Abstract
Keywords:
1. Introduction
2. Literature Review
3. Research Method
4. Results and Discussion
4.1. Data Analysis and Results
4.1.1. Rangking of Critical Success Factors for Toll Road Infrastructure Financing Implementation in Indonesia
4.1.2. Identification of Critical Success Factors for Toll Road Infrastructure Financing Implementation in Indonesia
| Rank | Factors | RII | SD | MS |
|---|---|---|---|---|
| Investment Analysis | ||||
| 1 | IA3: Internal Rate of Return (IRR) | 0.96 | 0.48 | 5.79 |
| 1 | IA6: Good feasibility studies | 0.96 | 0.51 | 5.74 |
| 2 | IA5: Profitability to attract investors and lenders | 0.94 | 0.61 | 5.65 |
| Public-Sector Investment Decision | ||||
| 1 | PID3: Affordability | 0.88 | 0.74 | 5.31 |
| 2 | PID2: Economic Justification | 0.85 | 0.96 | 5.07 |
| The Private-Sector Investor’s Perspective | ||||
| 1 | PIP2: The Investment Decision | 0.92 | 0.63 | 5.53 |
| 2 | PIP1: The Investment Pool | 0.84 | 0.74 | 5.03 |
| Private-Sector Financing—Sources and Procedures | ||||
| 1 | FPSP1: Commercial Banks | 0.90 | 0.84 | 5.40 |
| 2 | FPSP3: Availability of financial market | 0.89 | 0.73 | 5.35 |
| Financial Structuring | ||||
| 1 | FS3: Financing Costs | 0.94 | 0.61 | 5.61 |
| 2 | FS1: The Financial Model | 0.93 | 0.63 | 5.59 |
| Financial Hedging | ||||
| 1 | FH1: Interest-Rate Risk | 0.94 | 0.63 | 5.64 |
| 2 | FH2: Inflation Issues | 0.91 | 0.73 | 5.46 |
| Lenders’ Cash-Flow Controls, Security and Enforcement | ||||
| 1 | LCSE1: Control of Cash Flow | 0.95 | 0.57 | 5.69 |
| 2 | LCSE2: Security | 0.93 | 0.65 | 5.56 |
| Service-Fee Mechanism | ||||
| 1 | SFM1: Contract Scope | 0.94 | 0.60 | 5.65 |
| 1 | SFM2: Payment & Scheme Structure | 0.94 | 0.60 | 5.65 |
| 2 | SFM3: Third-Party and Secondary Revenues | 0.84 | 0.89 | 5.03 |
| Risk Evaluation and Transfer | ||||
| 1 | RET1: Principles of Risk Transfer | 0.91 | 0.65 | 5.47 |
| 1 | RET2: Political Risks | 0.91 | 0.74 | 5.45 |
| 1 | RET4: Completion Risks | 0.91 | 0.75 | 5.43 |
| 2 | RET5: Operation-Phase Risks | 0.90 | 0.73 | 5.39 |
4.2. Internal Rate of Return
4.3. Affordability
4.4. The Investment Decision
4.5. Commercial Banks
4.6. Financing Costs
4.7. Interest Rate Risk
4.8. Control of Cash Flow
4.9. Contract Scope
4.10. Risk Evaluation and Transfer
4.11. Implications for Future Researches and Managerial Practices
5. Conclusions
References
- Alcaraz Carrillo de Albornoz, V.; Sánchez Soliño, A.; Lara Galera, A.; Isabel Álvarez, J.M. Bankrupt PPPs: Is it really so bad? Case study of R-3 and R-5 toll motorways in Spain. Transport Policy 2021, 114, 78–87. [Google Scholar] [CrossRef]
- Almarri, K.; Boussabaine, H. The Influence of Critical Success Factors on Value for Money Viability Analysis in Public–Private Partnership Projects. Project Management Journal 2017, 48, 93–106. [Google Scholar] [CrossRef]
- Amberg, M. Background of Critical Success Factor Research; 2005. [Google Scholar]
- Ameyaw, C.; Adjei-Kumi, T.; Owusu-Manu, D.-G. Exploring value for money (VfM) assessment methods of public-private partnership projects in Ghana. Journal of Financial Management of Property and Construction 2015, 20, 268–285. [Google Scholar] [CrossRef]
- Ashuri, B.; Kashani, H.; Molenaar, K.; Lee, S. A Valuation Model for Choosing the Optimal Minimum Revenue Guarantee (MRG) in a Highway Project: A Real-Option Approach; 2010. [Google Scholar] [CrossRef]
- Bing, L.; Akintoye, A.; Edwards, P.J.; Hardcastle, C. The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management 2005, 23, 25–35. [Google Scholar] [CrossRef]
- Boeing Singh, L.; Kalidindi, S.N. Traffic revenue risk management through Annuity Model of PPP road projects in India. International Journal of Project Management 2006, 24, 605–613. [Google Scholar] [CrossRef]
