Submitted:
30 August 2023
Posted:
01 September 2023
You are already at the latest version
Abstract
Keywords:
1. Introduction
2. State of knowledge
3. Project Schedule Management

4. Project Cost Management

5. Project Risk Management

6. Methods
7. Results
7.1. Artificial Intelligence and the Impact on Project Schedule Management
7.2. Artificial Intelligence and the Impact on Project Cost Management
7.3. Artificial Intelligence and the Impact on Project Risk Management
8. Artificial Intelligence and the Impact on the Three Knowledge areas
9. Discussions and conclusion
Appendix A
| Project management knowledge areas | Answer options | |||||
|---|---|---|---|---|---|---|
| Statements | Very much | Significantly | Moderate | Insignificantly | Very little | Don’t know |
| Project schedule management | ||||||
| AI will affect the development of the project charter | ||||||
| AI will affect the scope management plan and development approach when planning schedule | ||||||
| AI will affect enterprise environmental factors when planning schedules | ||||||
| AI will affect the schedule management plan and scope baseline when defining, sequencing and estimating activities | ||||||
| AI will affect duration estimating databases, productivity metrics and location of team members | ||||||
| AI will affect the schedule baseline | ||||||
| AI will affect the performance measurement baseline | ||||||
| AI will affect the work performance data | ||||||
| Project cost management | ||||||
| AI will affect the financial resources when planning costs | ||||||
| AI will affect the reaction to enterprise environmental factors when planning costs | ||||||
| AI will affect the financial controls procedures | ||||||
| AI will affect the cost management estimates | ||||||
| AI will affect the estimation of resource cost based on market conditions, resource cost rates, exchange rates and inflation | ||||||
| AI will affect the determination of budget based on cost- and resource management plan | ||||||
| AI will affect the monitoring and reporting methods of the variance of the cost baseline | ||||||
| AI will affect cost negotiation and contracting | ||||||
| AI will affect cost awareness | ||||||
| AI will affect cost types in projects | ||||||
| Project risk management | ||||||
| AI will affect the development of the risk management plan | ||||||
| AI will affect the determination of roles and responsibilities for managing risk | ||||||
| AI will affect the setting of risk thresholds for a project | ||||||
| AI will affect risk breakdown structures (RBS) | ||||||
| AI will affect the information/lessons learned repository from previous similar projects | ||||||
| AI will affect the identification of project objectives that are at risk | ||||||
| AI will affect the identification of areas subject to uncertainty | ||||||
| AI will affect the budgeting for risk management | ||||||
| AI will affect the identification of costs subject to risk or uncertainty | ||||||
| AI will affect the probability and impact matrix | ||||||
| AI will affect risk identification techniques | ||||||
| AI will affect the mitigation of risk | ||||||
Appendix B
| Project management knowledge areas | Answer options | |||||
|---|---|---|---|---|---|---|
| Statements | Very much | Significantly | Moderate | Insignificantly | Very little | Don’t know |
| Project schedule management | ||||||
| AI will affect the development of the project charter | 8% | 25% | 33% | 33% | 0% | 0% |
| AI will affect the scope management plan and development approach when planning schedule | 25% | 33% | 25% | 17% | 0% | 0% |
| AI will affect enterprise environmental factors when planning schedules | 8% | 75% | 17% | 0% | 0% | 0% |
| AI will affect the schedule management plan and scope baseline when defining, sequencing and estimating activities | 17% | 58% | 25% | 0% | 0% | 0% |
| AI will affect duration estimating databases, productivity metrics and location of team members | 25% | 33% | 42% | 0% | 0% | 0% |
