Construction Waste Audit in the Framework of Sustainable Waste Management in Construction Projects - Case Study

Version 1 : Received: 10 December 2020 / Approved: 11 December 2020 / Online: 11 December 2020 (16:20:49 CET)

A peer-reviewed article of this Preprint also exists.

Spišáková, M.; Mésároš, P.; Mandičák, T. Construction Waste Audit in the Framework of Sustainable Waste Management in Construction Projects—Case Study. Buildings 2021, 11, 61. Spišáková, M.; Mésároš, P.; Mandičák, T. Construction Waste Audit in the Framework of Sustainable Waste Management in Construction Projects—Case Study. Buildings 2021, 11, 61.

Abstract

The issue of sustainability has long been the subject of interest of the architecture engineering and construction sector. All three aspects of sustainability - economic, environmental and social - can be affected through appropriate construction waste management. Construction and demolition waste (CDW) is one of the largest worldwide waste streams, therefore it is given great attention by all stakeholders (investors, contractors, authorities, etc.). Researches have shown that one of the main barriers to insufficiency CDW recovery is inadequate policies and legal frameworks to manage CDW. It is also one of the EU's environmental priorities. Aim of the article is to confirm the economic potential of construction and demolition waste audit processing through case study. A pre-demolition waste audit has been processed for unused building of shopping center in the town Snina in Slovakia. Subsequently, a comparison of economic parameters (waste disposal costs and transport costs) of recommended CDW management was performed. This comparison confirmed the economic benefits of environmentally friendly construction waste management methods according to the waste audit results, which will also increase the sustainability of construction projects. In addition, the cost parameters of selected waste disposal methods could be another dimension of building information modelling.

Keywords

construction and demolition waste; renovation; demolition; waste disposal; pre-renovation audit; waste audit; construction; comparison; costs

Subject

Engineering, Automotive Engineering

Comments (0)

We encourage comments and feedback from a broad range of readers. See criteria for comments and our Diversity statement.

Leave a public comment
Send a private comment to the author(s)
* All users must log in before leaving a comment
Views 0
Downloads 0
Comments 0
Metrics 0


×
Alerts
Notify me about updates to this article or when a peer-reviewed version is published.
We use cookies on our website to ensure you get the best experience.
Read more about our cookies here.