- Brealey, R.A.; Myers, S.C.; Allen, F. Principles of Corporate Finance, 10th ed.; McGraw-Hill, 2011. [Google Scholar]
- Brigham, E.F.; Ehrhardt, M.C. Financial Management: Theory & Practice, 15th ed.; Cengage Learning, 2016. [Google Scholar]
- Bringham, E.; Houston, J.F. Essentials of Financial Management, 14th ed.; Cengage Learning, 2018. [Google Scholar]
- Chen, B. Optimal capital structure of government-subsidized private participation in infrastructure projects. The Engineering Economist 2020, 65, 321–338. [Google Scholar] [CrossRef]
- Chen, B.; Mao, C.-K.; Hu, J.-L. The optimal debt ratio of public–private partnership projects. International Journal of Construction Management 2015, 15, 239–253. [Google Scholar] [CrossRef]
- Chou, J.-S.; Ping Tserng, H.; Lin, C.; Yeh, C.-P. Critical factors and risk allocation for PPP policy: Comparison between HSR and general infrastructure projects. Transport Policy 2012, 22, 36–48. [Google Scholar] [CrossRef]
- Chou, J.-S.; Pramudawardhani, D. Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. International Journal of Project Management 2015, 33, 1136–1150. [Google Scholar] [CrossRef]
- Dulaimi, M.F.; Alhashemi, M.; Ling, F.Y.Y.; Kumaraswamy, M. The execution of public–private partnership projects in the UAE. Construction Management and Economics 2010, 28, 393–402. [Google Scholar] [CrossRef]
- El-Sayegh, S.M.; Mansour, M.H. Risk Assessment and Allocation in Highway Construction Projects in the UAE. Journal of Management in Engineering 2015, 31. [Google Scholar] [CrossRef]
- Enshassi, A.; Choudhry, R.; Mayer, P.; Younis, S. Safety performance of subcontractors in the Palestinian construction industry. Journal of Construction in Developing Countries 2008, 13. [Google Scholar]
- Cheung, E.; Chan, A.P. Risk Factors of Public-Private Partnership Projects in China: Comparison between the Water, Power, and Transportation Sectors. Journal of Urban Planning and Development 2011, 137, 409–415. [Google Scholar] [CrossRef]
- Esty, B.C. Why Study Large Projects? An Introduction to Research on Project Finance. European Financial Management 2004, 10, 213–224. [Google Scholar] [CrossRef]
- Fabozzi, F.J.; Nahlik, C. Project Financing, 8th ed.; Euromoney, 2012. [Google Scholar]
- Gatti, S. Project finance in theory and practice: designing, structuring, and financing private and public projects; Elsevier, 2023. [Google Scholar]
- Gholamreza, H.; Zeinab, H. Risk Allocation in Public–Private Partnership Infrastructure Projects in Developing Countries: Case Study of the Tehran–Chalus Toll Road. Journal of Infrastructure Systems 2012, 18, 210–217. [Google Scholar] [CrossRef]
- Gitman, L.J.; Zutter, C.J. Principles of Managerial Finance, 14th ed.; Pearson, 2015. [Google Scholar]
- Gupta, A.; Chandra Gupta, M.; Agrawal, R. Identification and ranking of critical success factors for BOT projects in India. Management Research Review 2013, 36, 1040–1060. [Google Scholar] [CrossRef]
- Gwilliam, K. Africa’s Transport Infrastructure; The World Bank, 2011. [Google Scholar] [CrossRef]
- Hallowell, M.R.; Gambatese, J.A. Activity-Based Safety Risk Quantification for Concrete Formwork Construction. Journal of Construction Engineering and Management 2009, 135, 990–998. [Google Scholar] [CrossRef]
- Hoppe, E.I.; Schmitz, P.W. Public-private partnerships versus traditional procurement: Innovation incentives and information gathering. The RAND Journal of Economics 2013, 44, 56–74. [Google Scholar] [CrossRef]
- Hwang, B.-G.; Lim, E.-S. Critical Success Factors for Key Project Players and Objectives: Case Study of Singapore. Journal of Construction Engineering and Management 2013, 139, 204–215. [Google Scholar] [CrossRef]
- Hwang, B.-G.; Zhao, X.; Gay, M.J.S. Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management 2013, 31, 424–433. [Google Scholar] [CrossRef]
