]
  74. Dahiya, S.; Singh, B.; Gaur, S.; Garg, V.; Kushwaha, H. Analysis of groundwater quality using fuzzy synthetic evaluation. J. Hazard. Mater. 2007, 147, 938–946. [Google Scholar] [CrossRef]
  75. Ahmadabadi, A.A.; Heravi, G. The effect of critical success factors on project success in Public-Private Partnership projects: A case study of highway projects in Iran. Transport Policy 2019, 73, 152–161. [Google Scholar] [CrossRef]
  76. Chan; Lam, P. T.I.; Chan, D.W.M.; Cheung, E.; Ke, Y. Critical success factors for PPPs in infrastructure developments: Chinese perspective. Journal of Construction Engineering and Management 2010, 136, 484–494. [Google Scholar] [CrossRef]
  77. Konadu-Agyemang, K.; Takyi, B.K. Structural adjustment programs and the political economy of development and underdevelopment in Ghana. In IMF and World Bank Sponsored Structural Adjustment Programs in Africa; Routledge: 2018; pp. 17-40.
  78. Chileshe, N.; Yirenkyi-Fianko, A.B. An evaluation of risk factors impacting construction projects in Ghana. Journal of Engineering, Design and Technology, 2012. [Google Scholar]
  79. Chan, A.P.; Ameyaw, E.E. The private sector’s involvement in the water industry of Ghana. Journal of Engineering, Design and Technology, 2013. [Google Scholar]
  80. Chiang, Y.H.; Cheng, E.W.L. Perception of financial institutions toward financing PFI projects in Hong Kong. Journal of Construction Engineering and Management 2009, 135, 833–840. [Google Scholar] [CrossRef]
  81. Dikmen, I.; Birgonul, M.T.; Atasoy, G. Best Value Procurement in Build Operate Transfer Projects: The Turkish Experience. In Policy, Finance & Management for Public-Private Partnerships; 2009; pp. 363-378.
  82. Ter Haar, R.; Laney, A.; Levine, M. Construction insurance and UK construction contracts; Informa Law from Routledge: 2016.
  83. Carbonara, N.; Costantino, N.; Gunnigan, L.; Pellegrino, R. Risk management in motorway PPP projects: empirical-based guidelines. Transport Reviews 2015, 35, 162–182. [Google Scholar] [CrossRef]
  84. Ke; Wang; Chan. Risk management practice in China’s Public-Private Partnership projects. J. Civ. Eng. Manage. 2012, 18, 675–684. [Google Scholar] [CrossRef]
  85. Kumar, L.; Jindal, A.; Velaga, N.R. Financial risk assessment and modelling of PPP based Indian highway infrastructure projects. Transport Policy 2018, 62, 2–11. [Google Scholar] [CrossRef]
  86. Kardes, I.; Ozturk, A.; Cavusgil, S.T.; Cavusgil, E. Managing global megaprojects: Complexity and risk management. Int. Bus. Rev. 2013, 22, 905–917. [Google Scholar] [CrossRef]
  87. Hood, J.; Asenova, D.; Bailey, S.; Manochin, M. The UK’s prudential borrowing framework: A retrograde step in managing risk? Journal of Risk Research 2007, 10, 49–66. [Google Scholar] [CrossRef]
  88. Shen, L.Y.; Platten, A.; Deng, X.P. Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management 2006, 24, 587–594. [Google Scholar] [CrossRef]
  89. Kim, K.; Cho, H.; Yook, D. Financing for a sustainable PPP development: Valuation of the contractual rights under exercise conditions for an urban railway PPP Project in Korea. Sustainability (Switzerland) 2019, 11. [Google Scholar] [CrossRef]
  90. Demirag, I.; Khadaroo, I.; Stapleton, P.; Stevenson, C. Risks and the financing of PPP: Perspectives from the financiers. The British Accounting Review 2011, 43, 294–310. [Google Scholar] [CrossRef]