| AI will affect the schedule baseline | 50% | 33% | 17% | 0% | 0% | 0% |
| AI will affect the performance measurement baseline | 8% | 42& | 33% | 17% | 0% | 0% |
| AI will affect the work performance data | 17% | 25% | 25% | 33% | 0% | 0% |
| Project cost management | ||||||
| AI will affect the financial resources when planning costs | 17% | 17% | 67% | 0% | 0% | 0% |
| AI will affect the reaction to enterprise environmental factors when planning costs | 17% | 42% | 17% | 25% | 0% | 0% |
| AI will affect the financial controls procedures | 17% | 58% | 17% | 0% | 0% | 8% |
| AI will affect the cost management estimates | 33% | 58% | 8% | 0% | 0% | 0% |
| AI will affect the estimation of resource cost based on market conditions, resource cost rates, exchange rates and inflation | 33% | 58% | 8% | 0% | 0% | 0% |
| AI will affect the determination of budget based on cost- and resource management plan | 8% | 33% | 58% | 0% | 0% | 0% |
| AI will affect the monitoring and reporting methods of the variance of the cost baseline | 33% | 42% | 8% | 17% | 0% | 0% |
| AI will affect cost negotiation and contracting | 0% | 0% | 25% | 50% | 25% | 0% |
| AI will affect cost awareness | 33% | 8% | 50% | 8% | 0% | 0% |
| AI will affect cost types in projects | 0% | 17% | 25% | 50% | 0% | 8% |
| Project risk management | ||||||
| AI will affect the development of the risk management plan | 25% | 58% | 8% | 8% | 0% | 0% |
| AI will affect the determination of roles and responsibilities for managing risk | 0% | 17% | 50% | 17% | 17% | 0% |
| AI will affect the setting of risk thresholds for a project | 8% | 75% | 8% | 0% | 0% | 8% |
| AI will affect risk breakdown structures (RBS) | 17% | 33% | 42% | 8% | 0% | 0% |
| AI will affect the information/lessons learned repository from previous similar projects | 33% | 25% | 33% | 0% | 8% | 0% |
| AI will affect the identification of project objectives that are at risk | 0% | 42% | 58% | 0% | 0% | 0% |
| AI will affect the identification of areas subject to uncertainty | 8% | 50% | 33% | 8% | 0% | 0% |
| AI will affect the budgeting for risk management | 17% | 17% | 58% | 8% | 0% | 0% |
| AI will affect the identification of costs subject to risk or uncertainty | 25% | 42% | 33% | 0% | 0% | 0% |
| AI will affect the probability and impact matrix | 8% | 83% | 8% | 0% | 0% | 0% |
| AI will affect risk identification techniques | 0% | 25% | 50% | 17% | 0% | 8% |
| AI will affect the mitigation of risk | 0% | 58% | 25% | 17% | 0% | 0% |
References
- W. N. Hosley, “The application of artificial intelligence software to project management,” Proj. Manag. J., vol. 18, no. 3, pp. 73–75, 1987, [Online]. Available: https://www.pmi.org/learning/library/application-artificial-intelligence-software-pm-5234.
- G. Auth, O. Jokisch, and C. Dürk, “Revisiting automated project management in the digital age – a survey of AI approaches,” Online J. Appl. Knowl. Manag., vol. 7, no. 1, pp. 27–39, May 2019. https://doi.org/10.36965/OJAKM.2019.7(1)27-39. [CrossRef]
- V. Kolbjørnsrud, R. Amico, and R. J. Thomas, “How Artificial Intelligence Will Redefine Management,” 2016.
- T. V. Fridgeirsson, H. T. Ingason, H. I. Jonasson, and H. Jonsdottir, “An Authoritative Study on the Near Future Effect of Artificial Intelligence on Project Management Knowledge Areas,” Sustainability, vol. 13, no. 4, p. 2345, Feb. 2021. https://doi.org/10.3390/su13042345. [CrossRef]
- “What is Project Management | PMI.” https://www.pmi.org/about/learn-about-pmi/what-is-project-management (accessed May 09, 2021).
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed. USA: Project Management Institute, Inc., 2021).
- [19] PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th ed. USA: Project Management Institute, Inc., 2017.
- N. J. Nilsson, “THE QUEST FOR ARTIFICIAL INTELLIGENCE A HISTORY OF IDEAS AND ACHIEVEMENTS,” 2009. Accessed: May 09, 2021. [Online]. Available: http://www.cambridge.org/us/0521122937http://www.cambridge.org/us/0521122937http://www.cambridge.org/us/0521122937.