- Ismail, S. Critical success factors of public private partnership (PPP) implementation in Malaysia. Asia-Pacific Journal of Business Administration 2013, 5, 6–19. [Google Scholar] [CrossRef]
- Jacobson, C.; Choi, S. Success factors: Public works and public-private partnerships. International Journal of Public Sector Management. 2008, 21, 637–657. [Google Scholar] [CrossRef]
- Jayasena, N.; Chan, D.D.; Kumaraswamy, M. A systematic literature review and analysis towards developing PPP models for delivering smart infrastructure. Built Environment Project and Asset Management 2020. ahead-of-print. [Google Scholar] [CrossRef]
- Jefferies, M. Critical Success Factors of Public Private Sector Partnerships: A Case Study of the Sydney SuperDome. Engineering, Construction and Architectural Management 2006, 13, 451–462. [Google Scholar] [CrossRef]
- Ke, F.; Wei, X.; Shouqing, W.; Chunlin, W.; Yanguang, X. Optimizing an Equity Capital Structure Model for Public–Private Partnership Projects Involved with Public Funds. Journal of Construction Engineering and Management 2017, 143, 04017067. [Google Scholar] [CrossRef]
- Ke, Y.; Wang, S.; Chan, A.P.C.; Lam, P.T.I. Preferred risk allocation in China’s public–private partnership (PPP) projects. International Journal of Project Management 2010, 28, 482–492. [Google Scholar] [CrossRef]
- Ke, Y.; Wang, S.Q.; Chan, A. Risk Allocation in Public-Private Partnership Infrastructure Projects: A Comparative Study. Journal of Infrastructure Systems 2010, 16, 343–351. [Google Scholar] [CrossRef]
- Kurniawati, E.; Sugiyanto, C. Pengaruh Struktur Umur Penduduk terhadap Pertumbuhan Ekonomi di Indonesia. Jurnal Ekonomi Dan Pembangunan Indonesia 2021, 21, 41–58. [Google Scholar] [CrossRef]
- Leidecker, J.K.; Bruno, A.V. Identifying and using critical success factors. Long Range Planning 1984, 17, 23–32. [Google Scholar] [CrossRef]
- Liu, H.; Song, S.; Hu, Y.; Yan, X. Monte-Carlo optimization model for dynamic capital structure adjustment in Chinese public-private partnerships under revenue uncertainty. Transportation Research Part A: Policy and Practice 2020, 142, 115–128. [Google Scholar] [CrossRef]
- Liu, J.; Love, P.E.D.; Smith, J.; Regan, M.; Davis, P.R. Life Cycle Critical Success Factors for Public-Private Partnership Infrastructure Projects. Journal of Management in Engineering 2015, 31. [Google Scholar] [CrossRef]
- Liu, T.; Mostafa, S.; Mohamed, S.; Nguyen, T.S. Emerging themes of public-private partnership application in developing smart city projects: a conceptual framework. Built Environment Project and Asset Management 2021, 11, 138–156. [Google Scholar] [CrossRef]
- Maghsoodi, A.I.; Khalilzadeh, M. Identification and Evaluation of Construction Projects’ Critical Success Factors Employing Fuzzy-TOPSIS Approach. KSCE Journal of Civil Engineering 2018, 22, 1593–1605. [Google Scholar] [CrossRef]
- Malek, M.; Gundaliya, P. Value for money factors in Indian public-private partnership road projects: An exploratory approach. Journal of Project Management 2021, 23–32. [Google Scholar] [CrossRef]
- Nevitt, P.K.; Fabozzi, F.Z. Project Financing; Euromoney Books, 2000. [Google Scholar]
- Park, S.H. Whole Life Performance Assessment: Critical Success Factors. Journal of Construction Engineering and Management 2009, 135, 1146–1161. [Google Scholar] [CrossRef]
- PwC. The Long View How Will The Global Economic Order Change by 2050? 2017. [Google Scholar]
- Rockart, J.F. The Changing Role of the Information Systems Executive: A Critical Success Factors Perspective. Sloan Management Review 1982, 24, 3–13. [Google Scholar]
- Bakatjan, S.; Arikan, M.; Tiong, R.L. Optimal Capital Structure Model for BOT Power Projects in Turkey. Journal of Construction Engineering and Management 2003, 129, 89–97. [Google Scholar] [CrossRef]