  91. Chen, Y.Q.; Zhang, Y.B.; Liu, J.Y.; Mo, P. Interrelationships among critical success factors of construction projects based on the structural equation model. Journal of Management in Engineering 2011, 28, 243–251. [Google Scholar] [CrossRef]
  92. Jacobson, C.; Ok Choi, S. Success factors: Public works and public-private partnerships. International Journal of Public Sector Management 2008, 21, 637–657. [Google Scholar] [CrossRef]
  93. Ng, S.T.; Wong, Y.M.; Wong, J.M. Factors influencing the success of PPP at feasibility stage–a tripartite comparison study in Hong Kong. Habitat International 2012, 36, 423–432. [Google Scholar] [CrossRef]
  94. Simon, L.; Jefferies, M.; Davis, P.; Newaz, M.T. Developing a theoretical success factor framework for the tendering phase of social infrastructure PPPs. International Journal of Construction Management 2020, 20, 613–627. [Google Scholar] [CrossRef]
  95. Bing, L.; Akintoye, A.; Edwards, P.J.; Hardcastle, C. The allocation of risk in PPP/PFI construction projects in the UK. International Journal of project management 2005, 23, 25–35. [Google Scholar] [CrossRef]
  96. Sehgal, R.; Dubey, A.M. Identification of critical success factors for public–private partnership projects. Journal of Public Affairs 2019, 19. [Google Scholar] [CrossRef]
  97. Yun, S.; Jung, W.; Han, S.H.; Park, H. Critical organizational success factors for public private partnership projects - A comparison of solicited and unsolicited proposals. J. Civ. Eng. Manage. 2015, 21, 131–143. [Google Scholar] [CrossRef]
  98. Olusola Babatunde, S.; Opawole, A.; Emmanuel Akinsiku, O. Critical success factors in public-private partnership (PPP) on infrastructure delivery in Nigeria. Journal of Facilities Management 2012, 10, 212–225. [Google Scholar] [CrossRef]
  99. Shi, S.; Chong, H.Y.; Liu, L.; Ye, X. Examining the interrelationship among critical success factors of public private partnership infrastructure projects. Sustainability (Switzerland) 2016, 8. [Google Scholar] [CrossRef]
  100. Sun, H.; Jia, S.; Wang, Y. Optimal equity ratio of BOT highway project under government guarantee and revenue sharing. Transportmetrica A: Transport Science 2019, 15, 114–134. [Google Scholar] [CrossRef]
  101. Tan, J.; Zhao, J.Z. The Rise of Public–Private Partnerships in China: An Effective Financing Approach for Infrastructure Investment? Public Administration Review 2019, 79, 514–518. [Google Scholar] [CrossRef]
  102. Morgan, A.K.; Awafo, B.A.; Quartey, T. The effects of COVID-19 on global economic output and sustainability: Evidence from around the world and lessons for redress. Sustainability: Science, practice and policy 2021, 17, 76–80. [Google Scholar] [CrossRef]
  103. Phibbs, P. Driving alone: Sydney’s cross city tunnel. Built Environment 2008, 34, 364–374. [Google Scholar] [CrossRef]
Table 1. Financial risk management strategies (FRMSs) of sustainable PPP infrastructure projects.
Table 1. Financial risk management strategies (FRMSs) of sustainable PPP infrastructure projects.
S/N FRMSs References
FRMS1 Effective cost management strategies for sustainable and climate-friendly projects Osei-Kyei and Chan [11]
FRMS2 Access to enough capital to support sustainable projects Anarfo, Agoba and Abebreseh [9]
FRMS3 Sound corporate governance structures to meet economic sustainability targets. Kwofie, et al. [49]
FRMS4 Strategic green financing alliance Akomea-Frimpong, Jin and Osei-Kyei [23]