- S. Raisch and S. Krakowski, “Artificial Intelligence and Management: The Automation–Augmentation Paradox,” Acad. Manag. Rev., vol. 46, no. 1, pp. 192–210, Jan. 2021. https://doi.org/10.5465/amr.2018.0072. [CrossRef]
- A. Morad and M. C. Vorster, “Network-based versus AI-based techniques in project planning,” Proj. Manag. J., vol. 24, no. 1, pp. 23–30, 36, 1993, [Online]. Available: https://www.pmi.org/learning/library/artificial-intelligence-based-techniques-problem-solving-2109.
- M. Wauters and M. Vanhoucke, “A comparative study of Artificial Intelligence methods for project duration forecasting,” Expert Syst. Appl., vol. 46, pp. 249–261, Mar. 2016. https://doi.org/10.1016/j.eswa.2015.10.008. [CrossRef]
- H. F. Þorsteinsson, G. Jónsson, R. H. Magnúsdóttir, L. D. Jónsdóttir, and K. R. Þórisson, “Ísland og fjórða iðnbyltingin,” 2019. [Online]. Available: https://www.stjornarradid.is/library/04-Raduneytin/ForsAetisraduneytid/Framtidarnefnd/Fjorda-idnbyltingin-skyrsla.pdf.
- M.-Y. Cheng, H.-C. Tsai, and C.-L. Liu, “Artificial intelligence approaches to achieve strategic control over project cash flows,” Autom. Constr., vol. 18, no. 4, pp. 386–393, Jul. 2009. https://doi.org/10.1016/j.autcon.2008.10.005. [CrossRef]
- 14. M. Leyer and S. Schneider, “Decision augmentation and automation with artificial intelligence: Threat or opportunity for managers?,” Bus. Horiz., Feb. 2021. https://doi.org/10.1016/j.bushor.2021.02.026. [CrossRef]
- R. Schmelzer, “AI In Project Management,” Forbes, 2019. https://www.forbes.com/sites/cognitiveworld/2019/07/30/ai-in-project-management/?sh=45227249b4a0 (accessed May 09, 2021).
- C. Robson, Real World Research: A Resource for Users of Social Research Methods in Applied Settings, 3rd ed. United Kingdom: John Wiley & Sons Ltd, 2011.



| Respondent # | Background |
|---|---|
| 1 | Ph.D. in engineering. MPM instructor with good background in PM. Self-employed engineer. |
| 2 | MPM degree and IPMA level C certification. Experienced project manager with software background. Project manager at a large IT company. |
| 3 | MPM degree and IPMA level B certification. Experienced project manager with software background and experience in managing software projects. Project manager at a large IT company. |
| 4 | Ph.D. in computer science with good background in AI. Associate professor at Reykjavík University. |
| 5 | PM and leadership training. IPMA level B certification. Project manager at a large food processing company. |
| 6 | MPM degree and IPMA level B certification. Project manager at a construction contracting agency. |
| 7 | Ph.D. in computer science with a good background in AI. Professor at Reykjavík University. |
| 8 | MPM degree and IPMA level B certification. Experienced project manager with software background and experience in managing software projects. Project manager at a telecommunication company. |
| 9 | MPM degree and IPMA level B certification. Engineer at an engineering consultant company. |
| 10 | MPM degree and IPMA level C certification. Project manager at a large health technology company. |
| 11 | M.Sc. in computer science. Has good background in AI. Adjunct professor at Reykjavík University. |
| 12 | Ph.D. in signal processing. Has good background in AI. Associate professor at Reykjavík University. |
| Very much | Significantly | Moderate | Insignificantly | Very little | Don’t know | |
|---|---|---|---|---|---|---|
| Project Schedule Management | 20% | 41% | 27% | 13% | 0% | 0% |
| Project Cost Management | 19% | 33% | 28% | 15% | 3% | 2% |
| Project Risk Management | 12% | 44% | 34% | 7% | 2% | 1% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).