- Schwab, K.; Sala-i-Martin, X. The Global Competitiveness Report 2017–2018; World Economic Forum, 2017. [Google Scholar]
- Shapiro, A.; Dentcheva, D.; Ruszczynki, A. Lectures on Stochastic Programming Modeling and Theory; Society for Industrial and Applied Mathematics, 2009. [Google Scholar]
- Sharma, D.K.; Cui, Q.; Chen, L.; Lindly, J.K. Balancing Private and Public Interests in Public–Private Partnership Contracts through Optimization of Equity Capital Structure. Transportation Research Record 2010, 2151, 60–66. [Google Scholar] [CrossRef]
- Tang, L.; Shen, G.; Skitmore, M.; Cheng, E.W.L. Ranked Critical Factors in PPP Briefings. Journal of Management in Engineering 2012, 29, 164–171. [Google Scholar] [CrossRef]
- Vassallo, J.M.; Baeza, M.d.l.Á.; Ortega, A. What was wrong with the toll highway concessions in the Madrid Metropolitan Area? Canadian Journal of Civil Engineering 2012, 39, 81–90. [Google Scholar] [CrossRef]
- Verhoef, P.C.; Langerak, F.; Donkers, B. Understanding brand and dealer retention in the new car market: The moderating role of brand tier. Journal of Retailing 2007, 83, 97–113. [Google Scholar] [CrossRef]
- Vining, A.R.; Boardman, A.E. Public-private partnerships in Canada: Theory and evidence. Canadian Public Administration/Administration Publique Du Canada 2008, 51, 9–44. [Google Scholar] [CrossRef]
- von der Gracht, H.A. Consensus measurement in Delphi studies. Technological Forecasting and Social Change 2012, 79, 1525–1536. [Google Scholar] [CrossRef]
- Wang, W.-X.; Li, Q.-M.; Deng, X.-P.; Li, J.-H. Critical Success Factors of Infrastructure Projects under PPP Model in China. In Proceedings of the 2007 International Conference on Wireless Communications, Networking and Mobile Computing; 2007; pp. 4970–4974. [Google Scholar] [CrossRef]
- Warner, M.E. Private finance for public goods: social impact bonds. Journal of Economic Policy Reform 2013, 16, 303–319. [Google Scholar] [CrossRef]
- Wibowo, A.; Alfen, H.W. Government-led critical success factors in PPP infrastructure development. Built Environment Project and Asset Management 2015, 5, 121–134. [Google Scholar] [CrossRef]
- Xiao-Hua, J. Determinants of Efficient Risk Allocation in Privately Financed Public Infrastructure Projects in Australia. Journal of Construction Engineering and Management 2010, 136, 138–150. [Google Scholar] [CrossRef]
- Xu, Y.; Yeung, J.F.Y.; Chan, A.P.C.; Chan, D.W.M.; Wang, S.Q.; Ke, Y. Developing a risk assessment model for PPP projects in China — A fuzzy synthetic evaluation approach. Automation in Construction 2010, 19, 929–943. [Google Scholar] [CrossRef]
- Yu, Y.; Chan, A.P.; Chen, C.; Darko, A. Critical Risk Factors of Transnational Public–Private Partnership Projects: Literature Review. Journal of Infrastructure Systems 2018, 24, 04017042. [Google Scholar] [CrossRef]
- Yescombe, E.R.; Farquaharson, E. Public-Private Partnerships for Infrastructure, 2nd ed.; Elsevier, 2018. [Google Scholar] [CrossRef]
- Zala, P.; Vel, R. Evaluation of PPP projects in India: the case of power transmission lines. International Journal of Mechanical and Production Engineering Research and Development 2019, 9, 357–364. [Google Scholar]
- Zhang, X. Financial Viability Analysis and Capital Structure Optimization in Privatized Public Infrastructure Projects. Journal of Construction Engineering and Management-Asce 2005, 131. [Google Scholar] [CrossRef]
| Code | Factors | References |
|---|---|---|
| Investment Analysis | ||
| IA1 | Net Present Value (NPV) | Zala & Vel (2019); Ameyaw et al. (2015); Ashuri et al. (2010) |
| IA2 | Discounted Cash Flow (DCF) | Albornoz et al. (2021); Warner (2013); Vassallo et al. (2012) |
| IA3 | Internal Rate of Return (IRR) | Albornoz et al. (2021); Vassallo et al. (2012) |