FRMS5 Stabilisation of the macroeconomic indicators to foster sustainable projects Konadu-Agyemang [50]
FRMS6 Timely and independent audit review of project transactions Osei-Kyei and Chan [39]
FRMS7 Adopting hedging strategies such as options, swaps, futures and forward Aladaǧ and Işik [21]
FRMS8 Timely financial reports supervised by a project committee Babatunde, et al. [51]
FRMS9 Strong financial support from the community towards eco-friendly projects. Owusu-Antwi, Antwi, Ashong and Owusu-Peprah [8]
FRMS10 Thorough assessment of pre-construction stage fees and costs Effah, Chan and Owusu-Manu [10]
FRMS11 Involve professional financial consultants in the financial valuation of the projects Asante and Mills [52]
FRMS12 Roll out consistent and effective financial monitoring controls Aladaǧ and Işik [21]
FRMS13 Carefully planned measures to cover financial uncertainties and climate crisis. Akomea-Frimpong, Jin and Osei-Kyei [23]
FRMS14 Resilient commitment from top management towards inclusive financial practices Aldrete, et al. [53]
FRMS15 Clear and specific financial goals of the project are set from the start of the project Babatunde, et al. [54]
FRMS16 Risk-based tariff pricing to trigger sustained inflow of revenues and green finance Badu, et al. [55]
FRMS17 Social needs and concerns of project users included in toll charges. Eyiah-Botwe, et al. [56], Owusu, Chan and Shan [37]
FRMS18 Promotion of innovative technologies for financial risk management Akomea-Frimpong, Jin and Osei-Kyei [23]
FRMS19 The presence of strong private consortium attracted enough funds for the project Konadu-Agyemang [50]
FRMS20 Affordable insurance coverage to manage financial shocks Osei-Kyei and Chan [11]
FRMS21 Enough funding for recycling of construction wastes and carbon emissions Eyiah-Botwe, Aigbavboa and Thwala [56]
FRMS22 Strong political support to investigate and manage misuse of project funds Ghana [57],
FRMS23 Availability of comprehensive financial regulations Ghana [57], Luo, et al. [58]
Table 2. Basic information of respondents.
Table 2. Basic information of respondents.
Profile Category Frequency Percent (%)
Education status Diploma 20 6.97
Undergraduate 165 57.49
Masters 89 31.01
PhD 13 4.53
Total 287 100.00
Years of working on PPPs From 0-5 years 93 32.40
6 -10 years 127 44.25
11 -15 years 42 14.63
More than 15 years 25 8.71
Total 287 100.00
Participation in PPP projects 1 to 2 projects 149 51.92
3 to 4 projects 101 35.19
Either 5 or more projects 37 12.89
Total 287 100.00
PPP Sector Private 153 53.31
Public 134 46.69
Total 287 100.00
PPP project Type Social projects 87 30.31
Economic projects 122 42.51
Environmental projects 78 27.18
Total 287 100.00
PPP practitioner (title) Project manager 72 25.09
Quantity surveyor 69 24.04
Risk Manager 81 28.22
Account (finance) manager 65 22.65
Total 287 100.00
Table 3. Analysis of the dataset on PPP Sectors.
Table 3. Analysis of the dataset on PPP Sectors.
PPP sectors Mann-Whitney U test
Financial risk management strategies Public Sector Private Sector U-Stat. p-value Level of Sig.
Overall MS Rank MS SD MS SD
FRMS1 4.68 1 4.75 0.55 4.60 0.80 8.334 0.000 Significant
FRMS2 4.61 2 4.64 0.65 4.58 0.83 5.712 0.000 Significant
FRMS3 4.58 3 4.57 0.71 4.58 0.87 15.234 0.000 Significant
FRMS4 4.54 4 4.51 0.83 4.57 0.80 6.732 0.000 Significant
FRMS5 4.51 5 4.49 0.97 4.53 0.89 4.042 0.000 Significant
FRMS7 4.50 6 4.49 0.95 4.51 0.89 0.073 0.000 Significant
FRMS9 4.46 7 4.42 0.97 4.49 0.79 9.321 0.000 Significant
FRMS12 4.45 8 4.41 0.95 4.49 0.86 4.795 0.000 Significant
FRMS15 4.45 9 4.41 0.91 4.48 0.85 12.842 0.000 Significant
FRMS17 4.44 10 4.41 0.83 4.46 0.87 11.115 0.000 Significant
FRMS19 4.40 11 4.41 0.93 4.39 0.88 14.123 0.000 Significant
FRMS20 4.38 12 4.39 0.96 4.37 0.94 7.322 0.000 Significant
FRMS22 4.33 13 4.35 0.97 4.30 1.02 12.619 0.000 Significant
FRMS23 4.19 14 4.28 0.99 4.09 1.13 4.211 0.000 Significant
FRMS10 3.79 15 3.49 1.40 4.08 0.15 6.231 0.000 Significant
FRMS11 3.65 16 3.25 1.37 4.05 1.10 7.432 0.000 Significant
FRMS13 3.62 17 3.21 1.46 4.03 1.24 19.432 0.000 Significant
FRMS14 3.48 18 3.17 1.38 3.78 1.28 12.232 0.000 Significant
FRMS16 3.44 19 3.13 1.43 3.75 0.36 14.422 0.000 Significant
FRMS18 3.41 20 3.09 0.04 3.73 1.36 3.562 0.000 Significant
FRMS21 3.35 21 3.02 1.45 3.67 1.37 11.424 0.000 Significant
FRMS6 3.24 22 2.80 1.43 2.88 1.37 16.331 0.000 Significant
FRMS8 3.16 23 2.59 1.35 2.53 1.36 19.321 0.000 Significant
Table 4. Critical analysis of the dataset of PPP Practitioners.
Table 4. Critical analysis of the dataset of PPP Practitioners.
Perspectives of PPP practitioners Kruskal -Wallis test
Project managers Quantity Surveyors Risk Managers Account/finance officers F-Stat. p-value Level of Significance
Financial risk management strategies Overall MS Rank MS SD MS SD MS SD MS SD
FRMS1 4.84 1 4.70 0.74 4.75 0.62 4.91 0.19 4.98 0.10 16.392 0.000 Significant
FRMS2 4.73 2 4.63 0.91 4.64 0.64 4.77 1.15 4.86 1.22 23.302 0.000 Significant
FRMS3 4.61 3 4.62 0.84 4.64 0.67 4.45 1.18 4.71 1.28 12.520 0.000 Significant
FRMS4 4.50 4 4.61 0.67 4.62 0.77 4.22 1.19 4.55 1.18 6.382 0.000 Significant
FRMS5 4.36 5 4.59 0.85 4.60 0.71 4.01 0.26 4.25 1.26 11.450 0.000 Significant
FRMS7 4.23 6 4.57 0.96 4.60 0.64 3.88 1.25 3.85 0.43 7.894 0.000 Significant
FRMS9 4.11 7 4.54 0.93 4.58 0.70 3.88 1.29 3.43 1.40 22.410 0.000 Significant
FRMS12 4.03 8 4.51 0.96 4.55 0.68 3.63 1.43 3.42 1.42 0.093 0.541 Insignificant
FRMS15 4.00 9 4.51 0.73 4.50 0.78 3.58 1.35 3.39 1.40 3.431 0.000 Significant
FRMS17 3.98 10 4.50 0.92 4.47 0.77 3.57 1.38 3.36 1.43 5.921 0.000 Significant
FRMS19 3.95 11 4.45 0.85 4.46 0.78 3.54 1.44 3.36 1.47 18.321 0.000 Significant
FRMS20 3.85 12 4.45 0.74 4.07 1.24 3.52 0.47 3.35 1.44 2.932 0.000 Significant
FRMS22 3.84 13 4.43 0.78 4.06 1.29 3.51 1.47 3.35 1.39 10.832 0.000 Significant
FRMS23 3.79 14 4.41 0.84 3.92 1.27 3.50 1.44 3.34 0.48 0.432 0.343 Insignificant
FRMS10 3.58 15 3.64 1.40 3.90 1.42 3.46 1.45 3.32 1.38 8.732 0.000 Significant
FRMS11 3.56 16 3.58 1.38 3.90 1.43 3.46 1.40 3.31 1.46 4.921 0.000 Significant
FRMS13 3.54 17 3.54 0.43 3.88 1.38 3.43 0.46 3.29 1.44 12.032 0.000 Significant
FRMS14 3.49 18 3.48 1.43 3.78 1.44 3.43 1.37 3.28 1.47 13.320 0.000 Significant
FRMS16 3.44 19 3.46 1.48 3.73 1.40 3.30 1.36 3.26 1.11 5.321 0.000 Significant
FRMS18 3.36 20 3.43 0.64 3.49 1.39 3.28 1.40 3.25 1.40 14.321 0.000 Significant
FRMS21 3.23 21 3.25 1.42 3.16 1.42 3.27 1.43 3.24 1.43 12.342 0.000 Significant
FRMS6 3.14 22 2.82 1.35 2.67 0.05 2.85 0.42 2.61 0.56 3.453 0.000 Significant
FRMS8 3.09 23 2.57 1.37 2.53 1.32 2.59 0.02 2.52 1.50 2.342 0.000 Significant
Table 5. Critical analysis of PPP project type data.
Table 5. Critical analysis of PPP project type data.
PPP project type Kruskal-Wallis test
Economic projects Social projects Environmental projects F-Stat. p-value Level of Sig.
Financial risk management strategies Overall MS Rank MS SD MS SD MS SD
FRMS1 4.64 1 4.95 0.62 4.59 0.85 4.81 0.14 13.481 0.000 Significant
FRMS2 4.57 2 4.74 0.64 4.58 0.87 4.39 1.44 7.452 0.000 Significant
FRMS3 4.53 3 4.64 0.67 4.57 0.80 4.38 1.41 6.431 0.000 Significant
FRMS4 4.50 4 4.62 0.77 4.53 0.89 4.37 1.21 5.324 0.000 Significant
FRMS5 4.24 5 4.62 0.84 3.78 1.28 4.34 1.38 19.432 0.000 Significant
FRMS7 4.00 6 4.60 0.71 3.67 1.37 4.31 1.38 15.911 0.000 Significant
FRMS9 3.86 7 4.60 0.64 3.48 1.39 3.73 1.47 7.421 0.000 Significant
FRMS12 3.77 8 4.58 0.70 3.46 1.45 3.49 1.36 6.452 0.000 Significant
FRMS15 3.76 9 4.55 0.68 3.45 1.42 3.28 1.44 0.004 0.732 Insignificant
FRMS17 3.73 10 4.50 0.78 3.43 1.40 3.27 1.37 6.463 0.000 Significant
FRMS19 3.72 11 4.47 0.77 3.43 1.46 3.27 1.39 8.432 0.000 Significant
FRMS20 3.72 12 4.46 0.78 3.43 1.44 3.27 1.43 14.657 0.000 Significant
FRMS22 3.69 13 4.45 0.74 3.36 1.43 3.27 1.39 9.224 0.000 Significant
FRMS23 3.66 14 4.41 0.84 3.35 0.72 3.25 1.43 5.711 0.000 Significant
FRMS10 3.53 15 4.06 1.29 3.31 1.44 3.23 1.38 6.963 0.000 Significant
FRMS11 3.47 16 3.90 1.42 3.31 1.46 3.23 1.45 0.043 0.472 Insignificant
FRMS13 3.47 17 3.90 1.43 3.3 1.36 3.21 1.42 1.156 0.149 Insignificant
FRMS14 3.45 18 3.88 1.38 3.29 1.33 3.20 0.34 6.432 0.000 Significant
FRMS16 3.41 19 3.78 1.44 3.28 1.40 3.19 1.38 5.82 0.000 Significant
FRMS18 3.39 20 3.73 1.40 3.28 1.45 3.18 0.34 11.345 0.000 Significant
FRMS21 3.32 21 3.38 0.08 3.27 1.44 3.15 1.38 8.562 0.000 Significant
FRMS6 3.26 22 2.59 1.39 2.87 0.23 2.81 1.47 0.015 0.532 Insignificant
FRMS8 3.12 23 2.56 1.42 2.44 1.43 2.64 0.03 16.421 0.000 Significant
Table 6. Results of the exploratory factor analysis.
Table 6. Results of the exploratory factor analysis.
S/N Principal groups of tde FRMS Factor loadings Eigenvalues VE CVE
FRMSG1 Sustainable funding for the project 5.162 30.134 30.134
FRMS2 Access to enough capital to support sustainable projects 0.934
FRMS4 Strategic green financing alliance 0.892
FRMS9 Strong financial support from the community towards eco-friendly projects. 0.871
FRMS5 Stabilisation of the macroeconomic indicators to foster sustainable projects 0.821
FRMS16 Risk-based tariff pricing to trigger sustained inflow of revenues and green finance 0.799
FRMS19 The presence of strong private consortium attracted enough funds for the project 0.757
FRMS21 Enough funding for recycling of construction wastes and carbon emissions 0.742
FRMS17 Social needs and concerns of project users included in toll charges. 0.721
FRMSG2 Cost reduction initiatives 2.656 21.551 51.685
FRMS1 Effective cost management strategies for sustainable and climate-friendly projects 0.907
FRMS12 Roll out consistent and effective financial monitoring controls 0.881
FRMS7 Adopting hedging strategies such as options, swaps, futures and forward 0.875
FRMS10 Thorough assessment of pre-construction stage fees and costs 0.841
FRMS22 Strong political support to investigate and manage misuse of project funds 0.802
FRMS20 Affordable insurance coverage to manage financial shocks 0.784
FRMS13 Carefully planned measures to cover financial uncertainties and climate crisis. 0.732
FRMSG3 Competent team with committed leadership 1.804 14.192 65.877
FRMS15 Clear and specific financial goals of the project are set from the start of the project 0.845
FRMS14 Resilient commitment from top management towards inclusive financial practices 0.817
FRMS11 Involve professional financial consultants in the financial valuation of the projects 0.783
FRMS6 Timely and independent audit review of project transactions 0.804
FRMS8 Timely financial reports supervised by a project committee 0.755
FRMSG4 Innovative technologies and regulations 1.019 9.082 74.959
FRMS23 Availability of comprehensive financial regulations 0.837
FRMS18 Promotion of innovative technologies for financial risk management 0.792
FRMS3 Sound corporate governance structures to meet economic sustainability targets. 0.763
Note: VE- Variance Explained, and CVE- Cumulative Variance Explained.
Table 7. Weightings of FRMS and FRMSG.
Table 7. Weightings of FRMS and FRMSG.
S/N Principal groups of FRMS Mean scores of FRMS Weightings of tde FRMS Mean score of FRMSG Weightings of FRMSG
FRMSG1 Sustainable funding for the project 32.300 0.362
FRMS2 Access to enough capital to support sustainable projects 4.73 0.146
FRMS4 Strategic green financing alliance 4.50 0.139
FRMS9 Strong financial support from the community towards eco-friendly projects. 4.11 0.127
FRMS5 Stabilisation of the macroeconomic indicators to foster sustainable projects 4.36 0.135
FRMS16 Risk-based tariff pricing to trigger sustained inflow of revenues and green finance 3.44 0.107
FRMS19 The presence of strong private consortium attracted enough funds for the project 3.95 0.122
FRMS21 Enough funding for recycling of construction wastes and carbon emissions 3.23 0.100
FRMS17 Social needs and concerns of project users included in toll charges. 3.98 0.123
FRMSG2 Cost reduction initiatives 27.910 0.313
FRMS1 Effective cost management strategies for sustainable and climate-friendly projects 4.84 0.173
FRMS12 Roll out consistent and effective financial monitoring controls 4.03 0.144
FRMS7 Adopting hedging strategies such as options, swaps, futures and forward 4.23 0.152
FRMS10 Thorough assessment of pre-construction stage fees and costs 3.58 0.128
FRMS22 Strong political support to investigate and manage misuse of project funds 3.84 0.138
FRMS20 Affordable insurance coverage to manage financial shocks 3.85 0.138
FRMS13 Carefully planned measures to cover financial uncertainties and climate crisis. 3.54 0.127
FRMSG3 Competent team with committed leadership 17.310 0.194
FRMS15 Clear and specific financial goals of the project are set from the start of the project 4.00 0.231
FRMS14 Resilient commitment from top management towards inclusive financial practices 3.49 0.202
FRMS11 Involve professional financial consultants in the financial valuation of the projects 3.56 0.206
FRMS6 Timely and independent audit review of project transactions 3.17 0.183
FRMS8 Timely financial reports supervised by a project committee 3.09 0.179
FRMSG4 Innovative technologies and regulations 11.760 0.132
FRMS23 Availability of comprehensive financial regulations 3.79 0.322
FRMS18 Promotion of innovative technologies for financial risk management 3.36 0.286
FRMS3 Sound corporate governance structures to meet economic sustainability targets. 4.61 0.392
Total 89.280
Table 8. Membership functions (MFs) of FRMS and FRMSG.
Table 8. Membership functions (MFs) of FRMS and FRMSG.
S/N Principal groupings on FRMS and FRMSG Weightings MF of FRMS (Level 3) MF of FRMSG (Level 2)
FRMSG1 Sustainable funding for the project (0.031, 0.097, 0.265, 0.374, 0.232)
FRMS2 Access to enough capital to support sustainable projects 0.146 (0.000, 0.010, 0.233, 05.44, 0.213)
FRMS4 Strategic green financing alliance 0.139 (0.024, 0.066, 0.307, 05.83, 0.220)
FRMS9 Strong financial support from the community towards eco-friendly projects. 0.127 (0.077, 0.118, 0.174, 05.31, 0.300)
FRMS5 Stabilisation of the macroeconomic indicators to foster sustainable projects 0.135 (0.017, 0.059, 0.282, 05.75, 0.366)
FRMS16 Risk-based tariff pricing to trigger sustained inflow of revenues and green finance 0.107 (0.031, 0.132, 0.314, 05.07, 0.216)
FRMS19 The presence of strong private consortium attracted enough funds for the project 0.122 (0.007, 0.195, 0.348, 05.18, 0.031)
FRMS21 Enough funding for recycling of construction wastes and carbon emissions 0.100 (0.035, 0.094, 0.105, 05.04, 0.362)
FRMS17 Social needs and concerns of project users included in toll charges. 0.123 (0.066, 0.129, 0.334, 05.07, 0.164)
FRMSG2 Cost reduction initiatives (0.023, 0.048, 0.208, 0.362, 0.359)
FRMS1 Effective cost management strategies for sustainable and climate-friendly projects 0.173 (0.014, 0.063, 0.589, 0.314, 0.021)
FRMS12 Roll out consistent and effective financial monitoring controls 0.144 (0.045, 0.059, 0.087, 0.418, 0.390)
FRMS7 Adopting hedging strategies such as options, swaps, futures and forward 0.152 (0.035, 0.052, 0.098, 0.348, 0.467)
FRMS10 Thorough assessment of pre-construction stage fees and costs 0.128 (0.010, 0.028, 0.157, 0.240, 0.564)
FRMS22 Strong political support to investigate and manage misuse of project funds 0.138 (0.007, 0.028, 0.070, 0.418, 0.477)
FRMS20 Affordable insurance coverage to manage financial shocks 0.138 (0.035, 0.066, 0.080, 0.418, 0.401)
FRMS13 Carefully planned measures to cover financial uncertainties and climate crisis. 0.127 (0.014, 0.035, 0.296, 0.383, 0.272)
FRMSG3 Competent team with committed leadership (0.020, 0.076, 0.131, 0.373, 0.400)
FRMS15 Clear and specific financial goals of the project are set from the start of the project 0.231 (0.049, 0.167, 0.199, 0.251, 0.334)
FRMS14 Resilient commitment from top management towards inclusive financial practices 0.202 (0.031, 0.045, 0.195, 0.310, 0.418)
FRMS11 Involve professional financial consultants in the financial valuation of the projects 0.206 (0.010, 0.031, 0.070, 0.679, 0.209)
FRMS6 Timely and independent audit review of project transactions 0.183 (0.000, 0.059, 0.105, 0.279, 0.557)
FRMS8 Timely financial reports supervised by a project committee 0.179 (0.000, 0.059, 0.070, 0.348, 0.523)
FRMSG4 Innovative technologies and regulations (0.013, 0.057, 0.143, 0.337, 0.450)
FRMS23 Availability of comprehensive financial regulations 0.322 (0.010, 0.042, 0.244, 0.348, 0.355)
FRMS18 Promotion of innovative technologies for financial risk management 0.286 (0.035, 0.094, 0.105, 0.453, 0.314)
FRMS3 Sound corporate governance structures to meet economic sustainability targets. 0.392 (0.000, 0.042, 0.087, 0.244, 0.627)
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.
Copyright: This open access article is published under a Creative Commons CC BY 4.0 license, which permit the free download, distribution, and reuse, provided that the author and preprint are cited in any reuse.

Downloads

269

Views

95

Comments

0

Subscription

Notify me about updates to this article or when a peer-reviewed version is published.

Email

Prerpints.org logo

Preprints.org is a free preprint server supported by MDPI in Basel, Switzerland.

Subscribe

© 2025 MDPI (Basel, Switzerland) unless otherwise stated