| IA4 | Payback Period | Albornoz et al. (2021); Vassallo et al. (2012) |
| IA5 | Profitability to attract investors and lenders | Chou & Pramudawardhani (2015); Gupta et al. (2013) |
| IA6 | Good feasibility studies | Chou & Pramudawardhani (2015); Gupta et al. (2013); Dulaimi et al. (2010); Jefferies (2006) |
| Public-sector investment decision | ||
| PID1 | Business Diversification | Almarri & Boussabaine (2017) |
| PID2 | Economic Justification | Jayasena et al. (2020); Yescombe & Farquaharson (2018) |
| PID3 | Affordability | Yescombe & Farquaharson (2018); Jacobson & Choi (2008); Olusola Babatunde et al. (2012) |
| The Private-Sector Investor’s Perspective | ||
| PIP1 | The Investment Pool | Tang et al. (2012); Wang et al. (2007) |
| PIP2 | The Investment Decision | Yescombe & Farquaharson (2018); Jefferies (2006) |
| PIP3 | Joint-Venture Issues | Yescombe & Farquaharson (2018); Jefferies (2006); Bing et al. (2005); Zhang (2005) |
| Private-Sector Financing—Sources and Procedures | ||
| FPSP1 | Commercial Banks | Ameyaw & Chan (2016); Hwang & Lim (2013); Xu et al. (2010) |
| FPSP2 | Bond Issues | Ameyaw et al. (2015); Hwang et al. (2013); Xu et al. (2010) |
| FPSP3 | Availability of financial markets | Liu et al. (2021); Malek & Gundaliya (2021); Lam & Yang (2020); Wang, & Chan (2010) |
| Financial Structuring | ||
| FS1 | The Financial Model | Yao et al. (2018); Yescombe & Farquaharson (2018); Regan (2012) |
| FS2 | Model Inputs and Outputs | Yescombe & Farquaharson (2018); Ameyaw & Chan (2016) |
| FS3 | Financing Costs | Yescombe & Farquaharson (2018); Ismail (2013) |
| FS4 | Debt Profile | Yescombe & Farquaharson (2018); Ismail (2013) |
| Financial Hedging | ||
| FH1 | Interest-Rate Risk | Esther & C (2011); Gholamreza & Zeinab (2012); |
| FH2 | Inflation Issues | Gholamreza & Zeinab (2012); Esther & C (2011); Jie & W (2011); Xu et al. (2010); Singh & Kalidindi (2006) |
| FH3 | Exchange Risk | Chou et al. (2012); Esther & C (2011); Wang, & Chan (2010); Xu et al. (2010) |
| Lenders’ Cash-Flow Controls, Security and Enforcement | ||
| LCSE1 | Control of Cash Flow | Yescombe & Farquaharson (2018); Liu et al. (2020) |
| LCSE2 | Security | Liu et al. (2020); Yescombe & Farquaharson (2018) |
| LCSE3 | Intercreditor issues | Liu et al. (2020); Yescombe & Farquaharson (2018) |
| Service-Fee Mechanism | ||
| SFM1 | Contract Scope | Chou & Pramudawardhani (2015); Hwang & Lim (2013); Xu et al. (2010) |
| SFM2 | Payment & Scheme Structure | Chou et al. (2012); Esther & C (2011); Wang, & Chan (2010); Xu et al. (2010) |
| SFM3 | Third-Party and Secondary Revenues | Yescombe & Farquaharson (2018) |
| Risk Evaluation and Transfer | ||
| RET1 | Principles of Risk Transfer | Chou & Pramudawardhani, (2015); Hwang & Lim (2013); Bing et al. (2005) |
| RET2 | Political Risks | Jefferies (2006); Zhang (2005) |
| RET3 | Construction Risks | Bing et al. (2005) Xiao-Hua (2010) Wang, & Chan (2010) Xu et al. (2010) Hwang & Lim (2013) |
| RET4 | Completion Risks | Hwang & Lim (2013); Chou et al. (2012); Wang et al. (2010); Xiao-Hua (2010); Bing et al. (2005) |
| RET5 | Operation-Phase Risks | Hwang et al. (2013); Chou et al. (2012); Gholamreza & Zeinab (2012); Esther & C (2011); Wang, & Chan (2010); Bing et al. (2005) |
| Question Item | Type | Frequency | Percentage (%) |
|---|---|---|---|
| Field of expertise | Engineering | 27 | 28 |
| Financial | 56 | 59 | |
| Facility management | 9 | 9 | |
| Others | 3 | 3 | |
| Position PPP project experience |
Management | 43 | 45 |
| Undertaker | 39 | 41 | |
| Others | 13 | 14 | |
| Less than 6 years | 12 | 13 | |
| Position | 6-15 years | 29 | 31 |
| 16-30 years | 31 | 33 | |
| More than 30 years | 23 | 24 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |